Siderian

a stylized model · 2025 dollars

200 reactors at 114 USD/MWh in 23.6 years if the vessel line holds 12 a year and the targets are met; about 146 USD/MWh in the middle of the range; 181 USD/MWh in 42.2 years in the cautious case, with every uncertain input at its unfavourable end.

target case

114

USD/MWh

cautious case

181

USD/MWh

the middle of the range146 USD/MWh
four runs in five fall between133–159 USD/MWh

Average cost of electricity per unit at a 7% cost of money, under the model’s assumptions. The band is a spread from the stated ranges, not a probability.

at other costs of money, target–cautious
3%72–111 USD/MWh5%91–142 USD/MWh7%114–181 USD/MWh10%155–257 USD/MWh
overnight cost
7,360 USD/kW10,280 USD/kW
years to unit 200
23.6 years42.2 years
Progreso in use
68%30%
7%
cases

The problem

Given 200 reactors, 200 ready sites and one vessel line, the model chooses where every piece of work is done so that its electricity costs the least.

V vendorsevery part delivered as complete as it is soldone vessel line at Doosanthe heaviest parts go straight to the sitesP Progresoassembles and tests; forges nothingS 200 sites, readyone unit each, on the water, cranes in place15 days by seafrom Progreso to every site
V vendorsdeliver completeP ProgresoS 200 sites15 days by sea, every site
schematic: every site is 15 days from Progreso; positions are not geographic

Given

  • S200 unitsD of 1,117 MWD, one on each of 200 ready sites
  • Severy site 15 days by sea from Progreso
  • Vone dedicated vessel line at Doosan: 12 or 6 vessels a yearT
  • Va vendor that sells a complete assembly delivers it complete, to Progreso or straight to the site; every critical part has its own line
  • PProgreso assembles, fits out and tests; it does not forge, roll or cast

Chosen by the model

  • PSwhere each package of work is done: on site or at Progreso
  • Phow far it is finished before it ships: bare, fitted out, or fitted out and tested
  • PSthe size of each piece: sub pieces joined on site, or one complete lift
  • Probot cell or manual station, for each family of tasks
  • Pwhich factory test halls are built
  • Pthe stations and shifts of each bay
  • Pthe ships of each class
  • Pthe buffer of finished modules at the quay
  • PSthe route of each vendor part: straight to the site, or through Progreso first
  • Sthe ground work: one standard design, or one for each site
  • Show far ahead of its reactor vessel each site starts

The goal

The lowest cost of electricity, with as little labor as possible, above all on site.

The rules

  • SWestinghouse’s design, module list, lift order and build sequence, unchanged
  • Sholds that no labor can shorten: curing, weld inspection, pressure and leak tests, the hot test, inspection before fuel
  • Pevery shipped piece within its ship and the crane of the site
  • Pno bay over its capacity in any month
  • Vnever more units at power than vessels delivered

DdocumentedVderivedJjudgedTtargetVvendorPProgresoSsite

Data table
What the drawing shows
ItemValue
Units, and sites200
Net output of a unit1,117 MW
From Progreso to every site, by sea15 days
Vessels a year, target case12
Vessels a year, cautious case6
Vendors drawn20
Chosen by the model, and the rules
KindPlaceIn plain words
chosenProgreso, sitewhere each package of work is done: on site or at Progreso
chosenProgresohow far it is finished before it ships: bare, fitted out, or fitted out and tested
chosenProgreso, sitethe size of each piece: sub pieces joined on site, or one complete lift
chosenProgresorobot cell or manual station, for each family of tasks
chosenProgresowhich factory test halls are built
chosenProgresothe stations and shifts of each bay
chosenProgresothe ships of each class
chosenProgresothe buffer of finished modules at the quay
chosenProgreso, sitethe route of each vendor part: straight to the site, or through Progreso first
chosensitethe ground work: one standard design, or one for each site
chosensitehow far ahead of its reactor vessel each site starts
rulesiteWestinghouse’s design, module list, lift order and build sequence, unchanged
rulesiteholds that no labor can shorten: curing, weld inspection, pressure and leak tests, the hot test, inspection before fuel
ruleProgresoevery shipped piece within its ship and the crane of the site
ruleProgresono bay over its capacity in any month
rulevendornever more units at power than vessels delivered

The vessel line

In the model one dedicated line at Doosan sets the pace of everything: it gives 12 reactor vessels a year in the target case, 6 in the cautious case, and no unit can start up before its vessel arrives.

target case · 12 a yearT · ingot and forging limits the linecautious case · 6 a year · heat treatment and tests limits the line

6233524212target4122312111cautiousstations side by side01Ingot andforging5.0 monthslimits the line3 waiting02Heat treatmentand tests1.5 monthscautious:limits the line2 waiting03Rough machining2.0 months04Cladding2.5 months05Ring and nozzlewelds4.0 months06Post weld heattreatment1.0 months07Final machining3.0 months08Examination1.5 months09Pressure test0.5 months10Sea transportto the site1.2 months
01Ingot and forging5.0 months · 6 stations, 4 cautiouslimits the line · 3 waiting02Heat treatment and tests1.5 months · 2 stations, 1 cautiouscautious: limits · 2 waiting03Rough machining2.0 months · 3 stations, 2 cautious04Cladding2.5 months · 3 stations, 2 cautious05Ring and nozzle welds4.0 months · 5 stations, 3 cautious06Post weld heat treatment1.0 months · 2 stations, 1 cautious07Final machining3.0 months · 4 stations, 2 cautious08Examination1.5 months · 2 stations, 1 cautious09Pressure test0.5 months · 1 station, 1 cautious10Sea transport to the site1.2 months · 2 stations, 1 cautious

cautious case · 6 a yearT · heat treatment and tests limits the line

4122312111cautiousstations side by side01Ingot andforging5.0 months02Heat treatmentand tests1.5 monthslimits the line2 waiting03Rough machining2.0 months04Cladding2.5 months05Ring and nozzlewelds4.0 months06Post weld heattreatment1.0 months07Final machining3.0 months08Examination1.5 months09Pressure test0.5 months10Sea transportto the site1.2 months
01Ingot and forging5.0 months · 4 stations02Heat treatment and tests1.5 months · 1 stationlimits the line · 2 waiting03Rough machining2.0 months · 2 stations04Cladding2.5 months · 2 stations05Ring and nozzle welds4.0 months · 3 stations06Post weld heat treatment1.0 months · 1 station07Final machining3.0 months · 2 stations08Examination1.5 months · 1 station09Pressure test0.5 months · 1 station10Sea transport to the site1.2 months · 1 station
vessels in work at once
14–42 vessels7–21 vessels
months from first steel to the site
13.9–42.0 monthsthe same in both cases
first vessel after the orderJ
54 months60 months
months to reach the full rateJ
12 months24 months

The model gives these figures. The low one has every station working without a wait; the high one is the slowest flow on record. Each station is taken to work 85% of the timeJ.

Three paces, three hall lengths

A longer hall makes more vessels a year, and the model reaches unit 200 sooner.

6a year40.3 years to unit 20042.5 years to unit 20012a year23.6 years to unit 20026.1 years to unit 20024a yearoutside the brief15.8 years to unit 20018.0 years to unit 200
6 vessels a year40.3 years to unit 20042.5 years to unit 20012 vessels a year23.6 years to unit 20026.1 years to unit 20024 vessels a year · outside the brief15.8 years to unit 20018.0 years to unit 200

The other dedicated lines: what the model needs each year, and what is made today

Lineneeded a yearneeded a yearMade today
Steam generators2412no stated output found; Doosan has made 124 in about 40 yearsno limit found
Coolant pumps482412 to 16 a year, one qualified maker (secondary source)could hold the pace back
Large vessel forgings6030Japan Steel Works claims 12 vessel sets a year; Doosan about 5could hold the pace back
Turbine generators126no stated output foundno limit found
Data table
Stations of the vessel line, target case
StationWorkStationsVessels waitingLimits the line
Ingot and forging5.0 months63yes
Heat treatment and tests1.5 months20no
Rough machining2.0 months30no
Cladding2.5 months30no
Ring and nozzle welds4.0 months50no
Post weld heat treatment1.0 months20no
Final machining3.0 months40no
Examination1.5 months20no
Pressure test0.5 months10no
Sea transport to the site1.2 months20no
Stations of the vessel line, cautious case
StationWorkStationsVessels waitingLimits the line
Ingot and forging5.0 months40no
Heat treatment and tests1.5 months12yes
Rough machining2.0 months20no
Cladding2.5 months20no
Ring and nozzle welds4.0 months30no
Post weld heat treatment1.0 months10no
Final machining3.0 months20no
Examination1.5 months10no
Pressure test0.5 months10no
Sea transport to the site1.2 months10no
Vessels a year and years to the last unit
Vessels a yearIn the briefTarget caseCautious case
6yes40.3 years42.5 years
12yes23.6 years26.1 years
24no, shown for comparison15.8 years18.0 years

Who makes what

The model sends the heaviest finished parts straight to the site: the reactor vessel, steam generators, turbine generator, moisture separator reheaters and transformers. The pressurizer; coolant pumps; head package and control rod drives; and internals go through Progreso first.The model sends the heaviest finished parts straight to the site: the reactor vessel, steam generators, coolant pumps, turbine generator, moisture separator reheaters and transformers. The pressurizer; head package and control rod drives; and internals go through Progreso first.

A part goes straight when a detour would delay the reactor vessel or cost more than it saves. It goes through Progreso when it is fitted into a module there, or when catching a fault before it reaches the site is worth the detour. In the cautious case the model changes the route of some: the basemat rebar cages, containment bottom head, coolant pumps and passive safety tanks and heat exchanger go straight to the site. Today coolant pumps and squib valves (explosive valves that open the passive safety systems) each have only one qualified maker.

1234567891011P ProgresoS the siteson US waters; places not fixed
1234567891011
The world seen from above North America; a coarse outline drawn for this page. Vendors are placed by latitude and longitude. The sites are not placed: their marks only show the direction. A part with no line has no route of its own in the model.critical partother partonly one makerdelivered to Progresodelivered straight to the sitecautious case, where its route differsfinished modules, Progreso to the sites
  1. 1Turbine generatorToshibato siteto site
  2. 1Containment vessel platesIHIvia Progresovia Progreso
  3. 2Reactor vesselDoosan Enerbilityto siteto site
  4. 2Steam generatorsDoosan Enerbilityto siteto site
  5. 2CondenserBHI (Toshiba design)via Progresovia Progreso
  6. 3Large forgingsJapan Steel Works––
  7. 4Structural sub modulesVigor (Oregon Iron Works) and othersvia Progresovia Progreso
  8. 5Head packagePremier Technologyvia Progresovia Progreso
  9. 6EnrichmentUrenco USA––
  10. 7Fuel assembliesWestinghouse––
  11. 8Coolant pumpsCurtiss-Wrightvia Progresoto siteone maker
  12. 8Squib valvesSPX Copes-Vulcan––one maker
  13. 8Protection and control, control roomWestinghousevia Progresovia Progreso
  14. 8Mechanical modulesAeconvia Progresovia Progreso
  15. 8SimulatorGSE Systems––
  16. 9Shield building panelsNewport News Industrialvia Progresovia Progreso
  17. 9Safety pumps and valvesFlowserve and others––
  18. 10Internals, control rod drivesWestinghousevia Progresovia Progreso
  19. 10Nuclear cableGeneral Cable––
  20. 11Pressurizer, core makeup tanksMangiarotti (Westinghouse)via Progresovia Progreso

Where today’s output is known: what the model needs each year against what is made

  • 2Reactor vessel

    needed12 vessels
    made todayabout 5 sets a year (World Nuclear Association, marked uncertain)
  • 8Coolant pumpsone maker

    needed48
    made today12 to 16 a year (secondary source)
  • 6Enrichment

    neededabout 2.4 million units a year at 200 units
    made todayabout 5 million units a year

3Large forgings: the model needs 60 vessel forgings, plus steam generator, pressurizer and pump forgings; made today: 12 vessel sets a year claimed; 4 documented to 2007. The two are counted in different things, so they are not set side by side as bars.

