Siderian
a stylized model · 2025 dollars
200 reactors at 114 USD/MWh in 23.6 years if the vessel line holds 12 a year and the targets are met; about 146 USD/MWh in the middle of the range; 181 USD/MWh in 42.2 years in the cautious case, with every uncertain input at its unfavourable end.
target case
114
USD/MWh
cautious case
181
USD/MWh
Average cost of electricity per unit at a 7% cost of money, under the model’s assumptions. The band is a spread from the stated ranges, not a probability.
- at other costs of money, target–cautious
- 3%72–111 USD/MWh5%91–142 USD/MWh7%114–181 USD/MWh10%155–257 USD/MWh
- overnight cost
- 7,360 USD/kW10,280 USD/kW
- years to unit 200
- 23.6 years42.2 years
- Progreso in use
- 68%30%
The problem
Given 200 reactors, 200 ready sites and one vessel line, the model chooses where every piece of work is done so that its electricity costs the least.
Given
- S200 unitsD of 1,117 MWD, one on each of 200 ready sites
- Severy site 15 days by sea from Progreso
- Vone dedicated vessel line at Doosan: 12 or 6 vessels a yearT
- Va vendor that sells a complete assembly delivers it complete, to Progreso or straight to the site; every critical part has its own line
- PProgreso assembles, fits out and tests; it does not forge, roll or cast
Chosen by the model
- PSwhere each package of work is done: on site or at Progreso
- Phow far it is finished before it ships: bare, fitted out, or fitted out and tested
- PSthe size of each piece: sub pieces joined on site, or one complete lift
- Probot cell or manual station, for each family of tasks
- Pwhich factory test halls are built
- Pthe stations and shifts of each bay
- Pthe ships of each class
- Pthe buffer of finished modules at the quay
- PSthe route of each vendor part: straight to the site, or through Progreso first
- Sthe ground work: one standard design, or one for each site
- Show far ahead of its reactor vessel each site starts
The goal
The lowest cost of electricity, with as little labor as possible, above all on site.
The rules
- SWestinghouse’s design, module list, lift order and build sequence, unchanged
- Sholds that no labor can shorten: curing, weld inspection, pressure and leak tests, the hot test, inspection before fuel
- Pevery shipped piece within its ship and the crane of the site
- Pno bay over its capacity in any month
- Vnever more units at power than vessels delivered
DdocumentedVderivedJjudgedTtargetVvendorPProgresoSsite
Data table
| Item | Value |
|---|---|
| Units, and sites | 200 |
| Net output of a unit | 1,117 MW |
| From Progreso to every site, by sea | 15 days |
| Vessels a year, target case | 12 |
| Vessels a year, cautious case | 6 |
| Vendors drawn | 20 |
| Kind | Place | In plain words |
|---|---|---|
| chosen | Progreso, site | where each package of work is done: on site or at Progreso |
| chosen | Progreso | how far it is finished before it ships: bare, fitted out, or fitted out and tested |
| chosen | Progreso, site | the size of each piece: sub pieces joined on site, or one complete lift |
| chosen | Progreso | robot cell or manual station, for each family of tasks |
| chosen | Progreso | which factory test halls are built |
| chosen | Progreso | the stations and shifts of each bay |
| chosen | Progreso | the ships of each class |
| chosen | Progreso | the buffer of finished modules at the quay |
| chosen | Progreso, site | the route of each vendor part: straight to the site, or through Progreso first |
| chosen | site | the ground work: one standard design, or one for each site |
| chosen | site | how far ahead of its reactor vessel each site starts |
| rule | site | Westinghouse’s design, module list, lift order and build sequence, unchanged |
| rule | site | holds that no labor can shorten: curing, weld inspection, pressure and leak tests, the hot test, inspection before fuel |
| rule | Progreso | every shipped piece within its ship and the crane of the site |
| rule | Progreso | no bay over its capacity in any month |
| rule | vendor | never more units at power than vessels delivered |
The vessel line
In the model one dedicated line at Doosan sets the pace of everything: it gives 12 reactor vessels a year in the target case, 6 in the cautious case, and no unit can start up before its vessel arrives.
target case · 12 a yearT · ingot and forging limits the linecautious case · 6 a year · heat treatment and tests limits the line
cautious case · 6 a yearT · heat treatment and tests limits the line
- vessels in work at once
- 14–42 vessels7–21 vessels
- months from first steel to the site
- 13.9–42.0 monthsthe same in both cases
- first vessel after the orderJ
- 54 months60 months
- months to reach the full rateJ
- 12 months24 months
The model gives these figures. The low one has every station working without a wait; the high one is the slowest flow on record. Each station is taken to work 85% of the timeJ.
Three paces, three hall lengths
A longer hall makes more vessels a year, and the model reaches unit 200 sooner.
The other dedicated lines: what the model needs each year, and what is made today
Data table
| Station | Work | Stations | Vessels waiting | Limits the line |
|---|---|---|---|---|
| Ingot and forging | 5.0 months | 6 | 3 | yes |
| Heat treatment and tests | 1.5 months | 2 | 0 | no |
| Rough machining | 2.0 months | 3 | 0 | no |
| Cladding | 2.5 months | 3 | 0 | no |
| Ring and nozzle welds | 4.0 months | 5 | 0 | no |
| Post weld heat treatment | 1.0 months | 2 | 0 | no |
| Final machining | 3.0 months | 4 | 0 | no |
| Examination | 1.5 months | 2 | 0 | no |
| Pressure test | 0.5 months | 1 | 0 | no |
| Sea transport to the site | 1.2 months | 2 | 0 | no |
| Station | Work | Stations | Vessels waiting | Limits the line |
|---|---|---|---|---|
| Ingot and forging | 5.0 months | 4 | 0 | no |
| Heat treatment and tests | 1.5 months | 1 | 2 | yes |
| Rough machining | 2.0 months | 2 | 0 | no |
| Cladding | 2.5 months | 2 | 0 | no |
| Ring and nozzle welds | 4.0 months | 3 | 0 | no |
| Post weld heat treatment | 1.0 months | 1 | 0 | no |
| Final machining | 3.0 months | 2 | 0 | no |
| Examination | 1.5 months | 1 | 0 | no |
| Pressure test | 0.5 months | 1 | 0 | no |
| Sea transport to the site | 1.2 months | 1 | 0 | no |
| Vessels a year | In the brief | Target case | Cautious case |
|---|---|---|---|
| 6 | yes | 40.3 years | 42.5 years |
| 12 | yes | 23.6 years | 26.1 years |
| 24 | no, shown for comparison | 15.8 years | 18.0 years |
Who makes what
The model sends the heaviest finished parts straight to the site: the reactor vessel, steam generators, turbine generator, moisture separator reheaters and transformers. The pressurizer; coolant pumps; head package and control rod drives; and internals go through Progreso first.The model sends the heaviest finished parts straight to the site: the reactor vessel, steam generators, coolant pumps, turbine generator, moisture separator reheaters and transformers. The pressurizer; head package and control rod drives; and internals go through Progreso first.
A part goes straight when a detour would delay the reactor vessel or cost more than it saves. It goes through Progreso when it is fitted into a module there, or when catching a fault before it reaches the site is worth the detour. In the cautious case the model changes the route of some: the basemat rebar cages, containment bottom head, coolant pumps and passive safety tanks and heat exchanger go straight to the site. Today coolant pumps and squib valves (explosive valves that open the passive safety systems) each have only one qualified maker.
- 1Turbine generatorToshibato siteto site
- 1Containment vessel platesIHIvia Progresovia Progreso
- 2Reactor vesselDoosan Enerbilityto siteto site
- 2Steam generatorsDoosan Enerbilityto siteto site
- 2CondenserBHI (Toshiba design)via Progresovia Progreso
- 3Large forgingsJapan Steel Works––
- 4Structural sub modulesVigor (Oregon Iron Works) and othersvia Progresovia Progreso
- 5Head packagePremier Technologyvia Progresovia Progreso
- 6EnrichmentUrenco USA––
- 7Fuel assembliesWestinghouse––
- 8Coolant pumpsCurtiss-Wrightvia Progresoto siteone maker
- 8Squib valvesSPX Copes-Vulcan––one maker
- 8Protection and control, control roomWestinghousevia Progresovia Progreso
- 8Mechanical modulesAeconvia Progresovia Progreso
- 8SimulatorGSE Systems––
- 9Shield building panelsNewport News Industrialvia Progresovia Progreso
- 9Safety pumps and valvesFlowserve and others––
- 10Internals, control rod drivesWestinghousevia Progresovia Progreso
- 10Nuclear cableGeneral Cable––
- 11Pressurizer, core makeup tanksMangiarotti (Westinghouse)via Progresovia Progreso
Where today’s output is known: what the model needs each year against what is made
2Reactor vessel
needed12 vesselsmade todayabout 5 sets a year (World Nuclear Association, marked uncertain)8Coolant pumpsone maker
needed48made today12 to 16 a year (secondary source)6Enrichment
neededabout 2.4 million units a year at 200 unitsmade todayabout 5 million units a year
3Large forgings: the model needs 60 vessel forgings, plus steam generator, pressurizer and pump forgings; made today: 12 vessel sets a year claimed; 4 documented to 2007. The two are counted in different things, so they are not set side by side as bars.
For the other parts no stated yearly output was found; they are listed in the data table.
Data table: every part, its vendors, demand and capacity
| Pin | Part | Vendor | Place | Latitude | Longitude | Status | Critical | Single source | Ships as | Route, target case | Route, cautious case | Second vendor | Needed a year | Capacity today |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Turbine generator | Toshiba | Yokohama, Japan | 35.50 | 139.70 | verified | yes | no | complete | straight to the site | straight to the site | Mitsubishi Heavy Industries; Arabelle (EDF) | 12 | no stated output found |
| 1 | Containment vessel plates | IHI | Yokohama, Japan | 35.44 | 139.64 | verified | no | no | formed plates | through Progreso | through Progreso | Polish yards with Westinghouse orders | 12 sets | no stated output found |
| 2 | Reactor vessel | Doosan Enerbility | Changwon, South Korea | 35.20 | 128.60 | verified | yes | no | complete, tested, by sea | straight to the site | straight to the site | BWXT Canada (agreement only) | 12 vessels | about 5 sets a year (World Nuclear Association, marked uncertain) |
| 2 | Steam generators | Doosan Enerbility | Changwon, South Korea | 35.20 | 128.60 | verified | yes | no | complete | straight to the site | straight to the site | ENSA, Spain (to verify); BWXT Canada (agreement) | 24 | no stated output found; 124 made in about 40 years |
| 2 | Condenser | BHI (Toshiba design) | Haman, South Korea | 35.27 | 128.40 | verified | no | no | complete, in modules | through Progreso | through Progreso | Doosan Å koda (to verify) | 12 | no stated output found |
| 3 | Large forgings | Japan Steel Works | Muroran, Japan | 42.30 | 141.00 | verified | yes | no | forgings | no route of its own | no route of its own | Doosan; Sheffield Forgemasters; Framatome Le Creusot | 60 vessel forgings, plus steam generator, pressurizer and pump forgings | 12 vessel sets a year claimed; 4 documented to 2007 |
| 4 | Structural sub modules | Vigor (Oregon Iron Works) and others | Portland, Oregon | 45.52 | -122.68 | verified | no | no | sub modules | through Progreso | through Progreso | Mostostal Kielce, Mostostal Kraków, EPG, FAMAK (Poland) | 12 sets | no stated output found |
| 5 | Head package | Premier Technology | Blackfoot, Idaho | 43.19 | -112.34 | verified | no | no | fitted at its maker | through Progreso | through Progreso | none found | 12 | no stated output found |
| 6 | Enrichment | Urenco USA | Eunice, New Mexico | 32.44 | -103.16 | verified | no | no | enriched uranium | no route of its own | no route of its own | Orano (planned, Oak Ridge) | about 2.4 million units a year at 200 units | about 5 million units a year |
| 7 | Fuel assemblies | Westinghouse | Columbia, South Carolina | 34.00 | -81.03 | verified | no | no | complete assemblies | no route of its own | no route of its own | Västerås, Sweden | 12 first cores, then reloads | no stated output found |
| 8 | Coolant pumps | Curtiss-Wright | Cheswick, Pennsylvania | 40.54 | -79.80 | verified | yes | yes | complete pump | through Progreso | straight to the site | none qualified | 48 | 12 to 16 a year (secondary source) |
| 8 | Squib valves | SPX Copes-Vulcan | McKean, Pennsylvania | 41.85 | -78.64 | verified | yes | yes | complete valve | no route of its own | no route of its own | none found | 12 sets | no stated output found |
| 8 | Protection and control, control room | Westinghouse | Cranberry, Pennsylvania | 40.68 | -80.10 | verified | yes | no | cabinets, factory tested | through Progreso | through Progreso | none found | 12 sets | no stated output found |
| 8 | Mechanical modules | Aecon | Cambridge, Ontario | 43.36 | -80.31 | verified | no | no | tested modules | through Progreso | through Progreso | Turner Industries; CB&I Laurens | 12 sets | no stated output found |
| 8 | Simulator | GSE Systems | Columbia, Maryland | 39.20 | -76.86 | verified | no | no | complete | no route of its own | no route of its own | none found | 1 for the fleet, then updates | not applicable |
| 9 | Shield building panels | Newport News Industrial | Newport News, Virginia | 36.98 | -76.43 | verified | no | no | panels | through Progreso | through Progreso | Polish yards (to verify) | 12 sets of about 160 | no stated output found |
| 9 | Safety pumps and valves | Flowserve and others | Raleigh, North Carolina | 35.78 | -78.64 | verified | no | no | complete | no route of its own | no route of its own | Velan, Canada (to verify) | 12 sets | no stated output found |
| 10 | Internals, control rod drives | Westinghouse | Newington, New Hampshire | 43.10 | -70.83 | verified | yes | no | complete | through Progreso | through Progreso | none found | 12 sets | no stated output found |
| 10 | Nuclear cable | General Cable | Willimantic, Connecticut | 41.71 | -72.21 | verified | no | no | reels | no route of its own | no route of its own | none found | 12 sets | no stated output found |
| 11 | Pressurizer, core makeup tanks | Mangiarotti (Westinghouse) | Monfalcone, Italy | 45.80 | 13.53 | to verify | yes | no | complete | through Progreso | through Progreso | Doosan; ENSA (candidates) | 12 and 24 | no stated output found |
Progreso
The model gives one factory on the quay that assembles, fits out and tests the modules of every unit, with 68% of its work stations in use in the target case and 30% in the cautious case.
drawn: the target case · the cautious figures stand beside it, below
drawn: the cautious case · the cautious figures stand beside it, below
one roof: ten work stations; lit roofs: the share in useten robotsten peopleone module’s way to the shipships under way are drawn small
- work stations in use
- 68%30%
- people
- 2,1816,249
- robotsJ
- 6550
- cost to build, billion USD
- 5.515.9
- crane shipsJ
- 1513
- float on, float off shipsJ
- 58
- months to build and proveJ
- 3444
Every bay runs at close to the same share, because the model sizes each one for its busiest month. All four test halls are built in both cases: each saves more on every unit than it costs once.
Data table
| Bay | Method | Stations | Shift stations in use | Use, steady | Use, ramp | Robots | People | Capital |
|---|---|---|---|---|---|---|---|---|
| Structural bay | mixed | 361 | 742 | 69% | 100% | 291 | 1,330 | 437 million USD |
| Rebar bay | robot | 63 | 128 | 68% | 99% | 63 | 128 | 57 million USD |
| Mechanical bay | robot | 144 | 296 | 68% | 100% | 144 | 294 | 130 million USD |
| Electrical bay | robot | 63 | 129 | 69% | 100% | 63 | 129 | 57 million USD |
| Coating bay | robot | 25 | 50 | 67% | 97% | 25 | 50 | 23 million USD |
| Test halls | mixed | 80 | 162 | 67% | 98% | 69 | 250 | 90 million USD |
| Item | State | Value | Second value |
|---|---|---|---|
| Test hall: Instrument and control, whole system on the simulator | built | 17 million USD saved a unit | 140 million USD cost |
| Test hall: Electrical cabinets | built | 102 million USD saved a unit | 60 million USD cost |
| Test hall: Pipe module pressure test | built | 143 million USD saved a unit | 45 million USD cost |
| Test hall: Module to module fit check | built | 28 million USD saved a unit | 80 million USD cost |
| Heavy lift crane ship | in the fleet | 15 ships | 10.4 voyages a unit |
| Semi submersible heavy transport ship | in the fleet | 5 ships | 3.4 voyages a unit |
| Modules in the yard | 6 | ||
| Buffer of finished modules at the quay | 1 | ||
| People, robots | 2,181 people | 655 robots | |
| Capital; months to build and qualify | 5.5 billion USD | 34 months |
| Bay | Method | Stations | Shift stations in use | Use, steady | Use, ramp | Robots | People | Capital |
|---|---|---|---|---|---|---|---|---|
| Structural bay | manual | 825 | 754 | 30% | 50% | 0 | 3,311 | 3,300 million USD |
| Rebar bay | manual | 104 | 94 | 30% | 50% | 0 | 415 | 416 million USD |
| Mechanical bay | manual | 280 | 256 | 30% | 50% | 0 | 1,123 | 1,120 million USD |
| Electrical bay | manual | 123 | 112 | 30% | 50% | 0 | 491 | 492 million USD |
| Coating bay | manual | 49 | 44 | 30% | 49% | 0 | 193 | 196 million USD |
| Test halls | manual | 179 | 163 | 30% | 50% | 0 | 716 | 716 million USD |
| Item | State | Value | Second value |
|---|---|---|---|
| Test hall: Instrument and control, whole system on the simulator | built | 20 million USD saved a unit | 200 million USD cost |
| Test hall: Electrical cabinets | built | 158 million USD saved a unit | 90 million USD cost |
| Test hall: Pipe module pressure test | built | 201 million USD saved a unit | 70 million USD cost |
| Test hall: Module to module fit check | built | 19 million USD saved a unit | 120 million USD cost |
| Heavy lift crane ship | in the fleet | 13 ships | 7.8 voyages a unit |
| Semi submersible heavy transport ship | in the fleet | 8 ships | 4.6 voyages a unit |
| Modules in the yard | 3 | ||
| Buffer of finished modules at the quay | 1 | ||
| People, robots | 6,249 people | 0 robots | |
| Capital; months to build and qualify | 15.9 billion USD | 44 months |
One site
The model gives a site that runs 63.0 months in the target case and 94.1 months in the cautious case, from the first day of ground work to full power; the final tests, which no extra labor can shorten, close it.
For comparison only: Westinghouse’s target is 36 months from first concrete to fuel load; Vogtle took 125 monthsD from first concrete to commercial operation, with about 9,000 people on site at its peak.
drawn: the target case · the cautious case as a second row and an open outline
drawn: the cautious case · the cautious case as a second row and an open outline
a phase of the workone taska wait no labor can shortena crane liftthe longest chain of taskstests and records that do not need the vesselfull power
Making the site ready before the reactor vessel comes
When the vessel arrives, the model has 48% of the site’s work done in the target case and 45% in the cautious case; starting earlier would finish more of it, but would bring full power only a little sooner.
- head start the model gives
- 0.0 months0.0 months
- head start that would have all else done
- 19.3 months23.4 months
- months from the vessel’s arrival to full power
- 34.349.9with the latest start34.349.9as the model gives it33.149.2with all else done first
To have everything that does not need the vessel finished on the day it arrives, the site would start 19.3 months earlier. The model then gives 33.1 months from the vessel to full power, against 34.3 months with the latest start: almost all of that wait is set by work that can only follow the vessel, the reactor vessel, steam generators, coolant pumps, cold hydro and hot functional test, inspection closure and fuel load and power ascension. The model gives a head start of 0.0 months: the months gained are worth less to it than the cost of a site that stands finished and waiting.
To have everything that does not need the vessel finished on the day it arrives, the site would start 23.4 months earlier. The model then gives 49.2 months from the vessel to full power, against 49.9 months with the latest start: almost all of that wait is set by work that can only follow the vessel, the reactor vessel, steam generators, coolant pumps, cold hydro and hot functional test, inspection closure and fuel load and power ascension. The model gives a head start of 0.0 months: the months gained are worth less to it than the cost of a site that stands finished and waiting.
What sets the wait after the vessel: the work that can only follow it, in order
- Reactor vessel3.9 months, of which 0.1 a fixed wait
- Steam generators4.4 months, of which 0.1 a fixed wait
- Coolant pumps5.3 months, of which 0.1 a fixed wait
- Cold hydro and hot functional test6.5 months, of which 3.1 a fixed wait
- Inspection closure and fuel load6.0 months, of which 3.0 a fixed wait
- Power ascension7.0 months, of which 2.0 a fixed wait
- Reactor vessel5.6 months, of which 0.1 a fixed wait
- Steam generators6.2 months, of which 0.1 a fixed wait
- Coolant pumps7.6 months, of which 0.1 a fixed wait
- Cold hydro and hot functional test10.0 months, of which 3.1 a fixed wait
- Inspection closure and fuel load10.6 months, of which 3.0 a fixed wait
- Power ascension9.2 months, of which 2.0 a fixed wait
worka fixed wait that no labor can shorten
The longest chain of tasks, in plain steps: a day lost on any of them is a day lost at the end
- 1Prepare the ground: clear it, dig, and fill it back firmfrom month 00
- 2Build the turbine hall and fit the turbine, its pipes and its cablesfrom month 1423
- 3Connect the last cables across the whole plantfrom month 3959
- 4Run the tests that do not need the reactor vesselfrom month 4061
- 5Test the finished plant, first cold, then hotfrom month 4364
- 6Pass the final inspections, load the fuel and raise the power step by stepfrom month 5074
Ground work
One standard design for the ground and the quay, used at every siteT.
- ground crews
- 1412
- months of early start
- 00
- heavy cranesJ
- 128
Crews that move from site to siteJ
Data table
| Task | Chain | Start | Duration | Of which hold | Critical | Crane lift |
|---|---|---|---|---|---|---|
| Clearing and grading | Ground work | 0.0 | 1.6 months | 0.0 months | yes | no |
| Excavation and dewatering | Ground work | 1.6 | 6.8 months | 0.0 months | yes | no |
| Engineered backfill | Ground work | 8.5 | 5.5 months | 0.3 months | yes | no |
| Unloading quay and heavy haul road | Ground work | 1.6 | 4.4 months | 1.0 months | no | no |
| Cooling water works and towers | Turbine hall | 8.5 | 9.6 months | 0.9 months | no | no |
| Switchyard | Turbine hall | 1.6 | 3.9 months | 0.0 months | no | no |
| Site buildings | Turbine hall | 1.6 | 5.4 months | 0.0 months | no | no |
| Basemat rebar cages | Concrete and buildings | 14.0 | 1.9 months | 0.0 months | no | no |
| Basemat concrete | Concrete and buildings | 15.9 | 3.8 months | 0.9 months | no | no |
| Containment bottom head | Reactor building | 19.7 | 3.2 months | 0.2 months | no | yes |
| Containment rings | Reactor building | 26.4 | 2.3 months | 0.2 months | no | yes |
| Containment top head | Reactor building | 37.0 | 0.5 months | 0.2 months | no | yes |
| Structural modules CA01, CA02 to CA05, CA20 | Reactor building | 22.9 | 3.5 months | 0.5 months | no | yes |
| Shield building panels | Concrete and buildings | 19.7 | 2.3 months | 0.2 months | no | no |
| Shield building roof and water tank | Concrete and buildings | 37.5 | 2.1 months | 0.3 months | no | yes |
| Interior concrete | Concrete and buildings | 26.4 | 16.2 months | 0.9 months | no | no |
| Auxiliary and fuel building concrete | Concrete and buildings | 26.4 | 13.6 months | 0.9 months | no | no |
| Embeds and penetrations | Concrete and buildings | 19.7 | 6.5 months | 0.0 months | no | no |
| Steel platforms and stairs | Reactor building | 26.4 | 1.0 months | 0.0 months | no | no |
| Coatings and liner closure | Reactor building | 37.5 | 4.5 months | 0.2 months | no | no |
| Piping modules | Reactor building | 26.4 | 1.2 months | 0.3 months | no | no |
| Mechanical equipment modules | Reactor building | 26.4 | 1.2 months | 0.3 months | no | no |
| Electrical equipment modules | Reactor building | 26.4 | 0.8 months | 0.2 months | no | no |
| Large pipe spools | Reactor building | 27.6 | 7.6 months | 0.5 months | no | no |
| Cable sets | Reactor building | 27.2 | 2.5 months | 0.2 months | no | no |
| Ventilation | Reactor building | 40.0 | 1.9 months | 0.0 months | no | no |
| Reactor vessel | Reactor building | 28.7 | 3.9 months | 0.1 months | no | yes |
| Steam generators | Reactor building | 32.6 | 4.4 months | 0.1 months | no | yes |
| Pressurizer | Reactor building | 26.4 | 3.1 months | 0.1 months | no | yes |
| Coolant pumps | Reactor building | 37.0 | 5.3 months | 0.1 months | no | no |
| Head package and control rod drives | Reactor building | 32.6 | 3.9 months | 0.1 months | no | no |
| Internals | Reactor building | 32.6 | 3.9 months | 0.1 months | no | no |
| Passive safety tanks and heat exchanger | Reactor building | 26.4 | 5.0 months | 0.2 months | no | no |
| Turbine building blocks | Turbine hall | 14.0 | 3.3 months | 0.5 months | yes | no |
| Turbine generator | Turbine hall | 17.3 | 14.4 months | 0.2 months | yes | yes |