For the other parts no stated yearly output was found; they are listed in the data table.

Data table: every part, its vendors, demand and capacity
What the map shows
PinPartVendorPlaceLatitudeLongitudeStatusCriticalSingle sourceShips asRoute, target caseRoute, cautious caseSecond vendorNeeded a yearCapacity today
1Turbine generatorToshibaYokohama, Japan35.50139.70verifiedyesnocompletestraight to the sitestraight to the siteMitsubishi Heavy Industries; Arabelle (EDF)12no stated output found
1Containment vessel platesIHIYokohama, Japan35.44139.64verifiednonoformed platesthrough Progresothrough ProgresoPolish yards with Westinghouse orders12 setsno stated output found
2Reactor vesselDoosan EnerbilityChangwon, South Korea35.20128.60verifiedyesnocomplete, tested, by seastraight to the sitestraight to the siteBWXT Canada (agreement only)12 vesselsabout 5 sets a year (World Nuclear Association, marked uncertain)
2Steam generatorsDoosan EnerbilityChangwon, South Korea35.20128.60verifiedyesnocompletestraight to the sitestraight to the siteENSA, Spain (to verify); BWXT Canada (agreement)24no stated output found; 124 made in about 40 years
2CondenserBHI (Toshiba design)Haman, South Korea35.27128.40verifiednonocomplete, in modulesthrough Progresothrough ProgresoDoosan Å koda (to verify)12no stated output found
3Large forgingsJapan Steel WorksMuroran, Japan42.30141.00verifiedyesnoforgingsno route of its ownno route of its ownDoosan; Sheffield Forgemasters; Framatome Le Creusot60 vessel forgings, plus steam generator, pressurizer and pump forgings12 vessel sets a year claimed; 4 documented to 2007
4Structural sub modulesVigor (Oregon Iron Works) and othersPortland, Oregon45.52-122.68verifiednonosub modulesthrough Progresothrough ProgresoMostostal Kielce, Mostostal Kraków, EPG, FAMAK (Poland)12 setsno stated output found
5Head packagePremier TechnologyBlackfoot, Idaho43.19-112.34verifiednonofitted at its makerthrough Progresothrough Progresonone found12no stated output found
6EnrichmentUrenco USAEunice, New Mexico32.44-103.16verifiednonoenriched uraniumno route of its ownno route of its ownOrano (planned, Oak Ridge)about 2.4 million units a year at 200 unitsabout 5 million units a year
7Fuel assembliesWestinghouseColumbia, South Carolina34.00-81.03verifiednonocomplete assembliesno route of its ownno route of its ownVästerås, Sweden12 first cores, then reloadsno stated output found
8Coolant pumpsCurtiss-WrightCheswick, Pennsylvania40.54-79.80verifiedyesyescomplete pumpthrough Progresostraight to the sitenone qualified4812 to 16 a year (secondary source)
8Squib valvesSPX Copes-VulcanMcKean, Pennsylvania41.85-78.64verifiedyesyescomplete valveno route of its ownno route of its ownnone found12 setsno stated output found
8Protection and control, control roomWestinghouseCranberry, Pennsylvania40.68-80.10verifiedyesnocabinets, factory testedthrough Progresothrough Progresonone found12 setsno stated output found
8Mechanical modulesAeconCambridge, Ontario43.36-80.31verifiednonotested modulesthrough Progresothrough ProgresoTurner Industries; CB&I Laurens12 setsno stated output found
8SimulatorGSE SystemsColumbia, Maryland39.20-76.86verifiednonocompleteno route of its ownno route of its ownnone found1 for the fleet, then updatesnot applicable
9Shield building panelsNewport News IndustrialNewport News, Virginia36.98-76.43verifiednonopanelsthrough Progresothrough ProgresoPolish yards (to verify)12 sets of about 160no stated output found
9Safety pumps and valvesFlowserve and othersRaleigh, North Carolina35.78-78.64verifiednonocompleteno route of its ownno route of its ownVelan, Canada (to verify)12 setsno stated output found
10Internals, control rod drivesWestinghouseNewington, New Hampshire43.10-70.83verifiedyesnocompletethrough Progresothrough Progresonone found12 setsno stated output found
10Nuclear cableGeneral CableWillimantic, Connecticut41.71-72.21verifiednonoreelsno route of its ownno route of its ownnone found12 setsno stated output found
11Pressurizer, core makeup tanksMangiarotti (Westinghouse)Monfalcone, Italy45.8013.53to verifyyesnocompletethrough Progresothrough ProgresoDoosan; ENSA (candidates)12 and 24no stated output found

Progreso

The model gives one factory on the quay that assembles, fits out and tests the modules of every unit, with 68% of its work stations in use in the target case and 30% in the cautious case.

drawn: the target case · the cautious figures stand beside it, below

Structuralrobots, hands · 361 stationsRebarrobots · 63 stationsMechanicalrobots · 144 stationsElectricalrobots · 63 stationsCoatingrobots · 25 stationsInspectionrobots, hands · 80 stationsyard6 modules waitingInstrument and controltest hall, builtElectrical cabinetstest hall, builtPipe module pressure testtest hall, builtModule to module fit checktest hall, builtbuffer at the quay1 finished module15 crane ships5 float on, float off ships
Structuralrobots, hands361 stationsRebarrobots63 stationsMechanicalrobots144 stationsElectricalrobots63 stationsCoatingrobots25 stationsInspectionrobots, hands80 stationstest hallsall built15 crane ships5 float on ships

drawn: the cautious case · the cautious figures stand beside it, below

Structuralby hand · 825 stationsRebarby hand · 104 stationsMechanicalby hand · 280 stationsElectricalby hand · 123 stationsCoatingby hand · 49 stationsInspectionby hand · 179 stationsyard3 modules waitingInstrument and controltest hall, builtElectrical cabinetstest hall, builtPipe module pressure testtest hall, builtModule to module fit checktest hall, builtbuffer at the quay1 finished module13 crane ships8 float on, float off ships
Structuralby hand825 stationsRebarby hand104 stationsMechanicalby hand280 stationsElectricalby hand123 stationsCoatingby hand49 stationsInspectionby hand179 stationstest hallsall built13 crane ships8 float on ships

one roof: ten work stations; lit roofs: the share in useten robotsten peopleone module’s way to the shipships under way are drawn small

work stations in use
68%30%
people
2,1816,249
robotsJ
6550
cost to build, billion USD
5.515.9
crane shipsJ
1513
float on, float off shipsJ
58
months to build and proveJ
3444

Every bay runs at close to the same share, because the model sizes each one for its busiest month. All four test halls are built in both cases: each saves more on every unit than it costs once.

Data table
Bays, target case
BayMethodStationsShift stations in useUse, steadyUse, rampRobotsPeopleCapital
Structural baymixed36174269%100%2911,330437 million USD
Rebar bayrobot6312868%99%6312857 million USD
Mechanical bayrobot14429668%100%144294130 million USD
Electrical bayrobot6312969%100%6312957 million USD
Coating bayrobot255067%97%255023 million USD
Test hallsmixed8016267%98%6925090 million USD
Test halls, ships and the yard, target case
ItemStateValueSecond value
Test hall: Instrument and control, whole system on the simulatorbuilt17 million USD saved a unit140 million USD cost
Test hall: Electrical cabinetsbuilt102 million USD saved a unit60 million USD cost
Test hall: Pipe module pressure testbuilt143 million USD saved a unit45 million USD cost
Test hall: Module to module fit checkbuilt28 million USD saved a unit80 million USD cost
Heavy lift crane shipin the fleet15 ships10.4 voyages a unit
Semi submersible heavy transport shipin the fleet5 ships3.4 voyages a unit
Modules in the yard6
Buffer of finished modules at the quay1
People, robots2,181 people655 robots
Capital; months to build and qualify5.5 billion USD34 months
Bays, cautious case
BayMethodStationsShift stations in useUse, steadyUse, rampRobotsPeopleCapital
Structural baymanual82575430%50%03,3113,300 million USD
Rebar baymanual1049430%50%0415416 million USD
Mechanical baymanual28025630%50%01,1231,120 million USD
Electrical baymanual12311230%50%0491492 million USD
Coating baymanual494430%49%0193196 million USD
Test hallsmanual17916330%50%0716716 million USD
Test halls, ships and the yard, cautious case
ItemStateValueSecond value
Test hall: Instrument and control, whole system on the simulatorbuilt20 million USD saved a unit200 million USD cost
Test hall: Electrical cabinetsbuilt158 million USD saved a unit90 million USD cost
Test hall: Pipe module pressure testbuilt201 million USD saved a unit70 million USD cost
Test hall: Module to module fit checkbuilt19 million USD saved a unit120 million USD cost
Heavy lift crane shipin the fleet13 ships7.8 voyages a unit
Semi submersible heavy transport shipin the fleet8 ships4.6 voyages a unit
Modules in the yard3
Buffer of finished modules at the quay1
People, robots6,249 people0 robots
Capital; months to build and qualify15.9 billion USD44 months

One site

The model gives a site that runs 63.0 months in the target case and 94.1 months in the cautious case, from the first day of ground work to full power; the final tests, which no extra labor can shorten, close it.

For comparison only: Westinghouse’s target is 36 months from first concrete to fuel load; Vogtle took 125 monthsD from first concrete to commercial operation, with about 9,000 people on site at its peak.

drawn: the target case · the cautious case as a second row and an open outline

Ground workConcrete and buildingsReactor buildingTurbine hallTesting and starttests and records thatdo not need the vesselfull power63.0 monthsthe vessel is settarget case28.7 months before the vessel34.3 months after it63.0 monthscautious case44.2 months before the vessel49.9 months after it94.1 monthsfrom first concretethis site, fuel loadedWestinghouse’s target, fuel loaded: 36 monthsVogtle, in operation: 125 months, off the pagemonth 01224364860728496People on sitetrades, support and staffVogtle’s peak: 9,000 peoplepeak 4,319 peopleaverage 1,967cautious peak 3,817
0122436486072monthGroundConcreteReactorTurbineTestswork startsfirst concretemonth 16vessel set28.7 months infuel loadedfull power63.0 months28.7 before the vessel · 34.3 after · 63.0 months44.2 before the vessel · 49.9 after · 94.1 monthspeople on siteVogtle’s peak 9,000peak 4,3190122436486072average 1,967 people

drawn: the cautious case · the cautious case as a second row and an open outline

Ground workConcrete and buildingsReactor buildingTurbine hallTesting and starttests and records thatdo not need the vesselfull power94.1 monthsthe vessel is setcautious case44.2 months before the vessel49.9 months after it94.1 monthsfrom first concretethis site, fuel loadedWestinghouse’s target, fuel loaded: 36 monthsVogtle, in operation: 125 months, off the pagemonth 01224364860728496People on sitetrades, support and staffVogtle’s peak: 9,000 peoplepeak 3,817 peopleaverage 1,705
01224364860728496monthGroundConcreteReactorTurbineTestswork startsfirst concretemonth 28vessel set44.2 months infuel loadedfull power94.1 months44.2 before the vessel · 49.9 after · 94.1 monthspeople on siteVogtle’s peak 9,000peak 3,81701224364860728496average 1,705 people

a phase of the workone taska wait no labor can shortena crane liftthe longest chain of taskstests and records that do not need the vesselfull power

Making the site ready before the reactor vessel comes

When the vessel arrives, the model has 48% of the site’s work done in the target case and 45% in the cautious case; starting earlier would finish more of it, but would bring full power only a little sooner.

head start the model gives
0.0 months0.0 months
head start that would have all else done
19.3 months23.4 months
months from the vessel’s arrival to full power
34.349.9with the latest start34.349.9as the model gives it33.149.2with all else done first

To have everything that does not need the vessel finished on the day it arrives, the site would start 19.3 months earlier. The model then gives 33.1 months from the vessel to full power, against 34.3 months with the latest start: almost all of that wait is set by work that can only follow the vessel, the reactor vessel, steam generators, coolant pumps, cold hydro and hot functional test, inspection closure and fuel load and power ascension. The model gives a head start of 0.0 months: the months gained are worth less to it than the cost of a site that stands finished and waiting.