| Condenser | Turbine hall | 17.3 | 6.5 months | 0.2 months | no | no |
| Moisture separator reheaters | Turbine hall | 17.3 | 7.2 months | 0.1 months | no | no |
| Feedwater train | Turbine hall | 17.3 | 6.1 months | 0.2 months | no | no |
| Transformers | Turbine hall | 5.5 | 5.8 months | 0.1 months | no | no |
| Turbine island pipe and cable | Turbine hall | 31.7 | 7.1 months | 0.5 months | yes | no |
| Annex building | Concrete and buildings | 14.0 | 5.4 months | 0.3 months | no | no |
| Diesel building | Concrete and buildings | 14.0 | 3.2 months | 0.2 months | no | no |
| Waste building | Concrete and buildings | 14.0 | 3.1 months | 0.2 months | no | no |
| Auxiliary electrical rooms | Concrete and buildings | 19.3 | 2.5 months | 0.2 months | no | no |
| Protection and control cabinets | Reactor building | 21.8 | 2.7 months | 0.2 months | no | no |
| Main control room | Reactor building | 24.5 | 3.7 months | 0.3 months | no | no |
| Plant wide cable termination | Reactor building | 38.8 | 1.2 months | 0.0 months | yes | no |
| Cold hydro and hot functional test | Testing and start | 43.5 | 6.5 months | 3.1 months | yes | no |
| Inspection closure and fuel load | Testing and start | 50.0 | 6.0 months | 3.0 months | yes | no |
| Power ascension | Testing and start | 56.0 | 7.0 months | 2.0 months | yes | no |
| Tests that do not need the vessel | Testing and start | 40.0 | 3.4 months | 0.0 months | yes | no |
| Inspection records closed before the vessel | Testing and start | 43.5 | 4.6 months | 0.0 months | no | no |
| Measure | People |
|---|---|
| Peak | 4,319 |
| Average | 1,967 |
| Vogtle’s peak | 9,000 |
| Month by month, from the first | 951 1,972 1,488 1,488 1,488 1,596 1,432 1,181 1,824 1,437 1,437 1,437 1,330 2,881 2,638 2,804 2,475 3,225 2,388 2,539 1,988 2,091 2,260 2,104 1,832 1,621 3,713 4,319 3,609 3,305 2,492 3,773 3,638 3,558 3,558 3,558 3,096 3,120 3,731 2,615 1,994 1,309 1,040 1,187 1,187 1,187 1,187 1,187 1,187 1,880 1,161 1,161 1,161 1,161 1,161 1,457 763 763 763 763 763 763 763 |
| Task | Chain | Start | Duration | Of which hold | Critical | Crane lift |
|---|---|---|---|---|---|---|
| Clearing and grading | Ground work | 0.0 | 2.8 months | 0.0 months | yes | no |
| Excavation and dewatering | Ground work | 2.8 | 11.5 months | 0.0 months | yes | no |
| Engineered backfill | Ground work | 14.3 | 9.0 months | 0.3 months | yes | no |
| Unloading quay and heavy haul road | Ground work | 2.8 | 6.8 months | 1.0 months | no | no |
| Cooling water works and towers | Turbine hall | 14.3 | 13.5 months | 0.9 months | no | no |
| Switchyard | Turbine hall | 2.8 | 5.9 months | 0.0 months | no | no |
| Site buildings | Turbine hall | 2.8 | 8.3 months | 0.0 months | no | no |
| Basemat rebar cages | Concrete and buildings | 23.3 | 4.3 months | 0.0 months | no | no |
| Basemat concrete | Concrete and buildings | 27.6 | 5.0 months | 0.9 months | no | no |
| Containment bottom head | Reactor building | 32.6 | 4.6 months | 0.2 months | no | yes |
| Containment rings | Reactor building | 42.4 | 1.8 months | 0.2 months | no | yes |
| Containment top head | Reactor building | 55.9 | 0.7 months | 0.2 months | no | yes |
| Structural modules CA01, CA02 to CA05, CA20 | Reactor building | 37.2 | 5.2 months | 0.5 months | no | yes |
| Shield building panels | Concrete and buildings | 32.6 | 3.4 months | 0.2 months | no | no |
| Shield building roof and water tank | Concrete and buildings | 56.6 | 2.9 months | 0.3 months | no | yes |
| Interior concrete | Concrete and buildings | 42.4 | 22.9 months | 0.9 months | no | no |
| Auxiliary and fuel building concrete | Concrete and buildings | 42.4 | 19.1 months | 0.9 months | no | no |
| Embeds and penetrations | Concrete and buildings | 32.6 | 10.0 months | 0.0 months | no | no |
| Steel platforms and stairs | Reactor building | 42.4 | 1.6 months | 0.0 months | no | no |
| Coatings and liner closure | Reactor building | 56.6 | 6.4 months | 0.2 months | no | no |
| Piping modules | Reactor building | 42.4 | 1.7 months | 0.3 months | no | no |
| Mechanical equipment modules | Reactor building | 42.4 | 1.7 months | 0.3 months | no | no |
| Electrical equipment modules | Reactor building | 42.4 | 1.2 months | 0.2 months | no | no |
| Large pipe spools | Reactor building | 44.0 | 11.4 months | 0.5 months | no | no |
| Cable sets | Reactor building | 43.5 | 3.7 months | 0.2 months | no | no |
| Ventilation | Reactor building | 61.5 | 2.9 months | 0.0 months | no | no |
| Reactor vessel | Reactor building | 44.2 | 5.6 months | 0.1 months | no | yes |
| Steam generators | Reactor building | 49.7 | 6.2 months | 0.1 months | no | yes |
| Pressurizer | Reactor building | 42.4 | 4.4 months | 0.1 months | no | yes |
| Coolant pumps | Reactor building | 55.9 | 7.6 months | 0.1 months | no | no |
| Head package and control rod drives | Reactor building | 49.7 | 5.6 months | 0.1 months | no | no |
| Internals | Reactor building | 49.7 | 5.5 months | 0.1 months | no | no |
| Passive safety tanks and heat exchanger | Reactor building | 42.4 | 8.3 months | 0.2 months | no | no |
| Turbine building blocks | Turbine hall | 23.3 | 4.8 months | 0.5 months | yes | no |
| Turbine generator | Turbine hall | 28.1 | 20.7 months | 0.2 months | yes | yes |
| Condenser | Turbine hall | 28.1 | 9.8 months | 0.2 months | no | no |
| Moisture separator reheaters | Turbine hall | 28.1 | 10.3 months | 0.1 months | no | no |
| Feedwater train | Turbine hall | 28.1 | 9.3 months | 0.2 months | no | no |
| Transformers | Turbine hall | 8.6 | 8.3 months | 0.1 months | no | no |
| Turbine island pipe and cable | Turbine hall | 48.8 | 10.7 months | 0.5 months | yes | no |
| Annex building | Concrete and buildings | 23.3 | 8.1 months | 0.3 months | no | no |
| Diesel building | Concrete and buildings | 23.3 | 4.8 months | 0.2 months | no | no |
| Waste building | Concrete and buildings | 23.3 | 4.6 months | 0.2 months | no | no |
| Auxiliary electrical rooms | Concrete and buildings | 31.3 | 3.7 months | 0.2 months | no | no |
| Protection and control cabinets | Reactor building | 35.0 | 4.1 months | 0.2 months | no | no |
| Main control room | Reactor building | 39.1 | 5.6 months | 0.3 months | no | no |
| Plant wide cable termination | Reactor building | 59.5 | 1.9 months | 0.0 months | yes | no |
| Cold hydro and hot functional test | Testing and start | 64.3 | 10.0 months | 3.1 months | yes | no |
| Inspection closure and fuel load | Testing and start | 74.2 | 10.6 months | 3.0 months | yes | no |
| Power ascension | Testing and start | 84.8 | 9.2 months | 2.0 months | yes | no |
| Tests that do not need the vessel | Testing and start | 61.3 | 2.9 months | 0.0 months | yes | no |
| Inspection records closed before the vessel | Testing and start | 64.3 | 3.3 months | 0.0 months | no | no |
| Measure | People |
|---|---|
| Peak | 3,817 |
| Average | 1,705 |
| Vogtle’s peak | 9,000 |
| Month by month, from the first | 858 858 1,749 1,349 1,349 1,349 1,349 1,349 1,446 1,299 1,071 1,071 875 875 1,652 1,332 1,332 1,235 1,235 1,235 1,235 1,235 1,235 2,658 2,453 2,453 2,453 2,613 2,234 1,647 1,647 1,788 1,999 1,839 1,839 1,933 1,518 2,099 1,621 1,616 1,522 1,522 3,465 3,427 3,817 3,053 3,053 2,993 3,476 3,451 3,378 3,282 3,282 3,282 3,282 3,454 2,895 2,820 2,820 3,433 2,107 2,254 1,221 1,126 1,633 1,486 1,062 1,062 1,062 1,062 1,062 1,062 1,062 1,062 1,567 963 963 963 963 963 963 963 963 963 1,253 748 748 748 748 748 748 748 748 748 748 |
The machine
One vessel line, 12 vessels a year, sets the pace of all 200 sites.
The fleet
200 sites fill in vessel order, each 15 days by sea from Progreso; the vessel line sets the pace.
- land prepared
- civil
- vessel set
- testing
- power
since the order
0 years0 months
target
cautious
units online
0 units
0 units
power online
0.0 GW
0.0 GW
ships at sea
0 ships
0 ships
sites open
0 sites
0 sites
gangs at work
0 gangs
0 gangs
schematic: every site is 15 days from Progreso; positions are not geographic
Why it costs less · from Vogtle to Siderian
For the same reactor the model gives 9.0 million hours to 12.0 million hours on site per unit, where Vogtle took 25.0 million hours.
Vogtle is the baseline: both units averaged, as built. Everything below is what the model changes from there, each gain counted once, under the model’s assumptions.
Three ways to build it
Fewer hours on site, fewer months on site, cheaper electricity: the model gives 63 months to 94 months on site against Vogtle’s 125 months.
site hours per unit, million
15.4million hours
19.4million hours
All on site
Siderian’s program with every package built at the site. It is below Vogtle because Vogtle’s own causes are removed and the crews learn from site to site; nothing moves to the factory.
- All on site
- Siderian’s program with every package built at the site. It is below Vogtle because Vogtle’s own causes are removed and the crews learn from site to site; nothing moves to the factory.
- months on site (grade: derived)
- 68 months97 months
- cost of electricity, at 7% only
- 137 USD/MWh217 USD/MWh
25.0million hours
25.0million hours
As Vogtle was built
both units averaged, as built
- As Vogtle was built
- both units averaged, as built
- months on site (grade: documented)
- 125 months125 months
- cost of electricity
- 228 USD/MWh252 USD/MWh
9.0million hours
12.0million hours
Siderian
the same program with the work placed where the model finds it cheapest
- Siderian
- the same program with the work placed where the model finds it cheapest
- months on site
- 63 months94 months
- cost of electricity
- 114 USD/MWh181 USD/MWh
Cost of electricity at a 7% cost of money, under the model’s assumptions. “All on site” was evaluated at 7% only, so its figure does not follow the control. Vogtle’s months run from first concrete to commercial operation.
The numbers in this drawing
| Way of building | Case | Site hours per unit | Months on site | Cost of electricity |
|---|---|---|---|---|
| All on site | target | 15.4 million hours | 68 months | 137 USD/MWh |
| All on site | cautious | 19.4 million hours | 97 months | 217 USD/MWh |
| As Vogtle was built | target | 25.0 million hours | 125 months | 228 USD/MWh |
| As Vogtle was built | cautious | 25.0 million hours | 125 months | 252 USD/MWh |
| Siderian | target | 9.0 million hours | 63 months | 114 USD/MWh |
| Siderian | cautious | 12.0 million hours | 94 months | 181 USD/MWh |
The ledger
From Vogtle’s 15,390 USD/kW to a fleet average of 7,360 USD/kW to 10,280 USD/kW, each gain taken once and in a fixed order.
This is the cost to build before any interest, often called the overnight cost. The packages are priced bottom up at Vogtle’s own hours and wages; what they do not explain of Vogtle’s cost, 6% in the target case and 1% in the cautious case, is carried unchanged through every stage and never reduced.
- Vogtle as built15,390 USD/kW15,390 USD/kW
- Causes particular to Vogtle−3,260 USD/kW−1,590 USD/kW
- One design and one program for 200 units−2,910 USD/kW−3,040 USD/kW
- Work moved to its place, net of the factory, ships and shipping−1,390 USD/kW−1,720 USD/kW
- Robots and factory tests−180 USD/kW−180 USD/kW
- Dedicated vendor lines−310 USD/kW−100 USD/kW
- Learning, to the fleet average−970 USD/kW−790 USD/kW
- Contingency990 USD/kW2,310 USD/kW
- Siderian, fleet average7,360 USD/kW10,280 USD/kW
The ledger as a table
| Stage | What changes | target | cautious |
|---|---|---|---|
| L0 | Vogtle as built | 15,390 USD/kW | 15,390 USD/kW |
| L1 | Causes particular to Vogtle | −3,260 USD/kW | −1,590 USD/kW |
| One program | One design and one program for 200 units | −2,910 USD/kW | −3,040 USD/kW |
| L2 | Work moved to its place, net of the factory, ships and shipping | −1,390 USD/kW | −1,720 USD/kW |
| L3 | Robots and factory tests | −180 USD/kW | −180 USD/kW |
| L4 | Dedicated vendor lines | −310 USD/kW | −100 USD/kW |
| L5 | Learning, to the fleet average | −970 USD/kW | −790 USD/kW |
| + | Contingency | 990 USD/kW | 2,310 USD/kW |
| = | Siderian, fleet average | 7,360 USD/kW | 10,280 USD/kW |
| Share of Vogtle’s cost the packages do not explain | 6% | 1% |
Vogtle’s causes, Siderian’s fixes
Each cause of Vogtle’s cost that the model prices has a named fix, and each fix is priced in one place.
The other causes and their fixes
“Priced in” names the row of the ledger above where the fix is counted. Sizes are as published for Vogtle.
Why it costs less · where the work goes
Of Vogtle’s 25.0 million hours on site per unit, the model leaves 9.0 to 12.0 million there and gives Progreso 0.4 to 2.2 million.
Hours per unit, by place
Hours that leave the site do not arrive whole: in the model one factory hour replaces several site hours, and part of Vogtle’s hours is not worked at all.
VVogtle, shops1.6 million hours
SVogtle, site25.0 million hours
leave the site
no longer worked
still worked on site
Vvendors1.6 million hours1.6 million hours
PProgreso0.4 million hours2.2 million hours
Ssite, what remains9.0 million hours12.0 million hours
The model gives 9.0 million hours (target) and 12.0 million hours (cautious) per unit still worked on site. Hours moved to the factory shrink. One hour in a shop replaces 8 to 5 hours inside the plant, for fitting out (grade: judged), 3 to 2 hours in an open yard, for fitting out (grade: judged) and 3 to 2 hours inside the plant, for plate and rebar (grade: judged) . The rule comes from shipyards and is used here as an analogy. The band that fades out is the rest of the fall: Vogtle’s own excess, removed first, and learning across the fleet. Vendor hours are those of Vogtle’s module shops, unchanged.
The numbers in this drawing
| Place | target | cautious |
|---|---|---|
| Vogtle, shops | 1,557 thousand hours | 1,557 thousand hours |
| Vogtle, site | 24,984 thousand hours | 24,984 thousand hours |
| Vogtle, all places | 26,541 thousand hours | 26,541 thousand hours |
| Siderian, vendors | 1,557 thousand hours | 1,557 thousand hours |
| Siderian, Progreso | 383 thousand hours | 2,177 thousand hours |
| Siderian, site | 9,032 thousand hours | 12,043 thousand hours |
| Siderian, all places | 10,973 thousand hours | 15,778 thousand hours |
The plant, package by package
50 packages, each sized by the site hours it took at Vogtle; the edge of each shows where the model does its movable work, the small arrow where its vendor parts go.
- Pfinished at Progreso
- Vsold complete by a vendor
- Sstays on site
- barefitted outfitted out and tested
- shipped completein pieces
- vendor parts straight to the sitethrough Progreso
- the cautious case chooses differently
Land and site worksLand and site works
Nuclear island structureNuclear island structure
Mechanical and electricalNuclear island mechanical and electrical
Primary componentsPrimary components
Turbine islandTurbine island
Other buildingsOther buildings
Instrument and controlInstrument and control
Tests and startTests and start
Point at a block, or touch it, to read the package. The filled blocks are the largest; a block keeps its Vogtle size, and only its edge, its depth and its piece size are the model’s choice.
The choices that matter most
The eight packages where the choice of place counts most: how much worse the next best choice would be, per unit.
Unless a row says otherwise, the model finishes the package at Progreso, fitted out and tested, and ships it completefinishes the package at Progreso, fitted out and tested, and ships it complete: the usual choice.
Of the packages with vendor parts to route, the model sends 5 straight to the site and 32 through Progreso in the target case and, in the cautious case, 9 straight to the site and 28 through Progreso. At Progreso they are received, inspected, held and shipped on. In the target case the The parts of containment bottom head, pressurizer, coolant pumps, head package and control rod drives and internals go through Progreso although the work itself stays where it was. In the cautious case the The parts of pressurizer, head package and control rod drives and internals go through Progreso although the work itself stays where it was. In the model’s terms, a defect caught at Progreso before it reaches the site is worth the detour; the vessel and the heaviest pieces go straight, because a detour would cost more or, for the vessel, hold up the site.
| Package | Where the model does its movable work | Its vendor parts go | Next best choice would cost more by | Site hours now, of Vogtle’s, thousand per unit |
|---|---|---|---|---|
| Turbine island pipe and cableTurbine island | the usual choice | through Progreso | 106.6 million USD164.6 million USD | 1,033of3,9001,425of3,900 |
| Cable setsNuclear island mechanical and electrical | the usual choice | through Progreso | 50.3 million USD72.7 million USD | 212of1,000292of1,000 |
| Plant wide cable terminationInstrument and control | the usual choice | local material, nothing to route | 40.0 million USD74.7 million USD | 95of400132of400 |
| Basemat rebar cagesNuclear island structure | PProgreso, bare, completeSsite | through Progresostraight to the site | 25.0 million USD16.1 million USD | 72of190145of190 |
| Large pipe spoolsNuclear island mechanical and electrical | the usual choice | through Progreso | 11.8 million USD7.9 million USD | 554of1,900764of1,900 |
| Protection and control cabinetsInstrument and control | the usual choice | through Progreso | 11.7 million USD17.1 million USD | 32of15044of150 |
| Turbine building blocksTurbine island | the usual choice | through Progreso | 11.1 million USD12.1 million USD | 180of850245of850 |
| Piping modulesNuclear island mechanical and electrical | the usual choice | through Progreso | 9.8 million USD13.9 million USD | 40of63355of633 |
| Package | Where the model does its movable work | Its vendor parts go | Next best choice would cost more by | Site hours now, of Vogtle’s, thousand per unit |
|---|---|---|---|---|
| Turbine island pipe and cableTurbine island | the usual choice | through Progreso | 106.6 million USD164.6 million USD | 1,033of3,9001,425of3,900 |
| Plant wide cable terminationInstrument and control | the usual choice | local material, nothing to route | 40.0 million USD74.7 million USD | 95of400132of400 |
| Cable setsNuclear island mechanical and electrical | the usual choice | through Progreso | 50.3 million USD72.7 million USD | 212of1,000292of1,000 |
| Reactor vesselPrimary components | VvendorVvendor | straight to the site | 1.3 million USD17.7 million USD | 36of6046of60 |
| Protection and control cabinetsInstrument and control | the usual choice | through Progreso | 11.7 million USD17.1 million USD | 32of15044of150 |
| Basemat rebar cagesNuclear island structure | PProgreso, bare, completeSsite | through Progresostraight to the site | 25.0 million USD16.1 million USD | 72of190145of190 |
| Piping modulesNuclear island mechanical and electrical | the usual choice | through Progreso | 9.8 million USD13.9 million USD | 40of63355of633 |
| Turbine building blocksTurbine island | the usual choice | through Progreso | 11.1 million USD12.1 million USD | 180of850245of850 |
Per unit, at steady state. A package with no choice is left out: a vendor sells it complete, or its work cannot leave the site. Where a cell has two lines, the first is the target case and the second the cautious case; the order is the target case’s.
All 50 packages, with hours at each place, weight shipped and a sort control
| Package | Place | Finished there | Shipped | Vendor parts go | Vendor hours | Progreso hours | Site hours | Vogtle site hours | Next best choice, million USD a unit | Shipped, tonnes |
|---|---|---|---|---|---|---|---|---|---|---|
| Clearing and gradingLand and site works | SsiteSsite | –– | –– | –– | 00 | 00 | 91126 | 180 | no choiceno choice | – |
| Excavation and dewateringLand and site works | SsiteSsite | –– | –– | –– | 00 | 00 | 302420 | 600 | no choiceno choice | – |
| Engineered backfillLand and site works | SsiteSsite | –– | –– | –– | 00 | 00 | 151210 | 300 | no choiceno choice | – |
| Unloading quay and heavy haul roadLand and site works | SsiteSsite | –– | –– | –– | 00 | 00 | 126175 | 250 | no choiceno choice | – |
| Cooling water works and towersLand and site works | SsiteSsite | –– | –– | –– | 00 | 00 | 681875 | 1,150 | no choiceno choice | – |
| SwitchyardLand and site works | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 633 | 7298 | 270 | 3.64.2 | 400 |
| Site buildingsLand and site works | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 635 | 136186 | 400 | 2.61.7 | 1,200 |
| Basemat rebar cagesNuclear island structure | PProgresoSsite | bare– | complete– | through Progresostraight to the site | 00 | 30 | 72145 | 190 | 25.016.1 | 1,800 |
| Basemat concreteNuclear island structure | SsiteSsite | –– | –– | –– | 00 | 00 | 7191 | 120 | no choiceno choice | – |
| Containment bottom headNuclear island structure | SsiteSsite | –– | –– | through Progresostraight to the site | 1313 | 00 | 5774 | 97 | 0.65.6 | – |
| Containment ringsNuclear island structure | PProgresoPProgreso | fitted out and testedbare | in piecescomplete | through Progresothrough Progreso | 4343 | 882 | 5436 | 317 | 0.68.9 | 2,220 |
| Containment top headNuclear island structure | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 1111 | 422 | 46 | 79 | 0.70.1 | 655 |
| Structural modules CA01, CA02 to CA05, CA20Nuclear island structure | PProgresoPProgreso | fitted out and testedfitted out | completecomplete | through Progresothrough Progreso | 322322 | 117611 | 248345 | 1,978 | 6.33.0 | 2,400 |
| Shield building panelsNuclear island structure | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 154154 | 847 | 78105 | 286 | 1.10.7 | 1,950 |
| Shield building roof and water tankNuclear island structure | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 7878 | 740 | 3850 | 182 | 1.82.1 | 1,234 |
| Interior concreteNuclear island structure | SsiteSsite | –– | –– | –– | 00 | 00 | 8591,104 | 1,450 | no choiceno choice | – |
| Auxiliary and fuel building concreteNuclear island structure | SsiteSsite | –– | –– | –– | 00 | 00 | 711914 | 1,200 | no choiceno choice | – |
| Embeds and penetrationsNuclear island structure | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 426 | 123167 | 330 | 2.31.5 | 150 |
| Steel platforms and stairsNuclear island structure | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 7878 | 947 | 2331 | 182 | 0.40.3 | 500 |
| Coatings and liner closureNuclear island structure | SsiteSsite | –– | –– | –– | 00 | 00 | 5369 | 90 | no choiceno choice | – |
| Piping modulesNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 518518 | 19111 | 4055 | 633 | 9.813.9 | 1,400 |
| Mechanical equipment modulesNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 240240 | 1060 | 2939 | 360 | 7.010.0 | 1,100 |
| Electrical equipment modulesNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 100100 | 425 | 1013 | 150 | 3.85.5 | 165 |
| Large pipe spoolsNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 27160 | 554764 | 1,900 | 11.87.9 | 1,000 |
| Cable setsNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 18104 | 212292 | 1,000 | 50.372.7 | 600 |
| VentilationNuclear island mechanical and electrical | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 315 | 3649 | 150 | 2.12.5 | 150 |
| Reactor vesselPrimary components | VvendorVvendor | –– | –– | straight to the sitestraight to the site | 00 | 00 | 3646 | 60 | 1.317.7 | – |
| Steam generatorsPrimary components | VvendorVvendor | –– | –– | straight to the sitestraight to the site | 00 | 00 | 5369 | 90 | 1.34.7 | – |
| PressurizerPrimary components | VvendorVvendor | –– | –– | through Progresothrough Progreso | 00 | 01 | 2430 | 40 | 1.79.0 | – |
| Coolant pumpsPrimary components | VvendorVvendor | –– | –– | through Progresostraight to the site | 00 | 10 | 6584 | 110 | 0.46.7 | – |
| Head package and control rod drivesPrimary components | VvendorVvendor | –– | –– | through Progresothrough Progreso | 00 | 02 | 3646 | 60 | 0.30.9 | – |
| InternalsPrimary components | VvendorVvendor | –– | –– | through Progresothrough Progreso | 00 | 02 | 2430 | 40 | 0.40.9 | – |
| Passive safety tanks and heat exchangerPrimary components | PProgresoSsite | fitted out and tested– | complete– | through Progresostraight to the site | 00 | 00 | 6091 | 120 | 1.33.5 | 700 |
| Turbine building blocksTurbine island | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 26148 | 180245 | 850 | 11.112.1 | 5,500 |
| Turbine generatorTurbine island | VvendorVvendor | –– | –– | straight to the sitestraight to the site | 00 | 00 | 444571 | 750 | 1.27.1 | – |
| CondenserTurbine island | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 425 | 156215 | 420 | 3.32.2 | 900 |
| Moisture separator reheatersTurbine island | VvendorVvendor | –– | –– | straight to the sitestraight to the site | 00 | 00 | 89114 | 150 | 3.16.6 | – |
| Feedwater trainTurbine island | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 318 | 111153 | 300 | 5.05.6 | 600 |
| TransformersTurbine island | VvendorVvendor | –– | –– | straight to the sitestraight to the site | 00 | 00 | 7191 | 120 | 3.06.7 | – |
| Turbine island pipe and cableTurbine island | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 62364 | 1,0331,425 | 3,900 | 106.6164.6 | 2,000 |
| Annex buildingOther buildings | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 950 | 237324 | 650 | 4.63.0 | 1,500 |
| Diesel buildingOther buildings | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 318 | 5777 | 180 | 2.62.8 | 400 |
| Waste buildingOther buildings | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 528 | 7399 | 250 | 2.73.2 | 700 |
| Auxiliary electrical roomsOther buildings | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 529 | 4459 | 200 | 4.15.4 | 500 |
| Protection and control cabinetsInstrument and control | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 316 | 3244 | 150 | 11.717.1 | 200 |
| Main control roomInstrument and control | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | through Progresothrough Progreso | 00 | 421 | 4258 | 200 | 8.311.8 | 150 |
| Plant wide cable terminationInstrument and control | PProgresoPProgreso | fitted out and testedfitted out and tested | completecomplete | –– | 00 | 638 | 95132 | 400 | 40.074.7 | – |
| Cold hydro and hot functional testTests and start | SsiteSsite | –– | –– | –– | 00 | 00 | 533685 | 900 | no choiceno choice | – |
| Inspection closure and fuel loadTests and start | SsiteSsite | –– | –– | –– | 00 | 00 | 474609 | 800 | no choiceno choice | – |
| Power ascensionTests and start | SsiteSsite | –– | –– | –– | 00 | 00 | 237305 | 400 | no choiceno choice | – |
Hours are thousand hours per unit at steady state.