To have everything that does not need the vessel finished on the day it arrives, the site would start 23.4 months earlier. The model then gives 49.2 months from the vessel to full power, against 49.9 months with the latest start: almost all of that wait is set by work that can only follow the vessel, the reactor vessel, steam generators, coolant pumps, cold hydro and hot functional test, inspection closure and fuel load and power ascension. The model gives a head start of 0.0 months: the months gained are worth less to it than the cost of a site that stands finished and waiting.

What sets the wait after the vessel: the work that can only follow it, in order

  1. Reactor vessel3.9 months, of which 0.1 a fixed wait
  2. Steam generators4.4 months, of which 0.1 a fixed wait
  3. Coolant pumps5.3 months, of which 0.1 a fixed wait
  4. Cold hydro and hot functional test6.5 months, of which 3.1 a fixed wait
  5. Inspection closure and fuel load6.0 months, of which 3.0 a fixed wait
  6. Power ascension7.0 months, of which 2.0 a fixed wait
  1. Reactor vessel5.6 months, of which 0.1 a fixed wait
  2. Steam generators6.2 months, of which 0.1 a fixed wait
  3. Coolant pumps7.6 months, of which 0.1 a fixed wait
  4. Cold hydro and hot functional test10.0 months, of which 3.1 a fixed wait
  5. Inspection closure and fuel load10.6 months, of which 3.0 a fixed wait
  6. Power ascension9.2 months, of which 2.0 a fixed wait

worka fixed wait that no labor can shorten

The longest chain of tasks, in plain steps: a day lost on any of them is a day lost at the end

  1. 1Prepare the ground: clear it, dig, and fill it back firmfrom month 00
  2. 2Build the turbine hall and fit the turbine, its pipes and its cablesfrom month 1423
  3. 3Connect the last cables across the whole plantfrom month 3959
  4. 4Run the tests that do not need the reactor vesselfrom month 4061
  5. 5Test the finished plant, first cold, then hotfrom month 4364
  6. 6Pass the final inspections, load the fuel and raise the power step by stepfrom month 5074

Ground work

One standard design for the ground and the quay, used at every siteT.

ground crews
1412
months of early start
00
heavy cranesJ
128

Crews that move from site to siteJ

Tradecrewscrewsunits per crew
Civil32256.3 · 8.0
Structural and module setting21159.5 · 13.3
Mechanical191410.5 · 14.3
Electrical26207.7 · 10.0
Start up151213.3 · 16.7
Data table
Tasks of one site, target case; months from the start of land preparation
TaskChainStartDurationOf which holdCriticalCrane lift
Clearing and gradingGround work0.01.6 months0.0 monthsyesno
Excavation and dewateringGround work1.66.8 months0.0 monthsyesno
Engineered backfillGround work8.55.5 months0.3 monthsyesno
Unloading quay and heavy haul roadGround work1.64.4 months1.0 monthsnono
Cooling water works and towersTurbine hall8.59.6 months0.9 monthsnono
SwitchyardTurbine hall1.63.9 months0.0 monthsnono
Site buildingsTurbine hall1.65.4 months0.0 monthsnono
Basemat rebar cagesConcrete and buildings14.01.9 months0.0 monthsnono
Basemat concreteConcrete and buildings15.93.8 months0.9 monthsnono
Containment bottom headReactor building19.73.2 months0.2 monthsnoyes
Containment ringsReactor building26.42.3 months0.2 monthsnoyes
Containment top headReactor building37.00.5 months0.2 monthsnoyes
Structural modules CA01, CA02 to CA05, CA20Reactor building22.93.5 months0.5 monthsnoyes
Shield building panelsConcrete and buildings19.72.3 months0.2 monthsnono
Shield building roof and water tankConcrete and buildings37.52.1 months0.3 monthsnoyes
Interior concreteConcrete and buildings26.416.2 months0.9 monthsnono
Auxiliary and fuel building concreteConcrete and buildings26.413.6 months0.9 monthsnono
Embeds and penetrationsConcrete and buildings19.76.5 months0.0 monthsnono
Steel platforms and stairsReactor building26.41.0 months0.0 monthsnono
Coatings and liner closureReactor building37.54.5 months0.2 monthsnono
Piping modulesReactor building26.41.2 months0.3 monthsnono
Mechanical equipment modulesReactor building26.41.2 months0.3 monthsnono
Electrical equipment modulesReactor building26.40.8 months0.2 monthsnono
Large pipe spoolsReactor building27.67.6 months0.5 monthsnono
Cable setsReactor building27.22.5 months0.2 monthsnono
VentilationReactor building40.01.9 months0.0 monthsnono
Reactor vesselReactor building28.73.9 months0.1 monthsnoyes
Steam generatorsReactor building32.64.4 months0.1 monthsnoyes
PressurizerReactor building26.43.1 months0.1 monthsnoyes
Coolant pumpsReactor building37.05.3 months0.1 monthsnono
Head package and control rod drivesReactor building32.63.9 months0.1 monthsnono
InternalsReactor building32.63.9 months0.1 monthsnono
Passive safety tanks and heat exchangerReactor building26.45.0 months0.2 monthsnono
Turbine building blocksTurbine hall14.03.3 months0.5 monthsyesno
Turbine generatorTurbine hall17.314.4 months0.2 monthsyesyes
CondenserTurbine hall17.36.5 months0.2 monthsnono
Moisture separator reheatersTurbine hall17.37.2 months0.1 monthsnono
Feedwater trainTurbine hall17.36.1 months0.2 monthsnono
TransformersTurbine hall5.55.8 months0.1 monthsnono
Turbine island pipe and cableTurbine hall31.77.1 months0.5 monthsyesno
Annex buildingConcrete and buildings14.05.4 months0.3 monthsnono
Diesel buildingConcrete and buildings14.03.2 months0.2 monthsnono
Waste buildingConcrete and buildings14.03.1 months0.2 monthsnono
Auxiliary electrical roomsConcrete and buildings19.32.5 months0.2 monthsnono
Protection and control cabinetsReactor building21.82.7 months0.2 monthsnono
Main control roomReactor building24.53.7 months0.3 monthsnono
Plant wide cable terminationReactor building38.81.2 months0.0 monthsyesno
Cold hydro and hot functional testTesting and start43.56.5 months3.1 monthsyesno
Inspection closure and fuel loadTesting and start50.06.0 months3.0 monthsyesno
Power ascensionTesting and start56.07.0 months2.0 monthsyesno
Tests that do not need the vesselTesting and start40.03.4 months0.0 monthsyesno
Inspection records closed before the vesselTesting and start43.54.6 months0.0 monthsnono
Site headcount by month, target case
MeasurePeople
Peak4,319
Average1,967
Vogtle’s peak9,000
Month by month, from the first951 1,972 1,488 1,488 1,488 1,596 1,432 1,181 1,824 1,437 1,437 1,437 1,330 2,881 2,638 2,804 2,475 3,225 2,388 2,539 1,988 2,091 2,260 2,104 1,832 1,621 3,713 4,319 3,609 3,305 2,492 3,773 3,638 3,558 3,558 3,558 3,096 3,120 3,731 2,615 1,994 1,309 1,040 1,187 1,187 1,187 1,187 1,187 1,187 1,880 1,161 1,161 1,161 1,161 1,161 1,457 763 763 763 763 763 763 763
Tasks of one site, cautious case; months from the start of land preparation
TaskChainStartDurationOf which holdCriticalCrane lift
Clearing and gradingGround work0.02.8 months0.0 monthsyesno
Excavation and dewateringGround work2.811.5 months0.0 monthsyesno
Engineered backfillGround work14.39.0 months0.3 monthsyesno
Unloading quay and heavy haul roadGround work2.86.8 months1.0 monthsnono
Cooling water works and towersTurbine hall14.313.5 months0.9 monthsnono
SwitchyardTurbine hall2.85.9 months0.0 monthsnono
Site buildingsTurbine hall2.88.3 months0.0 monthsnono
Basemat rebar cagesConcrete and buildings23.34.3 months0.0 monthsnono
Basemat concreteConcrete and buildings27.65.0 months0.9 monthsnono
Containment bottom headReactor building32.64.6 months0.2 monthsnoyes
Containment ringsReactor building42.41.8 months0.2 monthsnoyes
Containment top headReactor building55.90.7 months0.2 monthsnoyes
Structural modules CA01, CA02 to CA05, CA20Reactor building37.25.2 months0.5 monthsnoyes
Shield building panelsConcrete and buildings32.63.4 months0.2 monthsnono
Shield building roof and water tankConcrete and buildings56.62.9 months0.3 monthsnoyes
Interior concreteConcrete and buildings42.422.9 months0.9 monthsnono
Auxiliary and fuel building concreteConcrete and buildings42.419.1 months0.9 monthsnono
Embeds and penetrationsConcrete and buildings32.610.0 months0.0 monthsnono
Steel platforms and stairsReactor building42.41.6 months0.0 monthsnono
Coatings and liner closureReactor building56.66.4 months0.2 monthsnono
Piping modulesReactor building42.41.7 months0.3 monthsnono
Mechanical equipment modulesReactor building42.41.7 months0.3 monthsnono
Electrical equipment modulesReactor building42.41.2 months0.2 monthsnono
Large pipe spoolsReactor building44.011.4 months0.5 monthsnono
Cable setsReactor building43.53.7 months0.2 monthsnono
VentilationReactor building61.52.9 months0.0 monthsnono
Reactor vesselReactor building44.25.6 months0.1 monthsnoyes
Steam generatorsReactor building49.76.2 months0.1 monthsnoyes
PressurizerReactor building42.44.4 months0.1 monthsnoyes
Coolant pumpsReactor building55.97.6 months0.1 monthsnono
Head package and control rod drivesReactor building49.75.6 months0.1 monthsnono
InternalsReactor building49.75.5 months0.1 monthsnono
Passive safety tanks and heat exchangerReactor building42.48.3 months0.2 monthsnono
Turbine building blocksTurbine hall23.34.8 months0.5 monthsyesno
Turbine generatorTurbine hall28.120.7 months0.2 monthsyesyes
CondenserTurbine hall28.19.8 months0.2 monthsnono
Moisture separator reheatersTurbine hall28.110.3 months0.1 monthsnono
Feedwater trainTurbine hall28.19.3 months0.2 monthsnono
TransformersTurbine hall8.68.3 months0.1 monthsnono
Turbine island pipe and cableTurbine hall48.810.7 months0.5 monthsyesno
Annex buildingConcrete and buildings23.38.1 months0.3 monthsnono
Diesel buildingConcrete and buildings23.34.8 months0.2 monthsnono
Waste buildingConcrete and buildings23.34.6 months0.2 monthsnono
Auxiliary electrical roomsConcrete and buildings31.33.7 months0.2 monthsnono
Protection and control cabinetsReactor building35.04.1 months0.2 monthsnono
Main control roomReactor building39.15.6 months0.3 monthsnono
Plant wide cable terminationReactor building59.51.9 months0.0 monthsyesno
Cold hydro and hot functional testTesting and start64.310.0 months3.1 monthsyesno
Inspection closure and fuel loadTesting and start74.210.6 months3.0 monthsyesno
Power ascensionTesting and start84.89.2 months2.0 monthsyesno
Tests that do not need the vesselTesting and start61.32.9 months0.0 monthsyesno
Inspection records closed before the vesselTesting and start64.33.3 months0.0 monthsnono
Site headcount by month, cautious case
MeasurePeople
Peak3,817
Average1,705
Vogtle’s peak9,000
Month by month, from the first858 858 1,749 1,349 1,349 1,349 1,349 1,349 1,446 1,299 1,071 1,071 875 875 1,652 1,332 1,332 1,235 1,235 1,235 1,235 1,235 1,235 2,658 2,453 2,453 2,453 2,613 2,234 1,647 1,647 1,788 1,999 1,839 1,839 1,933 1,518 2,099 1,621 1,616 1,522 1,522 3,465 3,427 3,817 3,053 3,053 2,993 3,476 3,451 3,378 3,282 3,282 3,282 3,282 3,454 2,895 2,820 2,820 3,433 2,107 2,254 1,221 1,126 1,633 1,486 1,062 1,062 1,062 1,062 1,062 1,062 1,062 1,062 1,567 963 963 963 963 963 963 963 963 963 1,253 748 748 748 748 748 748 748 748 748 748

The machine

One vessel line, 12 vessels a year, sets the pace of all 200 sites.

The fleet

200 sites fill in vessel order, each 15 days by sea from Progreso; the vessel line sets the pace.

  1. land prepared
  2. civil
  3. vessel set
  4. testing
  5. power

since the order

0 years0 months

target

cautious

units online

0 units

0 units

power online

0.0 GW

0.0 GW

ships at sea

0 ships

0 ships

sites open

0 sites

0 sites

gangs at work

0 gangs

0 gangs

schematic: every site is 15 days from Progreso; positions are not geographic

Why it costs less · from Vogtle to Siderian

For the same reactor the model gives 9.0 million hours to 12.0 million hours on site per unit, where Vogtle took 25.0 million hours.

Vogtle is the baseline: both units averaged, as built. Everything below is what the model changes from there, each gain counted once, under the model’s assumptions.

Three ways to build it

Fewer hours on site, fewer months on site, cheaper electricity: the model gives 63 months to 94 months on site against Vogtle’s 125 months.

site hours per unit, million

15.4million hours

19.4million hours

All on site

Siderian’s program with every package built at the site. It is below Vogtle because Vogtle’s own causes are removed and the crews learn from site to site; nothing moves to the factory.

All on site
Siderian’s program with every package built at the site. It is below Vogtle because Vogtle’s own causes are removed and the crews learn from site to site; nothing moves to the factory.
months on site (grade: derived)
68 months97 months
cost of electricity, at 7% only
137 USD/MWh217 USD/MWh

25.0million hours

25.0million hours

As Vogtle was built

both units averaged, as built

As Vogtle was built
both units averaged, as built
months on site (grade: documented)
125 months125 months
cost of electricity
228 USD/MWh252 USD/MWh

9.0million hours

12.0million hours

Siderian

the same program with the work placed where the model finds it cheapest

Siderian
the same program with the work placed where the model finds it cheapest
months on site
63 months94 months
cost of electricity
114 USD/MWh181 USD/MWh

Cost of electricity at a 7% cost of money, under the model’s assumptions. “All on site” was evaluated at 7% only, so its figure does not follow the control. Vogtle’s months run from first concrete to commercial operation.

The numbers in this drawing
Way of buildingCaseSite hours per unitMonths on siteCost of electricity
All on sitetarget15.4 million hours68 months137 USD/MWh
All on sitecautious19.4 million hours97 months217 USD/MWh
As Vogtle was builttarget25.0 million hours125 months228 USD/MWh
As Vogtle was builtcautious25.0 million hours125 months252 USD/MWh
Sideriantarget9.0 million hours63 months114 USD/MWh
Sideriancautious12.0 million hours94 months181 USD/MWh

The ledger

From Vogtle’s 15,390 USD/kW to a fleet average of 7,360 USD/kW to 10,280 USD/kW, each gain taken once and in a fixed order.

This is the cost to build before any interest, often called the overnight cost. The packages are priced bottom up at Vogtle’s own hours and wages; what they do not explain of Vogtle’s cost, 6% in the target case and 1% in the cautious case, is carried unchanged through every stage and never reduced.

  1. Vogtle as built15,390 USD/kW15,390 USD/kW
  2. Causes particular to Vogtle−3,260 USD/kW−1,590 USD/kW
  3. One design and one program for 200 units−2,910 USD/kW−3,040 USD/kW
  4. Work moved to its place, net of the factory, ships and shipping−1,390 USD/kW−1,720 USD/kW
  5. Robots and factory tests−180 USD/kW−180 USD/kW
  6. Dedicated vendor lines−310 USD/kW−100 USD/kW
  7. Learning, to the fleet average−970 USD/kW−790 USD/kW
  8. Contingency990 USD/kW2,310 USD/kW
  9. Siderian, fleet average7,360 USD/kW10,280 USD/kW
The ledger as a table
StageWhat changestargetcautious
L0Vogtle as built15,390 USD/kW15,390 USD/kW
L1Causes particular to Vogtle−3,260 USD/kW−1,590 USD/kW
One programOne design and one program for 200 units−2,910 USD/kW−3,040 USD/kW
L2Work moved to its place, net of the factory, ships and shipping−1,390 USD/kW−1,720 USD/kW
L3Robots and factory tests−180 USD/kW−180 USD/kW
L4Dedicated vendor lines−310 USD/kW−100 USD/kW
L5Learning, to the fleet average−970 USD/kW−790 USD/kW
+Contingency990 USD/kW2,310 USD/kW
=Siderian, fleet average7,360 USD/kW10,280 USD/kW
Share of Vogtle’s cost the packages do not explain6%1%

Vogtle’s causes, Siderian’s fixes

Each cause of Vogtle’s cost that the model prices has a named fix, and each fix is priced in one place.

At VogtleIts size thereIn SiderianPriced in
Design unfinished at startabout 1,000 USD/kW, 19 monthsThe design is frozen before unit 1priced in Vogtle’s own causes
First use of the licence process, 188 amendmentsabout 1,600 USD/kW, 28 monthsThe same design every unit; records closed in the factory where allowedpriced in Vogtle’s own causes
Contractor failure and switchabout 500 USD/kW, 10 monthsOne integrator for all 200priced in Vogtle’s own causes
Half of site hours were supervision and support0.53 + 0.46 hours per craft hourFewer people on site, and their support with thempriced in work moved to its place
The other causes and their fixes
Sub modules from a new shop with wrong welds, joined on sitestop work in 2013Modules complete from Progreso, robot welded, fit checked before shippingpriced in Vogtle’s own causes, work moved to its place, robots and factory tests
Basemat rebar and mudmat nonconformancesdelayed first concreteRebar cages built and inspected at Progresopriced in robots and factory tests
Vendor quality escapes (pumps, valves)a pump redesign delayed China’s unitsDedicated lines, tested before shippingpriced in robots and factory tests
Electrical and cable reworknot quantifiedCabinets and cable sets tested as whole systems in the test hallspriced in robots and factory tests
Test sequence at the endhot functional test 94 days, then 42A standard sequence run by the same crewpriced in site schedule
Lost craft experienceabout 2,900 USD/kWTravelling crews and a standing factory workforcepriced in learning

“Priced in” names the row of the ledger above where the fix is counted. Sizes are as published for Vogtle.

Why it costs less · where the work goes

Of Vogtle’s 25.0 million hours on site per unit, the model leaves 9.0 to 12.0 million there and gives Progreso 0.4 to 2.2 million.

Hours per unit, by place

Hours that leave the site do not arrive whole: in the model one factory hour replaces several site hours, and part of Vogtle’s hours is not worked at all.

The model gives 9.0 million hours (target) and 12.0 million hours (cautious) per unit still worked on site. Hours moved to the factory shrink. One hour in a shop replaces 8 to 5 hours inside the plant, for fitting out (grade: judged), 3 to 2 hours in an open yard, for fitting out (grade: judged) and 3 to 2 hours inside the plant, for plate and rebar (grade: judged) . The rule comes from shipyards and is used here as an analogy. The band that fades out is the rest of the fall: Vogtle’s own excess, removed first, and learning across the fleet. Vendor hours are those of Vogtle’s module shops, unchanged.

The numbers in this drawing
Hours per unit at steady state, by place
Placetargetcautious
Vogtle, shops1,557 thousand hours1,557 thousand hours
Vogtle, site24,984 thousand hours24,984 thousand hours
Vogtle, all places26,541 thousand hours26,541 thousand hours
Siderian, vendors1,557 thousand hours1,557 thousand hours
Siderian, Progreso383 thousand hours2,177 thousand hours
Siderian, site9,032 thousand hours12,043 thousand hours
Siderian, all places10,973 thousand hours15,778 thousand hours

The plant, package by package

50 packages, each sized by the site hours it took at Vogtle; the edge of each shows where the model does its movable work, the small arrow where its vendor parts go.

  • finished at Progreso
  • sold complete by a vendor
  • stays on site
  • barefitted outfitted out and tested
  • shipped completein pieces
  • vendor parts straight to the sitethrough Progreso
  • the cautious case chooses differently

Land and site worksLand and site works

SClearing and grading: site work that cannot leave the site
SClearing and grading: site work that cannot leave the site
SExcavation and dewatering: site work that cannot leave the site
SExcavation and dewatering: site work that cannot leave the site
SEngineered backfill: site work that cannot leave the site
SEngineered backfill: site work that cannot leave the site
SUnloading quay and heavy haul road: site work that cannot leave the site
SUnloading quay and heavy haul road: site work that cannot leave the site
SCooling water works and towers: site work that cannot leave the site
SCooling water works and towers: site work that cannot leave the site
PSwitchyard: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PSwitchyard: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PSite buildings: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PSite buildings: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso

Nuclear island structureNuclear island structure

PBasemat rebar cages: finished at Progreso, bare, shipped complete; vendor parts go through Progreso
SBasemat rebar cages: kept on site, by the model’s choice; vendor parts go straight to the site
SBasemat concrete: site work that cannot leave the site
SBasemat concrete: site work that cannot leave the site
SContainment bottom head: kept on site, by the model’s choice; vendor parts go through Progreso
SContainment bottom head: kept on site, by the model’s choice; vendor parts go straight to the site
PContainment rings: finished at Progreso, fitted out and tested, shipped in pieces; vendor parts go through Progreso
PContainment rings: finished at Progreso, bare, shipped complete; vendor parts go through Progreso
PContainment top head: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PContainment top head: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Structural modules CA01, CA02 to CA05, CA20P: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Structural modules CA01, CA02 to CA05, CA20P: finished at Progreso, fitted out, shipped complete; vendor parts go through Progreso
PShield building panels: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PShield building panels: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PShield building roof and water tank: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PShield building roof and water tank: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Interior concreteS: site work that cannot leave the site
Interior concreteS: site work that cannot leave the site
Auxiliary and fuel building concreteS: site work that cannot leave the site
Auxiliary and fuel building concreteS: site work that cannot leave the site
PEmbeds and penetrations: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PEmbeds and penetrations: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PSteel platforms and stairs: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PSteel platforms and stairs: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
SCoatings and liner closure: site work that cannot leave the site
SCoatings and liner closure: site work that cannot leave the site

Mechanical and electricalNuclear island mechanical and electrical

Piping modulesP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Piping modulesP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PMechanical equipment modules: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PMechanical equipment modules: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PElectrical equipment modules: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PElectrical equipment modules: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Large pipe spoolsP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Large pipe spoolsP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Cable setsP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Cable setsP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PVentilation: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PVentilation: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso

Primary componentsPrimary components

Reactor vessel: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
Reactor vessel: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
VSteam generators: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
VSteam generators: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
Pressurizer: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
Pressurizer: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
VCoolant pumps: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
VCoolant pumps: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
Head package and control rod drives: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
Head package and control rod drives: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
Internals: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
Internals: sold complete by its vendor; the rest is site work; vendor parts go through Progreso
PPassive safety tanks and heat exchanger: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
SPassive safety tanks and heat exchanger: kept on site, by the model’s choice; vendor parts go straight to the site

Turbine islandTurbine island

Turbine building blocksP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Turbine building blocksP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Turbine generatorV: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
Turbine generatorV: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
CondenserP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
CondenserP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
VMoisture separator reheaters: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
VMoisture separator reheaters: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
PFeedwater train: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PFeedwater train: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
VTransformers: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
VTransformers: sold complete by its vendor; the rest is site work; vendor parts go straight to the site
Turbine island pipe and cableP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Turbine island pipe and cableP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso

Other buildingsOther buildings

Annex buildingP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
Annex buildingP: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PDiesel building: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PDiesel building: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PWaste building: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PWaste building: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PAuxiliary electrical rooms: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PAuxiliary electrical rooms: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso

Instrument and controlInstrument and control

PProtection and control cabinets: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PProtection and control cabinets: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PMain control room: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PMain control room: finished at Progreso, fitted out and tested, shipped complete; vendor parts go through Progreso
PPlant wide cable termination: finished at Progreso, fitted out and tested, shipped complete
PPlant wide cable termination: finished at Progreso, fitted out and tested, shipped complete

Tests and startTests and start

Cold hydro and hot functional testS: site work that cannot leave the site
Cold hydro and hot functional testS: site work that cannot leave the site
Inspection closure and fuel loadS: site work that cannot leave the site
Inspection closure and fuel loadS: site work that cannot leave the site
SPower ascension: site work that cannot leave the site
SPower ascension: site work that cannot leave the site

Point at a block, or touch it, to read the package. The filled blocks are the largest; a block keeps its Vogtle size, and only its edge, its depth and its piece size are the model’s choice.