Why it costs less · the price of less site labor, and of speed
The model finds no price for less site labor: its cost of electricity falls at every step down in site hours. Speed has a price, and it is small.
The brief asks for as little labor as possible, above all on site, and for the quickest fleet. Each could cost something; here is what the model gives for both, under its assumptions.
The price of less site labor
Allowed fewer and fewer site hours, the model gives 114 USD/MWh at 9.0 million hours in the target case and 181 USD/MWh at 12.0 million hours in the cautious case on site per unit: the point it chooses.
the chosen point114 USD/MWh9.0 million hours on site,11.0 million hours in all places
everything on site137 USD/MWh15.4 million hours
within one percent of the lowest
the chosen point181 USD/MWh12.0 million hours on site,15.8 million hours in all places
everything on site217 USD/MWh19.4 million hours
within one percent of the lowest
← fewer site hours per unitmore →
In both cases the model gives a lower cost of electricity at every step down in site hours, from the plan with everything on site to the chosen point, so the fewest site hours is also the cheapest. The rule for the chosen point: the fewest site hours whose cost is within one percent of the lowest. Each dot is the whole problem solved again with fewer site hours allowed, at a 7% cost of money; the curve does not follow the control.
The numbers in this drawing
| Case | Cap on site hours | Site hours | Hours, all places | Cost of electricity | Years to the last unit | Chosen |
|---|---|---|---|---|---|---|
| target | 13.8 million hours | 13.0 million hours | 14.7 million hours | 126 USD/MWh | 23.9 years | |
| target | 13.0 million hours | 12.4 million hours | 14.1 million hours | 123 USD/MWh | 23.8 years | |
| target | 12.1 million hours | 11.5 million hours | 13.3 million hours | 121 USD/MWh | 23.8 years | |
| target | 11.3 million hours | 10.8 million hours | 12.6 million hours | 119 USD/MWh | 23.8 years | |
| target | 10.5 million hours | 10.0 million hours | 11.9 million hours | 117 USD/MWh | 23.8 years | |
| target | 9.7 million hours | 9.3 million hours | 11.2 million hours | 115 USD/MWh | 23.8 years | |
| target | 8.9 million hours | 9.0 million hours | 11.0 million hours | 114 USD/MWh | 23.6 years | chosen |
| cautious | 18.5 million hours | 17.9 million hours | 19.8 million hours | 204 USD/MWh | 42.5 years | |
| cautious | 17.5 million hours | 16.9 million hours | 19.1 million hours | 199 USD/MWh | 42.5 years | |
| cautious | 16.6 million hours | 16.0 million hours | 18.5 million hours | 195 USD/MWh | 42.3 years | |
| cautious | 15.6 million hours | 15.1 million hours | 18.0 million hours | 191 USD/MWh | 42.3 years | |
| cautious | 14.7 million hours | 14.2 million hours | 17.3 million hours | 188 USD/MWh | 42.3 years | |
| cautious | 13.8 million hours | 13.3 million hours | 16.6 million hours | 185 USD/MWh | 42.4 years | |
| cautious | 12.8 million hours | 12.4 million hours | 16.0 million hours | 183 USD/MWh | 42.3 years | |
| cautious | 11.9 million hours | 12.0 million hours | 15.8 million hours | 181 USD/MWh | 42.2 years | chosen |
The price of speed
At 24 vessels a year the model gives the last unit at power in 15.8 years at 117 USD/MWh; at 6 a year, in 40.3 years at 112 USD/MWh.At 24 vessels a year the model gives the last unit at power in 18.0 years at 186 USD/MWh; at 6 a year, in 42.5 years at 179 USD/MWh. Speed moves the years far more than the cost.
24 a year117 USD/MWh15.8 years
12 a year114 USD/MWh23.6 years
6 a year112 USD/MWh40.3 years
24 a year186 USD/MWh18.0 years
12 a year182 USD/MWh26.1 years
6 a year179 USD/MWh42.5 years
0
years from the order to unit 200 at power →cost of electricity at 7%, from zero
24 a year is outside the brief: it needs a second vessel line, whose capital is included. Each point is the whole problem solved again at that pace, with the factory, the ships and the vendor lines sized for it.
what the slower fleet gives up
At 6 vessels a year in place of 12, the model gives the last unit 16.5 years later and 14,702 TWh less electricity on the way, worth 588–1,470 billion USD at power prices of 40–100 USD/MWh. The cost of electricity above counts each unit from its own first day of power, so it gives no credit for being early; this is that credit.
The numbers in this drawing
| Vessels a year | Case | Years to the last unit | Cost of electricity | Note |
|---|---|---|---|---|
| 6 | target | 40.3 years | 112 USD/MWh | |
| 6 | cautious | 42.5 years | 179 USD/MWh | |
| 12 | target | 23.6 years | 114 USD/MWh | |
| 12 | cautious | 26.1 years | 182 USD/MWh | |
| 24 | target | 15.8 years | 117 USD/MWh | outside the brief: needs a second vessel line |
| 24 | cautious | 18.0 years | 186 USD/MWh | outside the brief: needs a second vessel line |
How far to trust the answer
This is the best plan the model found, not one proved best. Every plan drawn by hand comes out at least as dear.
All on site
137.0 USD/MWh217.1 USD/MWh
As Vogtle was built
227.9 USD/MWh252.0 USD/MWh
The model’s split of work, every vendor part straight to the site
114.2 USD/MWh181.6 USD/MWh
The model’s split of work, every vendor part through Progreso
114.2 USD/MWh182.0 USD/MWh
The model’s answer, the site started as late as possible
114.2 USD/MWh181.5 USD/MWh
The model’s answer, the site started early enough to have all other work done when the vessel arrives
119.2 USD/MWh190.7 USD/MWh
Most to Progreso, shipped in pieces
115.3 USD/MWh183.9 USD/MWh
Everything to Progreso, shipped complete
114.3 USD/MWh182.5 USD/MWh
The model’s answer
114.2 USD/MWh181.5 USD/MWh
← cheapercost of electricity at 7%, to one decimal so that near ties can be told apartdearer →
With the model’s split of work between factory and site kept, sending every vendor part straight to the site gives 114.2 USD/MWh (181.6 USD/MWh cautious) and sending every one through Progreso gives 114.2 USD/MWh (182.0 USD/MWh cautious), against 114.2 USD/MWh (181.5 USD/MWh cautious) for the model’s own mix; starting every site early enough to have all other work done when the vessel arrives gives 119.2 USD/MWh (190.7 USD/MWh cautious).
When one of the inputs that set where work is cheapest moves by 20%, the model changes its choice for containment bottom head and containment rings in the target case; every other package stays where it is. In the cautious case it changesWhen one of those inputs moves by 20%, the model changes its choice for basemat rebar cages, containment bottom head, containment rings, containment top head, structural modules CA01, CA02 to CA05, CA20 and head package and control rod drives. The cost of money moves containment bottom head, containment rings, reactor vessel, steam generators, turbine generator, basemat rebar cages, coolant pumps and structural modules CA01, CA02 to CA05, CA20 in the target case.
The checks in full: the plans drawn by hand, what flips, how the answer was reached
| Plan | Case | Cost of electricity | Site hours per unit |
|---|---|---|---|
| All on site | target | 137.0 USD/MWh | 15.4 million hours |
| As Vogtle was built | target | 227.9 USD/MWh | 25.0 million hours |
| The model’s split of work, every vendor part straight to the site | target | 114.2 USD/MWh | 9.0 million hours |
| The model’s split of work, every vendor part through Progreso | target | 114.2 USD/MWh | 9.0 million hours |
| The model’s answer, the site started as late as possible | target | 114.2 USD/MWh | 9.0 million hours |
| The model’s answer, the site started early enough to have all other work done when the vessel arrives | target | 119.2 USD/MWh | 9.3 million hours |
| Most to Progreso, shipped in pieces | target | 115.3 USD/MWh | 9.4 million hours |
| Everything to Progreso, shipped complete | target | 114.3 USD/MWh | 8.9 million hours |
| The model’s answer | target | 114.2 USD/MWh | 9.0 million hours |
| All on site | cautious | 217.1 USD/MWh | 19.4 million hours |
| As Vogtle was built | cautious | 252.0 USD/MWh | 25.0 million hours |
| The model’s split of work, every vendor part straight to the site | cautious | 181.6 USD/MWh | 12.0 million hours |
| The model’s split of work, every vendor part through Progreso | cautious | 182.0 USD/MWh | 12.0 million hours |
| The model’s answer, the site started as late as possible | cautious | 181.5 USD/MWh | 12.0 million hours |
| The model’s answer, the site started early enough to have all other work done when the vessel arrives | cautious | 190.7 USD/MWh | 12.2 million hours |
| Most to Progreso, shipped in pieces | cautious | 183.9 USD/MWh | 12.5 million hours |
| Everything to Progreso, shipped complete | cautious | 182.5 USD/MWh | 11.8 million hours |
| The model’s answer | cautious | 181.5 USD/MWh | 12.0 million hours |
| Case | Input moved | By | Choices that change |
|---|---|---|---|
| target | Shop against site hours, outfittingShop against site hours, plate and rebarProgreso wageSite wageShippingRobot cellsNew shop at Progreso | 20% lower20% lower20% higher20% lower20% dearer20% dearerhours 20% higher | Containment bottom head (site, parts through Progreso → bare, complete)Containment rings (tested, pieces → tested, complete) |
| cautious | Shop against site hours, outfittingShop against site hours, plate and rebarProgreso wageSite wageShippingRobot cellsNew shop at Progreso | 20% lower20% lower20% higher20% lower20% dearer20% dearerhours 20% higher | Basemat rebar cages (site → bare, complete)Containment bottom head (site → bare, complete)Containment rings (bare, complete → tested, complete)Containment top head (tested, complete → tested, pieces)Structural modules CA01, CA02 to CA05, CA20 (fitted out, complete → tested, complete)Head package and control rod drives (site, parts through Progreso → site, parts straight to the site) |
| Case | Rounds until the plan stopped changing | Settled | Choices that change with the cost of money |
|---|---|---|---|
| target | 2 rounds | yes | Containment bottom head: bare/complete at 0%, site, parts through Progreso at 7%Containment rings: tested/complete at 0%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 0%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 0%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 0.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 0.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 1%, site, parts through Progreso at 7%Containment rings: tested/complete at 1%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 1%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 1.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 1.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 2%, site, parts through Progreso at 7%Containment rings: tested/complete at 2%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 2%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 2%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 2%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 2.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 2.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 3%, site, parts through Progreso at 7%Containment rings: tested/complete at 3%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 3%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 3%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 3.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 3.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 4%, site, parts through Progreso at 7%Containment rings: tested/complete at 4%, tested/pieces at 7%Containment bottom head: bare/complete at 4.5%, site, parts through Progreso at 7%Reactor vessel: site, parts through Progreso at 4.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 5%, site, parts through Progreso at 7%Reactor vessel: site, parts through Progreso at 5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 5.5%, site, parts through Progreso at 7%Containment bottom head: bare/complete at 6%, site, parts through Progreso at 7%Basemat rebar cages: site at 8.5%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 8.5%, site, parts through Progreso at 7%Containment rings: bare/complete at 8.5%, tested/pieces at 7%Basemat rebar cages: site at 9%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 9%, site, parts through Progreso at 7%Containment rings: bare/complete at 9%, tested/pieces at 7%Steam generators: site, parts through Progreso at 9%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 9%, site, parts through Progreso at 7%Basemat rebar cages: site at 9.5%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Containment rings: bare/complete at 9.5%, tested/pieces at 7%Steam generators: site, parts through Progreso at 9.5%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Basemat rebar cages: site at 10%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 10%, site, parts through Progreso at 7%Containment rings: bare/complete at 10%, tested/pieces at 7%Structural modules CA01, CA02 to CA05, CA20: fitted out/complete at 10%, tested/complete at 7%Steam generators: site, parts through Progreso at 10%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 10%, site, parts through Progreso at 7% |
| cautious | 3 rounds | yes | Basemat rebar cages: bare/complete at 0%, site at 7%Containment bottom head: bare/complete at 0%, site at 7%Containment rings: fitted out/complete at 0%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 0%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 0%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 0%, site at 7%Turbine generator: site, parts through Progreso at 0%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 0.5%, site at 7%Containment bottom head: bare/complete at 0.5%, site at 7%Containment rings: fitted out/complete at 0.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 0.5%, site at 7%Turbine generator: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 1%, site at 7%Containment bottom head: bare/pieces at 1%, site at 7%Containment rings: tested/complete at 1%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 1%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 1%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 1%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 1.5%, site at 7%Containment bottom head: bare/pieces at 1.5%, site at 7%Containment rings: tested/complete at 1.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 2%, site at 7%Containment bottom head: bare/pieces at 2%, site at 7%Containment rings: tested/complete at 2%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2%, fitted out/complete at 7%Steam generators: site, parts through Progreso at 2%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 2%, site at 7%Transformers: site, parts through Progreso at 2%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 2.5%, site at 7%Containment bottom head: bare/pieces at 2.5%, site at 7%Containment rings: tested/complete at 2.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 3%, site at 7%Containment bottom head: bare/pieces at 3%, site at 7%Containment rings: tested/complete at 3%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 3%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 3%, site, parts straight to the site at 7%Moisture separator reheaters: site, parts through Progreso at 3%, site, parts straight to the site at 7%Containment bottom head: bare/pieces at 3.5%, site at 7%Containment rings: fitted out/pieces at 3.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 3.5%, site at 7%Transformers: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Reactor vessel: site, parts through Progreso at 4%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 4%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 4%, site at 7%Coolant pumps: site, parts through Progreso at 4.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 4.5%, site at 7%Coolant pumps: site, parts through Progreso at 5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 5%, site at 7%Passive safety tanks and heat exchanger: tested/complete at 5.5%, site at 7%Moisture separator reheaters: site, parts through Progreso at 5.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 6%, site at 7%Moisture separator reheaters: site, parts through Progreso at 6%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 6.5%, site, parts straight to the site at 7%Head package and control rod drives: site, parts straight to the site at 6.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 7.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 7.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 8%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 8%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 8.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 8.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 9%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 9%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 9.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 10%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 10%, site, parts through Progreso at 7% |
Each round solves a mixed integer program to zero gap and then evaluates its answer exactly; after the last round every single change of one package is tried on the exact model and kept only if it lowers the cost. That finds a good answer and rules out its neighbours. It does not prove that no better one exists.