The choices that matter most

The eight packages where the choice of place counts most: how much worse the next best choice would be, per unit.

Unless a row says otherwise, the model finishes the package at Progreso, fitted out and tested, and ships it completefinishes the package at Progreso, fitted out and tested, and ships it complete: the usual choice.

Of the packages with vendor parts to route, the model sends 5 straight to the site and 32 through Progreso in the target case and, in the cautious case, 9 straight to the site and 28 through Progreso. At Progreso they are received, inspected, held and shipped on. In the target case the The parts of containment bottom head, pressurizer, coolant pumps, head package and control rod drives and internals go through Progreso although the work itself stays where it was. In the cautious case the The parts of pressurizer, head package and control rod drives and internals go through Progreso although the work itself stays where it was. In the model’s terms, a defect caught at Progreso before it reaches the site is worth the detour; the vessel and the heaviest pieces go straight, because a detour would cost more or, for the vessel, hold up the site.

PackageWhere the model does its movable workIts vendor parts goNext best choice
would cost more by
Site hours now, of Vogtle’s,
thousand per unit
Turbine island pipe and cableTurbine islandthe usual choicethrough Progreso106.6 million USD164.6 million USD1,033of3,9001,425of3,900
Cable setsNuclear island mechanical and electricalthe usual choicethrough Progreso50.3 million USD72.7 million USD212of1,000292of1,000
Plant wide cable terminationInstrument and controlthe usual choicelocal material, nothing to route40.0 million USD74.7 million USD95of400132of400
Basemat rebar cagesNuclear island structureProgreso, bare, completesitethrough Progresostraight to the site25.0 million USD16.1 million USD72of190145of190
Large pipe spoolsNuclear island mechanical and electricalthe usual choicethrough Progreso11.8 million USD7.9 million USD554of1,900764of1,900
Protection and control cabinetsInstrument and controlthe usual choicethrough Progreso11.7 million USD17.1 million USD32of15044of150
Turbine building blocksTurbine islandthe usual choicethrough Progreso11.1 million USD12.1 million USD180of850245of850
Piping modulesNuclear island mechanical and electricalthe usual choicethrough Progreso9.8 million USD13.9 million USD40of63355of633
PackageWhere the model does its movable workIts vendor parts goNext best choice
would cost more by
Site hours now, of Vogtle’s,
thousand per unit
Turbine island pipe and cableTurbine islandthe usual choicethrough Progreso106.6 million USD164.6 million USD1,033of3,9001,425of3,900
Plant wide cable terminationInstrument and controlthe usual choicelocal material, nothing to route40.0 million USD74.7 million USD95of400132of400
Cable setsNuclear island mechanical and electricalthe usual choicethrough Progreso50.3 million USD72.7 million USD212of1,000292of1,000
Reactor vesselPrimary componentsvendorvendorstraight to the site1.3 million USD17.7 million USD36of6046of60
Protection and control cabinetsInstrument and controlthe usual choicethrough Progreso11.7 million USD17.1 million USD32of15044of150
Basemat rebar cagesNuclear island structureProgreso, bare, completesitethrough Progresostraight to the site25.0 million USD16.1 million USD72of190145of190
Piping modulesNuclear island mechanical and electricalthe usual choicethrough Progreso9.8 million USD13.9 million USD40of63355of633
Turbine building blocksTurbine islandthe usual choicethrough Progreso11.1 million USD12.1 million USD180of850245of850

Per unit, at steady state. A package with no choice is left out: a vendor sells it complete, or its work cannot leave the site. Where a cell has two lines, the first is the target case and the second the cautious case; the order is the target case’s.

All 50 packages, with hours at each place, weight shipped and a sort control
PackagePlaceFinished thereShippedVendor parts goVendor
hours
Progreso
hours
Site
hours
Vogtle
site hours
Next best choice,
million USD a unit
Shipped,
tonnes
Clearing and gradingLand and site workssitesite––––––000091126180no choiceno choice–
Excavation and dewateringLand and site workssitesite––––––0000302420600no choiceno choice–
Engineered backfillLand and site workssitesite––––––0000151210300no choiceno choice–
Unloading quay and heavy haul roadLand and site workssitesite––––––0000126175250no choiceno choice–
Cooling water works and towersLand and site workssitesite––––––00006818751,150no choiceno choice–
SwitchyardLand and site worksProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0063372982703.64.2400
Site buildingsLand and site worksProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso006351361864002.61.71,200
Basemat rebar cagesNuclear island structureProgresositebare–complete–through Progresostraight to the site00307214519025.016.11,800
Basemat concreteNuclear island structuresitesite––––––00007191120no choiceno choice–
Containment bottom headNuclear island structuresitesite––––through Progresostraight to the site1313005774970.65.6–
Containment ringsNuclear island structureProgresoProgresofitted out and testedbarein piecescompletethrough Progresothrough Progreso434388254363170.68.92,220
Containment top headNuclear island structureProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso111142246790.70.1655
Structural modules CA01, CA02 to CA05, CA20Nuclear island structureProgresoProgresofitted out and testedfitted outcompletecompletethrough Progresothrough Progreso3223221176112483451,9786.33.02,400
Shield building panelsNuclear island structureProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso154154847781052861.10.71,950
Shield building roof and water tankNuclear island structureProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso787874038501821.82.11,234
Interior concreteNuclear island structuresitesite––––––00008591,1041,450no choiceno choice–
Auxiliary and fuel building concreteNuclear island structuresitesite––––––00007119141,200no choiceno choice–
Embeds and penetrationsNuclear island structureProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso004261231673302.31.5150
Steel platforms and stairsNuclear island structureProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso787894723311820.40.3500
Coatings and liner closureNuclear island structuresitesite––––––0000536990no choiceno choice–
Piping modulesNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso5185181911140556339.813.91,400
Mechanical equipment modulesNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso240240106029393607.010.01,100
Electrical equipment modulesNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso10010042510131503.85.5165
Large pipe spoolsNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso00271605547641,90011.87.91,000
Cable setsNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso00181042122921,00050.372.7600
VentilationNuclear island mechanical and electricalProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0031536491502.12.5150
Reactor vesselPrimary componentsvendorvendor––––straight to the sitestraight to the site00003646601.317.7–
Steam generatorsPrimary componentsvendorvendor––––straight to the sitestraight to the site00005369901.34.7–
PressurizerPrimary componentsvendorvendor––––through Progresothrough Progreso00012430401.79.0–
Coolant pumpsPrimary componentsvendorvendor––––through Progresostraight to the site001065841100.46.7–
Head package and control rod drivesPrimary componentsvendorvendor––––through Progresothrough Progreso00023646600.30.9–
InternalsPrimary componentsvendorvendor––––through Progresothrough Progreso00022430400.40.9–
Passive safety tanks and heat exchangerPrimary componentsProgresositefitted out and tested–complete–through Progresostraight to the site000060911201.33.5700
Turbine building blocksTurbine islandProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso002614818024585011.112.15,500
Turbine generatorTurbine islandvendorvendor––––straight to the sitestraight to the site00004445717501.27.1–
CondenserTurbine islandProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso004251562154203.32.2900
Moisture separator reheatersTurbine islandvendorvendor––––straight to the sitestraight to the site0000891141503.16.6–
Feedwater trainTurbine islandProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso003181111533005.05.6600
TransformersTurbine islandvendorvendor––––straight to the sitestraight to the site000071911203.06.7–
Turbine island pipe and cableTurbine islandProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso00623641,0331,4253,900106.6164.62,000
Annex buildingOther buildingsProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso009502373246504.63.01,500
Diesel buildingOther buildingsProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0031857771802.62.8400
Waste buildingOther buildingsProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0052873992502.73.2700
Auxiliary electrical roomsOther buildingsProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0052944592004.15.4500
Protection and control cabinetsInstrument and controlProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso00316324415011.717.1200
Main control roomInstrument and controlProgresoProgresofitted out and testedfitted out and testedcompletecompletethrough Progresothrough Progreso0042142582008.311.8150
Plant wide cable terminationInstrument and controlProgresoProgresofitted out and testedfitted out and testedcompletecomplete––006389513240040.074.7–
Cold hydro and hot functional testTests and startsitesite––––––0000533685900no choiceno choice–
Inspection closure and fuel loadTests and startsitesite––––––0000474609800no choiceno choice–
Power ascensionTests and startsitesite––––––0000237305400no choiceno choice–

Hours are thousand hours per unit at steady state.

Why it costs less · the price of less site labor, and of speed

The model finds no price for less site labor: its cost of electricity falls at every step down in site hours. Speed has a price, and it is small.

The brief asks for as little labor as possible, above all on site, and for the quickest fleet. Each could cost something; here is what the model gives for both, under its assumptions.

The price of less site labor

Allowed fewer and fewer site hours, the model gives 114 USD/MWh at 9.0 million hours in the target case and 181 USD/MWh at 12.0 million hours in the cautious case on site per unit: the point it chooses.

In both cases the model gives a lower cost of electricity at every step down in site hours, from the plan with everything on site to the chosen point, so the fewest site hours is also the cheapest. The rule for the chosen point: the fewest site hours whose cost is within one percent of the lowest. Each dot is the whole problem solved again with fewer site hours allowed, at a 7% cost of money; the curve does not follow the control.

The numbers in this drawing
Each row is one solve under a cap on site hours per unit
CaseCap on site hoursSite hoursHours, all placesCost of electricityYears to the last unitChosen
target13.8 million hours13.0 million hours14.7 million hours126 USD/MWh23.9 years
target13.0 million hours12.4 million hours14.1 million hours123 USD/MWh23.8 years
target12.1 million hours11.5 million hours13.3 million hours121 USD/MWh23.8 years
target11.3 million hours10.8 million hours12.6 million hours119 USD/MWh23.8 years
target10.5 million hours10.0 million hours11.9 million hours117 USD/MWh23.8 years
target9.7 million hours9.3 million hours11.2 million hours115 USD/MWh23.8 years
target8.9 million hours9.0 million hours11.0 million hours114 USD/MWh23.6 yearschosen
cautious18.5 million hours17.9 million hours19.8 million hours204 USD/MWh42.5 years
cautious17.5 million hours16.9 million hours19.1 million hours199 USD/MWh42.5 years
cautious16.6 million hours16.0 million hours18.5 million hours195 USD/MWh42.3 years
cautious15.6 million hours15.1 million hours18.0 million hours191 USD/MWh42.3 years
cautious14.7 million hours14.2 million hours17.3 million hours188 USD/MWh42.3 years
cautious13.8 million hours13.3 million hours16.6 million hours185 USD/MWh42.4 years
cautious12.8 million hours12.4 million hours16.0 million hours183 USD/MWh42.3 years
cautious11.9 million hours12.0 million hours15.8 million hours181 USD/MWh42.2 yearschosen

The price of speed

At 24 vessels a year the model gives the last unit at power in 15.8 years at 117 USD/MWh; at 6 a year, in 40.3 years at 112 USD/MWh.At 24 vessels a year the model gives the last unit at power in 18.0 years at 186 USD/MWh; at 6 a year, in 42.5 years at 179 USD/MWh. Speed moves the years far more than the cost.

24 a year is outside the brief: it needs a second vessel line, whose capital is included. Each point is the whole problem solved again at that pace, with the factory, the ships and the vendor lines sized for it.

what the slower fleet gives up

At 6 vessels a year in place of 12, the model gives the last unit 16.5 years later and 14,702 TWh less electricity on the way, worth 588–1,470 billion USD at power prices of 40–100 USD/MWh. The cost of electricity above counts each unit from its own first day of power, so it gives no credit for being early; this is that credit.

The numbers in this drawing
Vessels a yearCaseYears to the last unitCost of electricityNote
6target40.3 years112 USD/MWh
6cautious42.5 years179 USD/MWh
12target23.6 years114 USD/MWh
12cautious26.1 years182 USD/MWh
24target15.8 years117 USD/MWhoutside the brief: needs a second vessel line
24cautious18.0 years186 USD/MWhoutside the brief: needs a second vessel line

How far to trust the answer

This is the best plan the model found, not one proved best. Every plan drawn by hand comes out at least as dear.

With the model’s split of work between factory and site kept, sending every vendor part straight to the site gives 114.2 USD/MWh (181.6 USD/MWh cautious) and sending every one through Progreso gives 114.2 USD/MWh (182.0 USD/MWh cautious), against 114.2 USD/MWh (181.5 USD/MWh cautious) for the model’s own mix; starting every site early enough to have all other work done when the vessel arrives gives 119.2 USD/MWh (190.7 USD/MWh cautious).

When one of the inputs that set where work is cheapest moves by 20%, the model changes its choice for containment bottom head and containment rings in the target case; every other package stays where it is. In the cautious case it changesWhen one of those inputs moves by 20%, the model changes its choice for basemat rebar cages, containment bottom head, containment rings, containment top head, structural modules CA01, CA02 to CA05, CA20 and head package and control rod drives. The cost of money moves containment bottom head, containment rings, reactor vessel, steam generators, turbine generator, basemat rebar cages, coolant pumps and structural modules CA01, CA02 to CA05, CA20 in the target case.

The checks in full: the plans drawn by hand, what flips, how the answer was reached
Plans drawn by hand and the model’s answer
PlanCaseCost of electricitySite hours per unit
All on sitetarget137.0 USD/MWh15.4 million hours
As Vogtle was builttarget227.9 USD/MWh25.0 million hours
The model’s split of work, every vendor part straight to the sitetarget114.2 USD/MWh9.0 million hours
The model’s split of work, every vendor part through Progresotarget114.2 USD/MWh9.0 million hours
The model’s answer, the site started as late as possibletarget114.2 USD/MWh9.0 million hours
The model’s answer, the site started early enough to have all other work done when the vessel arrivestarget119.2 USD/MWh9.3 million hours
Most to Progreso, shipped in piecestarget115.3 USD/MWh9.4 million hours
Everything to Progreso, shipped completetarget114.3 USD/MWh8.9 million hours
The model’s answertarget114.2 USD/MWh9.0 million hours
All on sitecautious217.1 USD/MWh19.4 million hours
As Vogtle was builtcautious252.0 USD/MWh25.0 million hours
The model’s split of work, every vendor part straight to the sitecautious181.6 USD/MWh12.0 million hours
The model’s split of work, every vendor part through Progresocautious182.0 USD/MWh12.0 million hours
The model’s answer, the site started as late as possiblecautious181.5 USD/MWh12.0 million hours
The model’s answer, the site started early enough to have all other work done when the vessel arrivescautious190.7 USD/MWh12.2 million hours
Most to Progreso, shipped in piecescautious183.9 USD/MWh12.5 million hours
Everything to Progreso, shipped completecautious182.5 USD/MWh11.8 million hours
The model’s answercautious181.5 USD/MWh12.0 million hours
Which choices flip when an input moves
CaseInput movedByChoices that change
targetShop against site hours, outfittingShop against site hours, plate and rebarProgreso wageSite wageShippingRobot cellsNew shop at Progreso20% lower20% lower20% higher20% lower20% dearer20% dearerhours 20% higherContainment bottom head (site, parts through Progreso → bare, complete)Containment rings (tested, pieces → tested, complete)
cautiousShop against site hours, outfittingShop against site hours, plate and rebarProgreso wageSite wageShippingRobot cellsNew shop at Progreso20% lower20% lower20% higher20% lower20% dearer20% dearerhours 20% higherBasemat rebar cages (site → bare, complete)Containment bottom head (site → bare, complete)Containment rings (bare, complete → tested, complete)Containment top head (tested, complete → tested, pieces)Structural modules CA01, CA02 to CA05, CA20 (fitted out, complete → tested, complete)Head package and control rod drives (site, parts through Progreso → site, parts straight to the site)
How the answer was reached
CaseRounds until the plan stopped changingSettledChoices that change with the cost of money
target2 roundsyesContainment bottom head: bare/complete at 0%, site, parts through Progreso at 7%Containment rings: tested/complete at 0%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 0%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 0%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 0.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 0.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 1%, site, parts through Progreso at 7%Containment rings: tested/complete at 1%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 1%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 1.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 1.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 2%, site, parts through Progreso at 7%Containment rings: tested/complete at 2%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 2%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 2%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 2%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 2.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 2.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 3%, site, parts through Progreso at 7%Containment rings: tested/complete at 3%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 3%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 3%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 3.5%, site, parts through Progreso at 7%Containment rings: tested/complete at 3.5%, tested/pieces at 7%Reactor vessel: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 4%, site, parts through Progreso at 7%Containment rings: tested/complete at 4%, tested/pieces at 7%Containment bottom head: bare/complete at 4.5%, site, parts through Progreso at 7%Reactor vessel: site, parts through Progreso at 4.5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 5%, site, parts through Progreso at 7%Reactor vessel: site, parts through Progreso at 5%, site, parts straight to the site at 7%Containment bottom head: bare/complete at 5.5%, site, parts through Progreso at 7%Containment bottom head: bare/complete at 6%, site, parts through Progreso at 7%Basemat rebar cages: site at 8.5%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 8.5%, site, parts through Progreso at 7%Containment rings: bare/complete at 8.5%, tested/pieces at 7%Basemat rebar cages: site at 9%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 9%, site, parts through Progreso at 7%Containment rings: bare/complete at 9%, tested/pieces at 7%Steam generators: site, parts through Progreso at 9%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 9%, site, parts through Progreso at 7%Basemat rebar cages: site at 9.5%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Containment rings: bare/complete at 9.5%, tested/pieces at 7%Steam generators: site, parts through Progreso at 9.5%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Basemat rebar cages: site at 10%, bare/complete at 7%Containment bottom head: site, parts straight to the site at 10%, site, parts through Progreso at 7%Containment rings: bare/complete at 10%, tested/pieces at 7%Structural modules CA01, CA02 to CA05, CA20: fitted out/complete at 10%, tested/complete at 7%Steam generators: site, parts through Progreso at 10%, site, parts straight to the site at 7%Coolant pumps: site, parts straight to the site at 10%, site, parts through Progreso at 7%
cautious3 roundsyesBasemat rebar cages: bare/complete at 0%, site at 7%Containment bottom head: bare/complete at 0%, site at 7%Containment rings: fitted out/complete at 0%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 0%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 0%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 0%, site at 7%Turbine generator: site, parts through Progreso at 0%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 0.5%, site at 7%Containment bottom head: bare/complete at 0.5%, site at 7%Containment rings: fitted out/complete at 0.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 0.5%, site at 7%Turbine generator: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 0.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 1%, site at 7%Containment bottom head: bare/pieces at 1%, site at 7%Containment rings: tested/complete at 1%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 1%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 1%, site, parts straight to the site at 7%Turbine generator: site, parts through Progreso at 1%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 1%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 1.5%, site at 7%Containment bottom head: bare/pieces at 1.5%, site at 7%Containment rings: tested/complete at 1.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Steam generators: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 1.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 2%, site at 7%Containment bottom head: bare/pieces at 2%, site at 7%Containment rings: tested/complete at 2%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2%, fitted out/complete at 7%Steam generators: site, parts through Progreso at 2%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 2%, site at 7%Transformers: site, parts through Progreso at 2%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 2.5%, site at 7%Containment bottom head: bare/pieces at 2.5%, site at 7%Containment rings: tested/complete at 2.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Transformers: site, parts through Progreso at 2.5%, site, parts straight to the site at 7%Basemat rebar cages: bare/complete at 3%, site at 7%Containment bottom head: bare/pieces at 3%, site at 7%Containment rings: tested/complete at 3%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 3%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 3%, site, parts straight to the site at 7%Moisture separator reheaters: site, parts through Progreso at 3%, site, parts straight to the site at 7%Containment bottom head: bare/pieces at 3.5%, site at 7%Containment rings: fitted out/pieces at 3.5%, bare/complete at 7%Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3.5%, fitted out/complete at 7%Reactor vessel: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 3.5%, site at 7%Transformers: site, parts through Progreso at 3.5%, site, parts straight to the site at 7%Reactor vessel: site, parts through Progreso at 4%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 4%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 4%, site at 7%Coolant pumps: site, parts through Progreso at 4.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 4.5%, site at 7%Coolant pumps: site, parts through Progreso at 5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 5%, site at 7%Passive safety tanks and heat exchanger: tested/complete at 5.5%, site at 7%Moisture separator reheaters: site, parts through Progreso at 5.5%, site, parts straight to the site at 7%Passive safety tanks and heat exchanger: tested/complete at 6%, site at 7%Moisture separator reheaters: site, parts through Progreso at 6%, site, parts straight to the site at 7%Coolant pumps: site, parts through Progreso at 6.5%, site, parts straight to the site at 7%Head package and control rod drives: site, parts straight to the site at 6.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 7.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 7.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 8%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 8%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 8.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 8.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 9%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 9%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 9.5%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 9.5%, site, parts through Progreso at 7%Shield building roof and water tank: tested/pieces at 10%, tested/complete at 7%Head package and control rod drives: site, parts straight to the site at 10%, site, parts through Progreso at 7%

Each round solves a mixed integer program to zero gap and then evaluates its answer exactly; after the last round every single change of one package is tried on the exact model and kept only if it lowers the cost. That finds a good answer and rules out its neighbours. It does not prove that no better one exists.

7%

The price · cost

Before any interest, the model gives the average unit a cost of 7,360 USD/kW10,280 USD/kW.

This cost before interest is called the overnight cost: what a unit would cost if it were built in a night. At a 7% cost of money, interest raises it to 9,050 USD/kW14,210 USD/kW. In 2025 dollars for each kW of output, under the model’s assumptions.

Cost before interest, line by line

The largest line is vendor hardware and materials: the model gives 2,200 USD/kW2,630 USD/kW.

Contingency, an allowance for the plan running over, adds 980 USD/kW2,280 USD/kW. Each bar starts where the one above ends, a saving runs back to the left, and the last bar is their sum.