The price · cost
Before any interest, the model gives the average unit a cost of 7,360 USD/kW10,280 USD/kW.
This cost before interest is called the overnight cost: what a unit would cost if it were built in a night. At a 7% cost of money, interest raises it to 9,050 USD/kW14,210 USD/kW. In 2025 dollars for each kW of output, under the model’s assumptions.
Cost before interest, line by line
The largest line is vendor hardware and materials: the model gives 2,200 USD/kW2,630 USD/kW.
Contingency, an allowance for the plan running over, adds 980 USD/kW2,280 USD/kW. Each bar starts where the one above ends, a saving runs back to the left, and the last bar is their sum.
VVendor hardware and materialsJ
2,200
2,630
PProgreso laborT
10
90
PShippingJ
20
30
SSite labor, craft and supportV
980
1,410
SSite staff, crane and general conditionsJ
740
1,300
SConstruction equipment, temporary works, feeJ
540
810
SCrew travel, site design, waitingJ
10
40
VRouting of vendor parts: detours, defects caught early, waits for late partsJ
−10
30
Owner’s cost: licensing, staff, training, connectionJ
420
700
First fuel coreD
330
340
Not allocated (Vogtle remainder)V
990
230
VVendor dedicated linesJ
50
70
PProgreso, robots, ships, design, management (even share)J
100
320
ContingencyJ
980
2,280
Cost before interest
7,360
10,280
DdocumentedVderivedJjudgedTtarget
Every line at unit 1, on average and at unit 200
| Line | Place | Grade | Unit 1 | Fleet average | Unit 200 |
|---|---|---|---|---|---|
| Vendor hardware and materials | vendor | judged | 2,760 | 2,200 | 2,090 |
| Progreso labor | Progreso | target | 20 | 10 | 10 |
| Shipping | Progreso | judged | 20 | 20 | 20 |
| Site labor, craft and support | site | derived | 1,150 | 980 | 880 |
| Site staff, crane and general conditions | site | judged | 940 | 740 | 680 |
| Construction equipment, temporary works, fee | site | judged | 640 | 540 | 490 |
| Crew travel, site design, waiting | site | judged | 10 | 10 | 10 |
| Routing of vendor parts: detours, defects caught early, waits for late parts | vendor | judged | −20 | −10 | −10 |
| Owner’s cost: licensing, staff, training, connection | not one place | judged | 420 | 420 | 420 |
| First fuel core | not one place | documented | 330 | 330 | 330 |
| Not allocated (Vogtle remainder) | not one place | derived | 990 | 990 | 990 |
| Vendor dedicated lines | vendor | judged | 50 | 50 | 50 |
| Progreso, robots, ships, design, management (even share) | Progreso | judged | 100 | 100 | 100 |
| Contingency | not one place | judged | 2,010 | 980 | 850 |
| Cost before interest | 9,440 | 7,360 | 6,910 |
| Line | Place | Grade | Unit 1 | Fleet average | Unit 200 |
|---|---|---|---|---|---|
| Vendor hardware and materials | vendor | judged | 2,970 | 2,630 | 2,560 |
| Progreso labor | Progreso | target | 230 | 90 | 80 |
| Shipping | Progreso | judged | 30 | 30 | 30 |
| Site labor, craft and support | site | derived | 1,590 | 1,410 | 1,330 |
| Site staff, crane and general conditions | site | judged | 1,600 | 1,300 | 1,220 |
| Construction equipment, temporary works, fee | site | judged | 930 | 810 | 760 |
| Crew travel, site design, waiting | site | judged | 40 | 40 | 40 |
| Routing of vendor parts: detours, defects caught early, waits for late parts | vendor | judged | 30 | 30 | 30 |
| Owner’s cost: licensing, staff, training, connection | not one place | judged | 700 | 700 | 700 |
| First fuel core | not one place | documented | 340 | 340 | 340 |
| Not allocated (Vogtle remainder) | not one place | derived | 230 | 230 | 230 |
| Vendor dedicated lines | vendor | judged | 70 | 70 | 70 |
| Progreso, robots, ships, design, management (even share) | Progreso | judged | 320 | 320 | 320 |
| Contingency | not one place | judged | 4,190 | 2,280 | 2,060 |
| Cost before interest | 13,280 | 10,280 | 9,770 |
Unit 1 to unit 200
With repetition, the model brings the last unit down to 6,910 USD/kW9,770 USD/kW.
The first unit costs 9,440 USD/kW13,280 USD/kW, before interest.
9,440
8,290
7,200
6,910
13,280
11,480
10,110
9,770
unit 110100200USD/kW, before interest. Learning acts on hours, never on materials, and stops at a floor. Each step to the right is ten times as many units.
The numbers in this drawing
| Unit | target case | cautious case |
|---|---|---|
| 1 | 9,440 | 13,280 |
| 2 | 9,020 | 12,620 |
| 5 | 8,540 | 11,840 |
| 10 | 8,290 | 11,480 |
| 20 | 7,970 | 11,040 |
| 50 | 7,540 | 10,490 |
| 100 | 7,200 | 10,110 |
| 150 | 7,050 | 9,910 |
| 200 | 6,910 | 9,770 |
What interest adds
At 7%, the model adds 1,550 USD/kW3,310 USD/kW of interest during the build.
Interest on the program’s own capital adds 150 USD/kW620 USD/kW.
target case, with all interest9,050 USD/kW
- cost before interest
- 7,360 USD/kW
- interest during the build
- 1,550 USD/kW
- interest on the program’s own capital
- 150 USD/kW
cautious case, with all interest14,210 USD/kW
- cost before interest
- 10,280 USD/kW
- interest during the build
- 3,310 USD/kW
- interest on the program’s own capital
- 620 USD/kW
The program’s own capital is Progreso, the ships, the design and the vendors’ lines. Its interest runs from the day each was paid for until each unit is delivered.
The same at every cost of money
| Cost of money | Before interest | Interest during the build | Interest on program capital | With all interest |
|---|---|---|---|---|
| 0%, to check the sums | 7,310 | 0 | 0 | 7,310 |
| 0.5% | 7,310 | 100 | 10 | 7,430 |
| 1% | 7,310 | 210 | 20 | 7,540 |
| 1.5% | 7,310 | 320 | 30 | 7,660 |
| 2% | 7,310 | 430 | 30 | 7,770 |
| 2.5% | 7,310 | 540 | 40 | 7,890 |
| 3% | 7,310 | 650 | 50 | 8,020 |
| 3.5% | 7,310 | 760 | 70 | 8,140 |
| 4% | 7,320 | 880 | 70 | 8,270 |
| 4.5% | 7,330 | 980 | 90 | 8,390 |
| 5% | 7,330 | 1,100 | 100 | 8,520 |
| 5.5% | 7,330 | 1,220 | 110 | 8,650 |
| 6% | 7,330 | 1,340 | 120 | 8,790 |
| 6.5% | 7,360 | 1,430 | 130 | 8,920 |
| 7% | 7,360 | 1,550 | 150 | 9,050 |
| 7.5% | 7,360 | 1,670 | 160 | 9,190 |
| 8% | 7,360 | 1,790 | 180 | 9,330 |
| 8.5% | 7,360 | 1,920 | 190 | 9,480 |
| 9% | 7,360 | 2,050 | 210 | 9,620 |
| 9.5% | 7,360 | 2,180 | 230 | 9,760 |
| 10% | 7,370 | 2,300 | 240 | 9,910 |
| Cost of money | Before interest | Interest during the build | Interest on program capital | With all interest |
|---|---|---|---|---|
| 0%, to check the sums | 10,220 | 0 | 0 | 10,220 |
| 0.5% | 10,220 | 210 | 30 | 10,450 |
| 1% | 10,220 | 430 | 60 | 10,700 |
| 1.5% | 10,220 | 640 | 90 | 10,960 |
| 2% | 10,230 | 870 | 120 | 11,220 |
| 2.5% | 10,220 | 1,100 | 160 | 11,480 |
| 3% | 10,220 | 1,330 | 200 | 11,760 |
| 3.5% | 10,260 | 1,540 | 240 | 12,030 |
| 4% | 10,270 | 1,770 | 280 | 12,330 |
| 4.5% | 10,280 | 2,020 | 320 | 12,620 |
| 5% | 10,280 | 2,260 | 380 | 12,920 |
| 5.5% | 10,280 | 2,520 | 430 | 13,230 |
| 6% | 10,280 | 2,770 | 490 | 13,540 |
| 6.5% | 10,280 | 3,040 | 550 | 13,870 |
| 7% | 10,280 | 3,310 | 620 | 14,210 |
| 7.5% | 10,280 | 3,580 | 690 | 14,550 |
| 8% | 10,280 | 3,860 | 760 | 14,910 |
| 8.5% | 10,280 | 4,150 | 840 | 15,280 |
| 9% | 10,280 | 4,440 | 930 | 15,650 |
| 9.5% | 10,280 | 4,740 | 1,020 | 16,040 |
| 10% | 10,280 | 5,040 | 1,110 | 16,440 |
What is counted
The model’s figure counts more than the published ones it stands beside: the first fuel, the owner’s cost, a contingency and the program’s own capital are inside it.