  1. VVendor hardware and materialsJ

    2,200

    2,630

  2. PProgreso laborT

    10

    90

  3. PShippingJ

    20

    30

  4. SSite labor, craft and supportV

    980

    1,410

  5. SSite staff, crane and general conditionsJ

    740

    1,300

  6. SConstruction equipment, temporary works, feeJ

    540

    810

  7. SCrew travel, site design, waitingJ

    10

    40

  8. VRouting of vendor parts: detours, defects caught early, waits for late partsJ

    −10

    30

  9. Owner’s cost: licensing, staff, training, connectionJ

    420

    700

  10. First fuel coreD

    330

    340

  11. Not allocated (Vogtle remainder)V

    990

    230

  12. VVendor dedicated linesJ

    50

    70

  13. PProgreso, robots, ships, design, management (even share)J

    100

    320

  14. ContingencyJ

    980

    2,280

  15. Cost before interest

    7,360

    10,280

DdocumentedVderivedJjudgedTtarget

Every line at unit 1, on average and at unit 200
Cost before interest by line, target case, USD/kW
LinePlaceGradeUnit 1Fleet averageUnit 200
Vendor hardware and materialsvendorjudged2,7602,2002,090
Progreso laborProgresotarget201010
ShippingProgresojudged202020
Site labor, craft and supportsitederived1,150980880
Site staff, crane and general conditionssitejudged940740680
Construction equipment, temporary works, feesitejudged640540490
Crew travel, site design, waitingsitejudged101010
Routing of vendor parts: detours, defects caught early, waits for late partsvendorjudged−20−10−10
Owner’s cost: licensing, staff, training, connectionnot one placejudged420420420
First fuel corenot one placedocumented330330330
Not allocated (Vogtle remainder)not one placederived990990990
Vendor dedicated linesvendorjudged505050
Progreso, robots, ships, design, management (even share)Progresojudged100100100
Contingencynot one placejudged2,010980850
Cost before interest9,4407,3606,910
Cost before interest by line, cautious case, USD/kW
LinePlaceGradeUnit 1Fleet averageUnit 200
Vendor hardware and materialsvendorjudged2,9702,6302,560
Progreso laborProgresotarget2309080
ShippingProgresojudged303030
Site labor, craft and supportsitederived1,5901,4101,330
Site staff, crane and general conditionssitejudged1,6001,3001,220
Construction equipment, temporary works, feesitejudged930810760
Crew travel, site design, waitingsitejudged404040
Routing of vendor parts: detours, defects caught early, waits for late partsvendorjudged303030
Owner’s cost: licensing, staff, training, connectionnot one placejudged700700700
First fuel corenot one placedocumented340340340
Not allocated (Vogtle remainder)not one placederived230230230
Vendor dedicated linesvendorjudged707070
Progreso, robots, ships, design, management (even share)Progresojudged320320320
Contingencynot one placejudged4,1902,2802,060
Cost before interest13,28010,2809,770

Unit 1 to unit 200

With repetition, the model brings the last unit down to 6,910 USD/kW9,770 USD/kW.

The first unit costs 9,440 USD/kW13,280 USD/kW, before interest.

9,440

8,290

7,200

6,910

13,280

11,480

10,110

9,770

unit 110100200

USD/kW, before interest. Learning acts on hours, never on materials, and stops at a floor. Each step to the right is ten times as many units.

The numbers in this drawing
Cost before interest by unit, USD/kW
Unittarget casecautious case
19,44013,280
29,02012,620
58,54011,840
108,29011,480
207,97011,040
507,54010,490
1007,20010,110
1507,0509,910
2006,9109,770

What interest adds

At 7%, the model adds 1,550 USD/kW3,310 USD/kW of interest during the build.

Interest on the program’s own capital adds 150 USD/kW620 USD/kW.

target case, with all interest9,050 USD/kW

cost before interest
7,360 USD/kW
interest during the build
1,550 USD/kW
interest on the program’s own capital
150 USD/kW

cautious case, with all interest14,210 USD/kW

cost before interest
10,280 USD/kW
interest during the build
3,310 USD/kW
interest on the program’s own capital
620 USD/kW

The program’s own capital is Progreso, the ships, the design and the vendors’ lines. Its interest runs from the day each was paid for until each unit is delivered.

The same at every cost of money
Cost per kW by cost of money, target case, USD/kW
Cost of moneyBefore interestInterest during the buildInterest on program capitalWith all interest
0%, to check the sums7,310007,310
0.5%7,310100107,430
1%7,310210207,540
1.5%7,310320307,660
2%7,310430307,770
2.5%7,310540407,890
3%7,310650508,020
3.5%7,310760708,140
4%7,320880708,270
4.5%7,330980908,390
5%7,3301,1001008,520
5.5%7,3301,2201108,650
6%7,3301,3401208,790
6.5%7,3601,4301308,920
7%7,3601,5501509,050
7.5%7,3601,6701609,190
8%7,3601,7901809,330
8.5%7,3601,9201909,480
9%7,3602,0502109,620
9.5%7,3602,1802309,760
10%7,3702,3002409,910
Cost per kW by cost of money, cautious case, USD/kW
Cost of moneyBefore interestInterest during the buildInterest on program capitalWith all interest
0%, to check the sums10,2200010,220
0.5%10,2202103010,450
1%10,2204306010,700
1.5%10,2206409010,960
2%10,23087012011,220
2.5%10,2201,10016011,480
3%10,2201,33020011,760
3.5%10,2601,54024012,030
4%10,2701,77028012,330
4.5%10,2802,02032012,620
5%10,2802,26038012,920
5.5%10,2802,52043013,230
6%10,2802,77049013,540
6.5%10,2803,04055013,870
7%10,2803,31062014,210
7.5%10,2803,58069014,550
8%10,2803,86076014,910
8.5%10,2804,15084015,280
9%10,2804,44093015,650
9.5%10,2804,7401,02016,040
10%10,2805,0401,11016,440

What is counted

The model’s figure counts more than the published ones it stands beside: the first fuel, the owner’s cost, a contingency and the program’s own capital are inside it.

this model
7,360 USD/kW10,280 USD/kW
Vogtle, as built
15,390 USD/kW
The next pair
9,590 USD/kW
A mature plant
4,820 USD/kW
What each figure counts, line by line

Interest during the build

this modelleft out of this figure; shown beside it

Vogtle, as builtleft out

published estimatesleft out

Progreso, robots, ships, design and management

this modelcounted at what was spent, an even share for every unit, without interest

Vogtle, as builtits own first design and licence are inside the figure

published estimatesno factory; design taken as done

Vendors’ dedicated lines

this modelcounted the same way, at what was spent

Vogtle, as builtnone

published estimatesnone

Owner’s cost

this modelcounted

Vogtle, as builtcounted

published estimatescounted

First fuel core

this modelcounted

Vogtle, as builtnot stated

published estimatesnot stated

Contingency

this modelcounted, as an expected overrun on the plan

Vogtle, as builtits overruns are in the figure, as built

published estimatesleft out; the authors add a quarter

The part of Vogtle’s cost the packages do not explain

this modelcounted, unchanged

Vogtle, as builtinside the figure

published estimatesdoes not arise

The model puts neither case below the published estimate for a mature plant; had it, that would be flagged here and at the top of the page.

Published figures are from MIT and Idaho National Laboratory, put into 2025 dollars with one price index.

The price · LCOE

At a 7% cost of money, the model gives electricity from the average unit at 114 USD/MWh181 USD/MWh.

This is the levelized cost of electricity, LCOE: every dollar spent over a plant’s life divided by every MWh it makes, both discounted at the cost of money. Real, before income tax, under the model’s assumptions.

Average unit LCOE against the cost of money

Dearer money moves capital and its interest; running the plant and fuelling it barely change.

When money costs 3% the model gives 72 USD/MWh111 USD/MWh. At 10% it gives 155 USD/MWh257 USD/MWh.

target case

114USD/MWh at 7%

100200300 USD/MWhVogtlenext AP1000 pairmature AP1000BarakahShin Korirange of runstarget case0%to check the sums3%5%7%10%
the program’s own capital, with its interest
3 USD/MWh
interest during the build
13 USD/MWh
building the unit, before interest
62 USD/MWh
spent fuel and property tax
3 USD/MWh
fuel
10 USD/MWh
operation
24 USD/MWh

cautious case

181USD/MWh at 7%

100200300 USD/MWhVogtlenext AP1000 pairmature AP1000BarakahShin Korirange of runscautious case0%to check the sums3%5%7%10%
the program’s own capital, with its interest
9 USD/MWh
interest during the build
29 USD/MWh
building the unit, before interest
86 USD/MWh
spent fuel and property tax
5 USD/MWh
fuel
11 USD/MWh
operation
42 USD/MWh

The soft band is where four in five of the model’s runs fall when every uncertain input is drawn at random within its range, with the middle run dotted: a spread from the stated ranges, not a probability. The thin lines are published plants run through this model. At 0% the figures only check the sums.

The published plants, at the chosen cost of money
PlantCost before interestBuildLCOE at 7%, target operationLCOE at 7%, cautious operation
Vogtle as builtabout 15,000 USD/kW in 2024 dollars (MIT 2024)15,390 USD/kW125 months228 USD/MWh252 USD/MWh
The next AP1000 pair, published estimateMIT 2024: 8,300 to 10,400 USD/kW, 80 to 96 months9,590 USD/kW88 months143 USD/MWh166 USD/MWh
A mature AP1000, published estimateMIT 2024 and Idaho National Laboratory 2025: 4,600 to 4,750 USD/kW, 50 months4,820 USD/kW50 months84 USD/MWh107 USD/MWh
Barakah, as builtMIT 2018 restated figure, 2017 dollars; scope uncertain5,160 USD/kW100 months96 USD/MWh118 USD/MWh
Shin Kori 3 and 4, as builtIEA/NEA 2020, 2018 dollars; durations include policy halts3,040 USD/kW100 months72 USD/MWh94 USD/MWh

Each plant is its published capital cost and build time, spent evenly over the build, with this model’s operating cost: the target case’s beside the target case, the cautious case’s beside the cautious case. So within each pairing only capital and time differ.

The numbers in this drawing
Average unit LCOE and its parts by cost of money, target case, USD/MWh
Cost of moneyAverage unitRuns: one in ten belowRuns: middleRuns: one in ten aboveoperationfuelspent fuel and property taxbuilding the unit, before interestinterest during the buildthe program’s own capital, with its interest
0%, to check the sums52596571241031500
0.5%55626975241031700
1%58667279241032010
1.5%61707683241032211
2%64748187241032511
2.5%68798693241032821
3%72839198241033131
3.5%778996104241033541
4%8194102111241033851
4.5%86100109118241034261
5%91106115125241034672
5.5%97112122133241035082
6%1021191301412410354102
6.5%1081261381502410358112
7%1141331461592410362133
7.5%1201411541692410366153
8%1271491631782410370173
8.5%1341571721892410374203
9%1401651812002410378224
9.5%148174191211249382254
10%155182201223249386275
Comparison plants by cost of money, with the target case’s operating cost, USD/MWh
Cost of moneyVogtle as builtThe next AP1000 pairA mature AP1000BarakahShin Kori 3 and 4
0%6957474843
0.5%7560495045
1%8164515246
1.5%8969535447
2%9773555749
2.5%10679576050
3%11684606352
3.5%12790626654
4%13997657056
4.5%151103687358
5%165111717861
5.5%179118748263
6%195126778666
6.5%211134819169
7%228143849672
7.5%2461528810175
8%2651619210778
8.5%2851719511281
9%3061819911885
9.5%32819110312488
10%35120210713092
Average unit LCOE and its parts by cost of money, cautious case, USD/MWh
Cost of moneyAverage unitRuns: one in ten belowRuns: middleRuns: one in ten aboveoperationfuelspent fuel and property taxbuilding the unit, before interestinterest during the buildthe program’s own capital, with its interest
0%, to check the sums80596571411252001
0.5%84626975411252411
1%88667279411252711
1.5%93707683411253122
2%99748187411253532
2.5%104798693411253942
3%111839198411254463
3.5%1188996104411254983
4%125941021114112554104
4.5%1331001091184112559124
5%1421061151254112564155
5.5%1511121221334112569186
6%1611191301414212575217
6.5%1711261381504211580258
7%1811331461594211586299
7.5%19314115416942115913310
8%20414916317842115973811
8.5%217157172189421151034313
9%230165181200421151084914
9.5%243174191211421151145516
10%257182201223421151206118
Comparison plants by cost of money, with the cautious case’s operating cost, USD/MWh
Cost of moneyVogtle as builtThe next AP1000 pairA mature AP1000BarakahShin Kori 3 and 4
0%9179696965
0.5%9782707166
1%10386727467
1.5%11191747669
2%11995777970
2.5%129101798172
3%139106818574
3.5%150112848876
4%162119879278
4.5%174126909680
5%1881339310083
5.5%2031419610485
6%21814910010988
6.5%23515710311391
7%25216610711894
7.5%27017511012497
8%290185114129100
8.5%310195118135103
9%331205122141107
9.5%354215126147111
10%377226130153114

Unit by unit, at 7%

For the first unit the model gives 143 USD/MWh232 USD/MWh.