- this model
- 7,360 USD/kW10,280 USD/kW
- Vogtle, as built
- 15,390 USD/kW
- The next pair
- 9,590 USD/kW
- A mature plant
- 4,820 USD/kW
What each figure counts, line by line
Interest during the build
this modelleft out of this figure; shown beside it
Vogtle, as builtleft out
published estimatesleft out
Progreso, robots, ships, design and management
this modelcounted at what was spent, an even share for every unit, without interest
Vogtle, as builtits own first design and licence are inside the figure
published estimatesno factory; design taken as done
Vendors’ dedicated lines
this modelcounted the same way, at what was spent
Vogtle, as builtnone
published estimatesnone
Owner’s cost
this modelcounted
Vogtle, as builtcounted
published estimatescounted
First fuel core
this modelcounted
Vogtle, as builtnot stated
published estimatesnot stated
Contingency
this modelcounted, as an expected overrun on the plan
Vogtle, as builtits overruns are in the figure, as built
published estimatesleft out; the authors add a quarter
The part of Vogtle’s cost the packages do not explain
this modelcounted, unchanged
Vogtle, as builtinside the figure
published estimatesdoes not arise
The model puts neither case below the published estimate for a mature plant; had it, that would be flagged here and at the top of the page.
Published figures are from MIT and Idaho National Laboratory, put into 2025 dollars with one price index.
The price · LCOE
At a 7% cost of money, the model gives electricity from the average unit at 114 USD/MWh181 USD/MWh.
This is the levelized cost of electricity, LCOE: every dollar spent over a plant’s life divided by every MWh it makes, both discounted at the cost of money. Real, before income tax, under the model’s assumptions.
Average unit LCOE against the cost of money
Dearer money moves capital and its interest; running the plant and fuelling it barely change.
When money costs 3% the model gives 72 USD/MWh111 USD/MWh. At 10% it gives 155 USD/MWh257 USD/MWh.
target case
114USD/MWh at 7%
- the program’s own capital, with its interest
- 3 USD/MWh
- interest during the build
- 13 USD/MWh
- building the unit, before interest
- 62 USD/MWh
- spent fuel and property tax
- 3 USD/MWh
- fuel
- 10 USD/MWh
- operation
- 24 USD/MWh
cautious case
181USD/MWh at 7%
- the program’s own capital, with its interest
- 9 USD/MWh
- interest during the build
- 29 USD/MWh
- building the unit, before interest
- 86 USD/MWh
- spent fuel and property tax
- 5 USD/MWh
- fuel
- 11 USD/MWh
- operation
- 42 USD/MWh
The soft band is where four in five of the model’s runs fall when every uncertain input is drawn at random within its range, with the middle run dotted: a spread from the stated ranges, not a probability. The thin lines are published plants run through this model. At 0% the figures only check the sums.
The published plants, at the chosen cost of money
| Plant | Cost before interest | Build | LCOE at 7%, target operation | LCOE at 7%, cautious operation |
|---|---|---|---|---|
| Vogtle as builtabout 15,000 USD/kW in 2024 dollars (MIT 2024) | 15,390 USD/kW | 125 months | 228 USD/MWh | 252 USD/MWh |
| The next AP1000 pair, published estimateMIT 2024: 8,300 to 10,400 USD/kW, 80 to 96 months | 9,590 USD/kW | 88 months | 143 USD/MWh | 166 USD/MWh |
| A mature AP1000, published estimateMIT 2024 and Idaho National Laboratory 2025: 4,600 to 4,750 USD/kW, 50 months | 4,820 USD/kW | 50 months | 84 USD/MWh | 107 USD/MWh |
| Barakah, as builtMIT 2018 restated figure, 2017 dollars; scope uncertain | 5,160 USD/kW | 100 months | 96 USD/MWh | 118 USD/MWh |
| Shin Kori 3 and 4, as builtIEA/NEA 2020, 2018 dollars; durations include policy halts | 3,040 USD/kW | 100 months | 72 USD/MWh | 94 USD/MWh |
Each plant is its published capital cost and build time, spent evenly over the build, with this model’s operating cost: the target case’s beside the target case, the cautious case’s beside the cautious case. So within each pairing only capital and time differ.
The numbers in this drawing
| Cost of money | Average unit | Runs: one in ten below | Runs: middle | Runs: one in ten above | operation | fuel | spent fuel and property tax | building the unit, before interest | interest during the build | the program’s own capital, with its interest |
|---|---|---|---|---|---|---|---|---|---|---|
| 0%, to check the sums | 52 | 59 | 65 | 71 | 24 | 10 | 3 | 15 | 0 | 0 |
| 0.5% | 55 | 62 | 69 | 75 | 24 | 10 | 3 | 17 | 0 | 0 |
| 1% | 58 | 66 | 72 | 79 | 24 | 10 | 3 | 20 | 1 | 0 |
| 1.5% | 61 | 70 | 76 | 83 | 24 | 10 | 3 | 22 | 1 | 1 |
| 2% | 64 | 74 | 81 | 87 | 24 | 10 | 3 | 25 | 1 | 1 |
| 2.5% | 68 | 79 | 86 | 93 | 24 | 10 | 3 | 28 | 2 | 1 |
| 3% | 72 | 83 | 91 | 98 | 24 | 10 | 3 | 31 | 3 | 1 |
| 3.5% | 77 | 89 | 96 | 104 | 24 | 10 | 3 | 35 | 4 | 1 |
| 4% | 81 | 94 | 102 | 111 | 24 | 10 | 3 | 38 | 5 | 1 |
| 4.5% | 86 | 100 | 109 | 118 | 24 | 10 | 3 | 42 | 6 | 1 |
| 5% | 91 | 106 | 115 | 125 | 24 | 10 | 3 | 46 | 7 | 2 |
| 5.5% | 97 | 112 | 122 | 133 | 24 | 10 | 3 | 50 | 8 | 2 |
| 6% | 102 | 119 | 130 | 141 | 24 | 10 | 3 | 54 | 10 | 2 |
| 6.5% | 108 | 126 | 138 | 150 | 24 | 10 | 3 | 58 | 11 | 2 |
| 7% | 114 | 133 | 146 | 159 | 24 | 10 | 3 | 62 | 13 | 3 |
| 7.5% | 120 | 141 | 154 | 169 | 24 | 10 | 3 | 66 | 15 | 3 |
| 8% | 127 | 149 | 163 | 178 | 24 | 10 | 3 | 70 | 17 | 3 |
| 8.5% | 134 | 157 | 172 | 189 | 24 | 10 | 3 | 74 | 20 | 3 |
| 9% | 140 | 165 | 181 | 200 | 24 | 10 | 3 | 78 | 22 | 4 |
| 9.5% | 148 | 174 | 191 | 211 | 24 | 9 | 3 | 82 | 25 | 4 |
| 10% | 155 | 182 | 201 | 223 | 24 | 9 | 3 | 86 | 27 | 5 |
| Cost of money | Vogtle as built | The next AP1000 pair | A mature AP1000 | Barakah | Shin Kori 3 and 4 |
|---|---|---|---|---|---|
| 0% | 69 | 57 | 47 | 48 | 43 |
| 0.5% | 75 | 60 | 49 | 50 | 45 |
| 1% | 81 | 64 | 51 | 52 | 46 |
| 1.5% | 89 | 69 | 53 | 54 | 47 |
| 2% | 97 | 73 | 55 | 57 | 49 |
| 2.5% | 106 | 79 | 57 | 60 | 50 |
| 3% | 116 | 84 | 60 | 63 | 52 |
| 3.5% | 127 | 90 | 62 | 66 | 54 |
| 4% | 139 | 97 | 65 | 70 | 56 |
| 4.5% | 151 | 103 | 68 | 73 | 58 |
| 5% | 165 | 111 | 71 | 78 | 61 |
| 5.5% | 179 | 118 | 74 | 82 | 63 |
| 6% | 195 | 126 | 77 | 86 | 66 |
| 6.5% | 211 | 134 | 81 | 91 | 69 |
| 7% | 228 | 143 | 84 | 96 | 72 |
| 7.5% | 246 | 152 | 88 | 101 | 75 |
| 8% | 265 | 161 | 92 | 107 | 78 |
| 8.5% | 285 | 171 | 95 | 112 | 81 |
| 9% | 306 | 181 | 99 | 118 | 85 |
| 9.5% | 328 | 191 | 103 | 124 | 88 |
| 10% | 351 | 202 | 107 | 130 | 92 |
| Cost of money | Average unit | Runs: one in ten below | Runs: middle | Runs: one in ten above | operation | fuel | spent fuel and property tax | building the unit, before interest | interest during the build | the program’s own capital, with its interest |
|---|---|---|---|---|---|---|---|---|---|---|
| 0%, to check the sums | 80 | 59 | 65 | 71 | 41 | 12 | 5 | 20 | 0 | 1 |
| 0.5% | 84 | 62 | 69 | 75 | 41 | 12 | 5 | 24 | 1 | 1 |
| 1% | 88 | 66 | 72 | 79 | 41 | 12 | 5 | 27 | 1 | 1 |
| 1.5% | 93 | 70 | 76 | 83 | 41 | 12 | 5 | 31 | 2 | 2 |
| 2% | 99 | 74 | 81 | 87 | 41 | 12 | 5 | 35 | 3 | 2 |
| 2.5% | 104 | 79 | 86 | 93 | 41 | 12 | 5 | 39 | 4 | 2 |
| 3% | 111 | 83 | 91 | 98 | 41 | 12 | 5 | 44 | 6 | 3 |
| 3.5% | 118 | 89 | 96 | 104 | 41 | 12 | 5 | 49 | 8 | 3 |
| 4% | 125 | 94 | 102 | 111 | 41 | 12 | 5 | 54 | 10 | 4 |
| 4.5% | 133 | 100 | 109 | 118 | 41 | 12 | 5 | 59 | 12 | 4 |
| 5% | 142 | 106 | 115 | 125 | 41 | 12 | 5 | 64 | 15 | 5 |
| 5.5% | 151 | 112 | 122 | 133 | 41 | 12 | 5 | 69 | 18 | 6 |
| 6% | 161 | 119 | 130 | 141 | 42 | 12 | 5 | 75 | 21 | 7 |
| 6.5% | 171 | 126 | 138 | 150 | 42 | 11 | 5 | 80 | 25 | 8 |
| 7% | 181 | 133 | 146 | 159 | 42 | 11 | 5 | 86 | 29 | 9 |
| 7.5% | 193 | 141 | 154 | 169 | 42 | 11 | 5 | 91 | 33 | 10 |
| 8% | 204 | 149 | 163 | 178 | 42 | 11 | 5 | 97 | 38 | 11 |
| 8.5% | 217 | 157 | 172 | 189 | 42 | 11 | 5 | 103 | 43 | 13 |
| 9% | 230 | 165 | 181 | 200 | 42 | 11 | 5 | 108 | 49 | 14 |
| 9.5% | 243 | 174 | 191 | 211 | 42 | 11 | 5 | 114 | 55 | 16 |
| 10% | 257 | 182 | 201 | 223 | 42 | 11 | 5 | 120 | 61 | 18 |
| Cost of money | Vogtle as built | The next AP1000 pair | A mature AP1000 | Barakah | Shin Kori 3 and 4 |
|---|---|---|---|---|---|
| 0% | 91 | 79 | 69 | 69 | 65 |
| 0.5% | 97 | 82 | 70 | 71 | 66 |
| 1% | 103 | 86 | 72 | 74 | 67 |
| 1.5% | 111 | 91 | 74 | 76 | 69 |
| 2% | 119 | 95 | 77 | 79 | 70 |
| 2.5% | 129 | 101 | 79 | 81 | 72 |
| 3% | 139 | 106 | 81 | 85 | 74 |
| 3.5% | 150 | 112 | 84 | 88 | 76 |
| 4% | 162 | 119 | 87 | 92 | 78 |
| 4.5% | 174 | 126 | 90 | 96 | 80 |
| 5% | 188 | 133 | 93 | 100 | 83 |
| 5.5% | 203 | 141 | 96 | 104 | 85 |
| 6% | 218 | 149 | 100 | 109 | 88 |
| 6.5% | 235 | 157 | 103 | 113 | 91 |
| 7% | 252 | 166 | 107 | 118 | 94 |
| 7.5% | 270 | 175 | 110 | 124 | 97 |
| 8% | 290 | 185 | 114 | 129 | 100 |
| 8.5% | 310 | 195 | 118 | 135 | 103 |
| 9% | 331 | 205 | 122 | 141 | 107 |
| 9.5% | 354 | 215 | 126 | 147 | 111 |
| 10% | 377 | 226 | 130 | 153 | 114 |
Unit by unit, at 7%
For the first unit the model gives 143 USD/MWh232 USD/MWh.
For the last it gives 109 USD/MWh174 USD/MWh.
- unit 1
- 143 USD/MWh232 USD/MWh
- unit 100
- 112 USD/MWh179 USD/MWh
- unit 200
- 109 USD/MWh174 USD/MWh
- average unit
- 114 USD/MWh181 USD/MWh
- the fleet, from the order date
- 116 USD/MWh186 USD/MWh
The average counts each unit from its own first day of power and charges it an equal fee that repays the program’s capital: what the buyer of a plant pays. The fleet figure discounts the whole program to the day of the order.
Beside every LCOE
LCOE does not see time.
A ratio of discounted sums is the same for a fast and a slow fleet of equal plants. So the years from the order to unit 200 always stand beside it: 23.6 years42.2 years.
Against the same fleet at 12 vessels a year, the model has the cautious case finish 16.5 years later. On the way it makes 14,702 TWh less electricity.
How sure · sensitivity
The model gives 114 USD/MWh181 USD/MWh; this is what moves those numbers, and how far.
Every figure in this section is at a 7% cost of money, whatever the control says. Each case keeps the allocation of work it chose at that rate.
One input at a time
Vogtle cost before interest moves the target case most: the model gives 104–125 USD/MWh across its range. Shifts worked on site moves the cautious case most: the model gives 170–199 USD/MWh across its range.
One input is moved from the low end of its range to the high end while the rest stay put. The 8 widest are drawn; the rest are in the table.
Shifts worked on siteJ
1.0–2.0 shifts
111125170199Vogtle cost before interestD
13,850–16,930 USD/kW
104125174194Staff, upkeep and capital spent during lifeT
170–330 USD/kW a year
112131163183Learning of site crews, per doublingT
0–10%
113121173192Hardware and materials, share of Vogtle’s costJ
14–28%
179196Engineering, licensing and home office, share of Vogtle’s costJ
15–30%
106123180192Contingency common to the whole programJ
5–20%
111120172186Removed as particular to Vogtle (L1)T
1,590–3,256 USD/kW
123169
DdocumentedVderivedJjudgedTtarget
Every input tried, with its range and both ends
| Input | Grade | Low end | High end | Unit | LCOE at the low end | LCOE at the high end |
|---|---|---|---|---|---|---|
| Vogtle cost before interest | documented | 13,850 | 16,930 | USD/kW | 104 | 125 |
| Staff, upkeep and capital spent during life | target | 170 | 330 | USD/kW a year | 112 | 131 |
| Engineering, licensing and home office, share of Vogtle’s cost | judged | 15 | 30 | % | 123 | 106 |
| Shifts worked on site | judged | 1.0 | 2.0 | shifts | 125 | 111 |
| Learning on vendor lines, per doubling | target | 0 | 8 | % | 122 | 112 |
| Contingency common to the whole program | judged | 5 | 20 | % | 111 | 120 |
| Removed as particular to Vogtle (L1) | target | 1,590 | 3,256 | USD/kW | 123 | 114 |
| Learning of site crews, per doubling | target | 0 | 10 | % | 121 | 113 |
| Owner’s cost, share of Vogtle’s cost | documented | 10 | 16 | % | 118 | 110 |
| Owner’s cost: licensing, owner staff, training, spares, connection | judged | 300 | 900 | USD/kW | 113 | 120 |
| Fuel | derived | 7.0 | 13.0 | USD/MWh | 111 | 116 |
| Spent fuel | documented | 1 | 3 | USD/MWh | 114 | 116 |
| Lowest hours, share of unit 1 | judged | 40 | 70 | % | 114 | 115 |
| Input | Grade | Low end | High end | Unit | LCOE at the low end | LCOE at the high end |
|---|---|---|---|---|---|---|
| Shifts worked on site | judged | 1.0 | 2.0 | shifts | 199 | 170 |
| Staff, upkeep and capital spent during life | target | 170 | 330 | USD/kW a year | 163 | 183 |
| Vogtle cost before interest | documented | 13,850 | 16,930 | USD/kW | 174 | 194 |
| Learning of site crews, per doubling | target | 0 | 10 | % | 192 | 173 |
| Hardware and materials, share of Vogtle’s cost | judged | 14 | 28 | % | 179 | 196 |
| Contingency common to the whole program | judged | 5 | 20 | % | 172 | 186 |
| Removed as particular to Vogtle (L1) | target | 1,590 | 3,256 | USD/kW | 181 | 169 |
| Learning on vendor lines, per doubling | target | 0 | 8 | % | 187 | 175 |
| Engineering, licensing and home office, share of Vogtle’s cost | judged | 15 | 30 | % | 192 | 180 |
| Contingency per unit, at the end | judged | 2 | 15 | % | 175 | 185 |
| Fuel | derived | 7.0 | 13.0 | USD/MWh | 176 | 182 |
| Spent fuel | documented | 1 | 3 | USD/MWh | 180 | 182 |
| Lowest hours, share of unit 1 | judged | 40 | 70 | % | 181 | 182 |
Every input at once · a spread from the stated ranges, not a probability
The target case falls below nine runs in ten and theThe cautious case above nine runs in ten: the two cases are corners, not the middle.
The model is run many times with every uncertain input drawn at random within its range, one set of runs for both cases. Four runs in five fall between 133–159 USD/MWh.
the middle of the range146 USD/MWh
the middle of the range146 USD/MWh
the target case itself114 USD/MWh
the cautious case itself181 USD/MWh
The ranges had to be wide enough for the first unit’s cost to reach the published cost of the next AP1000 pair; they were, so none was widened. Along the bottom, USD/MWh; the heights show how many runs fall at each value and carry no scale.
The runs, counted
| From, USD/MWh | Draws |
|---|---|
| 110 | 1 |
| 112 | 0 |
| 114 | 4 |
| 116 | 3 |
| 118 | 16 |
| 120 | 33 |
| 122 | 49 |
| 125 | 85 |
| 127 | 157 |
| 129 | 208 |
| 131 | 297 |
| 133 | 434 |
| 135 | 479 |
| 137 | 556 |
| 139 | 682 |
| 141 | 778 |
| 143 | 810 |
| 145 | 780 |
| 147 | 801 |
| 149 | 696 |
| 151 | 681 |
| 153 | 564 |
| 155 | 453 |
| 157 | 374 |
| 159 | 332 |
| 161 | 204 |
| 163 | 149 |
| 165 | 131 |
| 167 | 95 |
| 169 | 148 |
| From, USD/MWh | Draws |
|---|---|
| 110 | 1 |
| 112 | 0 |
| 114 | 4 |
| 116 | 3 |
| 118 | 16 |
| 120 | 33 |
| 122 | 49 |
| 125 | 85 |
| 127 | 157 |
| 129 | 208 |
| 131 | 297 |
| 133 | 434 |
| 135 | 479 |
| 137 | 556 |
| 139 | 682 |
| 141 | 778 |
| 143 | 810 |
| 145 | 780 |
| 147 | 801 |
| 149 | 696 |
| 151 | 681 |
| 153 | 564 |
| 155 | 453 |
| 157 | 374 |
| 159 | 332 |
| 161 | 204 |
| 163 | 149 |
| 165 | 131 |
| 167 | 95 |
| 169 | 148 |
What would have to be true
The model reaches none of 60, 80 or 100 USD/MWh by moving any single input within its range.
Not reached even with these eight inputs at the favourable end of their ranges together (the model then gives 101 USD/MWh).
Not reached even with these eight inputs at the favourable end of their ranges together (the model then gives 112 USD/MWh).
The inputs tried, and their cautious values
| Input | Unit | Cautious value | Needed for 60 USD/MWh | Needed for 80 USD/MWh | Needed for 100 USD/MWh |
|---|---|---|---|---|---|
| Vogtle cost before interest | USD/kW | 15,390 | not reached at any value | not reached at any value | not reached at any value |
| Staff, upkeep and capital spent during life | USD/kW a year | 317 | not reached at any value | not reached at any value | not reached at any value |
| Engineering, licensing and home office, share of Vogtle’s cost | % | 22 | not reached at any value | not reached at any value | not reached at any value |
| Shifts worked on site | shifts | 1.4 | not reached at any value | not reached at any value | not reached at any value |
| Learning on vendor lines, per doubling | % | 3 | not reached at any value | not reached at any value | not reached at any value |
| Contingency common to the whole program | % | 15 | not reached at any value | not reached at any value | not reached at any value |
| Removed as particular to Vogtle (L1) | USD/kW | 1,590 | not reached at any value | not reached at any value | not reached at any value |
| Learning of site crews, per doubling | % | 5 | not reached at any value | not reached at any value | not reached at any value |
| Input | Unit | Cautious value | Needed for 60 USD/MWh | Needed for 80 USD/MWh | Needed for 100 USD/MWh |
|---|---|---|---|---|---|
| Shifts worked on site | shifts | 1.4 | not reached at any value | not reached at any value | not reached at any value |
| Staff, upkeep and capital spent during life | USD/kW a year | 317 | not reached at any value | not reached at any value | not reached at any value |
| Vogtle cost before interest | USD/kW | 15,390 | not reached at any value | not reached at any value | not reached at any value |
| Learning of site crews, per doubling | % | 5 | not reached at any value | not reached at any value | not reached at any value |
| Hardware and materials, share of Vogtle’s cost | % | 20 | not reached at any value | not reached at any value | not reached at any value |
| Contingency common to the whole program | % | 15 | not reached at any value | not reached at any value | not reached at any value |
| Removed as particular to Vogtle (L1) | USD/kW | 1,590 | not reached at any value | not reached at any value | not reached at any value |
| Learning on vendor lines, per doubling | % | 3 | not reached at any value | not reached at any value | not reached at any value |
What explains the gap between the two cases
In the model, operation explains 34% of the distance from the target case to the cautious one.
Site duration explains 24%.
target case114 USD/MWh
cautious case181 USD/MWh
Operation23 USD/MWh · 34%
Site duration16 USD/MWh · 24%
Contingency9 USD/MWh · 13%
Learning8 USD/MWh · 12%
- Operation23 USD/MWh · 34%
- Site duration16 USD/MWh · 24%
- Contingency9 USD/MWh · 13%
- Learning8 USD/MWh · 12%
- Wages and everything else6 USD/MWh · 9%
- Dedicated lines3 USD/MWh · 5%
- Factory against site hours2 USD/MWh · 3%
- Choice of allocation0 USD/MWh · 0%
- Vessels a year0 USD/MWh · 0%
Found by switching the groups of inputs from their target to their cautious values in many different orders and averaging what each switch adds. A group can come out slightly negative.
Scenarios
No learning at all is the scenario that costs most: the model then gives 129 USD/MWh198 USD/MWh.
A stopped line moves the date far more than the cost: LCOE does not see time.
The case as it stands
23.6 years
42.2 years
Vessel line stopped for 6 months
24.1 years
42.7 years
Vessel line stopped for 12 months
24.6 years
43.2 years
Another line (steam generators, pumps, valves or controls) holds the pace to 9.0 vessels a year
−129.1 years
+153.2 years
Eighty years of operation
−123.6 years
−242.2 years
No learning at all
+1524.2 years
+1742.8 years
Steel, forgings and wages 20% dearer in real terms
23.7 years
+1342.2 years
Vendor lines cost half as much again
+123.6 years
+142.2 years
Crane ships only: wide pieces shipped as sub pieces
+123.6 years
+242.2 years
Line, factory and ships built for 6 a year, not 12
−342.2 years
Each scenario’s LCOE and years
| Scenario | LCOE, USD/MWh | Years to unit 200 |
|---|---|---|
| The case as it stands | 114 | 23.6 |
| Vessel line stopped for 6 months | 114 | 24.1 |
| Vessel line stopped for 12 months | 114 | 24.6 |
| Another line (steam generators, pumps, valves or controls) holds the pace to 9.0 vessels a year | 113 | 29.1 |
| Eighty years of operation | 113 | 23.6 |
| No learning at all | 129 | 24.2 |
| Steel, forgings and wages 20% dearer in real terms | 114 | 23.7 |
| Vendor lines cost half as much again | 115 | 23.6 |
| Crane ships only: wide pieces shipped as sub pieces | 115 | 23.6 |
| Scenario | LCOE, USD/MWh | Years to unit 200 |
|---|---|---|
| The case as it stands | 181 | 42.2 |
| Vessel line stopped for 6 months | 182 | 42.7 |
| Vessel line stopped for 12 months | 182 | 43.2 |
| Another line (steam generators, pumps, valves or controls) holds the pace to 4.5 vessels a year | 183 | 53.2 |
| Eighty years of operation | 180 | 42.2 |
| No learning at all | 198 | 42.8 |
| Steel, forgings and wages 20% dearer in real terms | 194 | 42.2 |
| Vendor lines cost half as much again | 183 | 42.2 |
| Crane ships only: wide pieces shipped as sub pieces | 184 | 42.2 |
| Line, factory and ships built for 6 a year, not 12 | 178 | 42.2 |
The close
For the target case to hold, the vessel line has to reach 12 vessels a year, where the cautious case takes 6, and three things have to go its way: what it costs to run the plants, how long each site takes and how far the build runs over its plan; all of it under the model’s assumptions.
target case
114
cautious case
181
USD/MWh at 7%
23.6years
from the order to unit 200
USD/MWh at 7%
42.2years
from the order to unit 200