For the last it gives 109 USD/MWh174 USD/MWh.

unit 1
143 USD/MWh232 USD/MWh
unit 100
112 USD/MWh179 USD/MWh
unit 200
109 USD/MWh174 USD/MWh
average unit
114 USD/MWh181 USD/MWh
the fleet, from the order date
116 USD/MWh186 USD/MWh

The average counts each unit from its own first day of power and charges it an equal fee that repays the program’s capital: what the buyer of a plant pays. The fleet figure discounts the whole program to the day of the order.

Beside every LCOE

LCOE does not see time.

A ratio of discounted sums is the same for a fast and a slow fleet of equal plants. So the years from the order to unit 200 always stand beside it: 23.6 years42.2 years.

Against the same fleet at 12 vessels a year, the model has the cautious case finish 16.5 years later. On the way it makes 14,702 TWh less electricity.

How sure · sensitivity

The model gives 114 USD/MWh181 USD/MWh; this is what moves those numbers, and how far.

Every figure in this section is at a 7% cost of money, whatever the control says. Each case keeps the allocation of work it chose at that rate.

One input at a time

Vogtle cost before interest moves the target case most: the model gives 104–125 USD/MWh across its range. Shifts worked on site moves the cautious case most: the model gives 170–199 USD/MWh across its range.

One input is moved from the low end of its range to the high end while the rest stay put. The 8 widest are drawn; the rest are in the table.

← cheaper114 USD/MWh181 USD/MWhdearer →
  1. Shifts worked on siteJ

    1.0–2.0 shifts

    111125
    170199
  2. Vogtle cost before interestD

    13,850–16,930 USD/kW

    104125
    174194
  3. Staff, upkeep and capital spent during lifeT

    170–330 USD/kW a year

    112131
    163183
  4. Learning of site crews, per doublingT

    0–10%

    113121
    173192
  5. Hardware and materials, share of Vogtle’s costJ

    14–28%

    179196
  6. Engineering, licensing and home office, share of Vogtle’s costJ

    15–30%

    106123
    180192
  7. Contingency common to the whole programJ

    5–20%

    111120
    172186
  8. Removed as particular to Vogtle (L1)T

    1,590–3,256 USD/kW

    123
    169

DdocumentedVderivedJjudgedTtarget

Every input tried, with its range and both ends
One input at a time, target case: average unit LCOE in USD/MWh with one input at each end of its range
InputGradeLow endHigh endUnitLCOE at the low endLCOE at the high end
Vogtle cost before interestdocumented13,85016,930USD/kW104125
Staff, upkeep and capital spent during lifetarget170330USD/kW a year112131
Engineering, licensing and home office, share of Vogtle’s costjudged1530%123106
Shifts worked on sitejudged1.02.0shifts125111
Learning on vendor lines, per doublingtarget08%122112
Contingency common to the whole programjudged520%111120
Removed as particular to Vogtle (L1)target1,5903,256USD/kW123114
Learning of site crews, per doublingtarget010%121113
Owner’s cost, share of Vogtle’s costdocumented1016%118110
Owner’s cost: licensing, owner staff, training, spares, connectionjudged300900USD/kW113120
Fuelderived7.013.0USD/MWh111116
Spent fueldocumented13USD/MWh114116
Lowest hours, share of unit 1judged4070%114115
One input at a time, cautious case: average unit LCOE in USD/MWh with one input at each end of its range
InputGradeLow endHigh endUnitLCOE at the low endLCOE at the high end
Shifts worked on sitejudged1.02.0shifts199170
Staff, upkeep and capital spent during lifetarget170330USD/kW a year163183
Vogtle cost before interestdocumented13,85016,930USD/kW174194
Learning of site crews, per doublingtarget010%192173
Hardware and materials, share of Vogtle’s costjudged1428%179196
Contingency common to the whole programjudged520%172186
Removed as particular to Vogtle (L1)target1,5903,256USD/kW181169
Learning on vendor lines, per doublingtarget08%187175
Engineering, licensing and home office, share of Vogtle’s costjudged1530%192180
Contingency per unit, at the endjudged215%175185
Fuelderived7.013.0USD/MWh176182
Spent fueldocumented13USD/MWh180182
Lowest hours, share of unit 1judged4070%181182

Every input at once · a spread from the stated ranges, not a probability

The target case falls below nine runs in ten and theThe cautious case above nine runs in ten: the two cases are corners, not the middle.

The model is run many times with every uncertain input drawn at random within its range, one set of runs for both cases. Four runs in five fall between 133–159 USD/MWh.

the middle of the range146 USD/MWh

the middle of the range146 USD/MWh

the target case itself114 USD/MWh

the cautious case itself181 USD/MWh

110120130140150160170180 USD/MWh

The ranges had to be wide enough for the first unit’s cost to reach the published cost of the next AP1000 pair; they were, so none was widened. Along the bottom, USD/MWh; the heights show how many runs fall at each value and carry no scale.

The runs, counted
The runs, target case’s allocation: draws in each interval of average unit LCOE
From, USD/MWhDraws
1101
1120
1144
1163
11816
12033
12249
12585
127157
129208
131297
133434
135479
137556
139682
141778
143810
145780
147801
149696
151681
153564
155453
157374
159332
161204
163149
165131
16795
169148
The runs, cautious case’s allocation: draws in each interval of average unit LCOE
From, USD/MWhDraws
1101
1120
1144
1163
11816
12033
12249
12585
127157
129208
131297
133434
135479
137556
139682
141778
143810
145780
147801
149696
151681
153564
155453
157374
159332
161204
163149
165131
16795
169148

What would have to be true

The model reaches none of 60, 80 or 100 USD/MWh by moving any single input within its range.

Not reached even with these eight inputs at the favourable end of their ranges together (the model then gives 101 USD/MWh).

Not reached even with these eight inputs at the favourable end of their ranges together (the model then gives 112 USD/MWh).

The inputs tried, and their cautious values
What each input alone would have to be, target case
InputUnitCautious valueNeeded for 60 USD/MWhNeeded for 80 USD/MWhNeeded for 100 USD/MWh
Vogtle cost before interestUSD/kW15,390not reached at any valuenot reached at any valuenot reached at any value
Staff, upkeep and capital spent during lifeUSD/kW a year317not reached at any valuenot reached at any valuenot reached at any value
Engineering, licensing and home office, share of Vogtle’s cost%22not reached at any valuenot reached at any valuenot reached at any value
Shifts worked on siteshifts1.4not reached at any valuenot reached at any valuenot reached at any value
Learning on vendor lines, per doubling%3not reached at any valuenot reached at any valuenot reached at any value
Contingency common to the whole program%15not reached at any valuenot reached at any valuenot reached at any value
Removed as particular to Vogtle (L1)USD/kW1,590not reached at any valuenot reached at any valuenot reached at any value
Learning of site crews, per doubling%5not reached at any valuenot reached at any valuenot reached at any value
What each input alone would have to be, cautious case
InputUnitCautious valueNeeded for 60 USD/MWhNeeded for 80 USD/MWhNeeded for 100 USD/MWh
Shifts worked on siteshifts1.4not reached at any valuenot reached at any valuenot reached at any value
Staff, upkeep and capital spent during lifeUSD/kW a year317not reached at any valuenot reached at any valuenot reached at any value
Vogtle cost before interestUSD/kW15,390not reached at any valuenot reached at any valuenot reached at any value
Learning of site crews, per doubling%5not reached at any valuenot reached at any valuenot reached at any value
Hardware and materials, share of Vogtle’s cost%20not reached at any valuenot reached at any valuenot reached at any value
Contingency common to the whole program%15not reached at any valuenot reached at any valuenot reached at any value
Removed as particular to Vogtle (L1)USD/kW1,590not reached at any valuenot reached at any valuenot reached at any value
Learning on vendor lines, per doubling%3not reached at any valuenot reached at any valuenot reached at any value

What explains the gap between the two cases

In the model, operation explains 34% of the distance from the target case to the cautious one.

Site duration explains 24%.

target case114 USD/MWh

cautious case181 USD/MWh

Operation23 USD/MWh · 34%

Site duration16 USD/MWh · 24%

Contingency9 USD/MWh · 13%

Learning8 USD/MWh · 12%

  • Operation23 USD/MWh · 34%
  • Site duration16 USD/MWh · 24%
  • Contingency9 USD/MWh · 13%
  • Learning8 USD/MWh · 12%
  • Wages and everything else6 USD/MWh · 9%
  • Dedicated lines3 USD/MWh · 5%
  • Factory against site hours2 USD/MWh · 3%
  • Choice of allocation0 USD/MWh · 0%
  • Vessels a year0 USD/MWh · 0%

Found by switching the groups of inputs from their target to their cautious values in many different orders and averaging what each switch adds. A group can come out slightly negative.

Scenarios

No learning at all is the scenario that costs most: the model then gives 129 USD/MWh198 USD/MWh.

A stopped line moves the date far more than the cost: LCOE does not see time.

  1. The case as it stands

    23.6 years

    42.2 years

  2. Vessel line stopped for 6 months

    24.1 years

    42.7 years

  3. Vessel line stopped for 12 months

    24.6 years

    43.2 years

  4. Another line (steam generators, pumps, valves or controls) holds the pace to 9.0 vessels a year

    −1

    29.1 years

    +1

    53.2 years

  5. Eighty years of operation

    −1

    23.6 years

    −2

    42.2 years

  6. No learning at all

    +15

    24.2 years

    +17

    42.8 years

  7. Steel, forgings and wages 20% dearer in real terms

    23.7 years

    +13

    42.2 years

  8. Vendor lines cost half as much again

    +1

    23.6 years

    +1

    42.2 years

  9. Crane ships only: wide pieces shipped as sub pieces

    +1

    23.6 years

    +2

    42.2 years

  10. Line, factory and ships built for 6 a year, not 12

    −3

    42.2 years

Each scenario’s LCOE and years
Scenarios, target case
ScenarioLCOE, USD/MWhYears to unit 200
The case as it stands11423.6
Vessel line stopped for 6 months11424.1
Vessel line stopped for 12 months11424.6
Another line (steam generators, pumps, valves or controls) holds the pace to 9.0 vessels a year11329.1
Eighty years of operation11323.6
No learning at all12924.2
Steel, forgings and wages 20% dearer in real terms11423.7
Vendor lines cost half as much again11523.6
Crane ships only: wide pieces shipped as sub pieces11523.6
Scenarios, cautious case
ScenarioLCOE, USD/MWhYears to unit 200
The case as it stands18142.2
Vessel line stopped for 6 months18242.7
Vessel line stopped for 12 months18243.2
Another line (steam generators, pumps, valves or controls) holds the pace to 4.5 vessels a year18353.2
Eighty years of operation18042.2
No learning at all19842.8
Steel, forgings and wages 20% dearer in real terms19442.2
Vendor lines cost half as much again18342.2
Crane ships only: wide pieces shipped as sub pieces18442.2
Line, factory and ships built for 6 a year, not 1217842.2

The close

For the target case to hold, the vessel line has to reach 12 vessels a year, where the cautious case takes 6, and three things have to go its way: what it costs to run the plants, how long each site takes and how far the build runs over its plan; all of it under the model’s assumptions.

target case

114

cautious case

181

USD/MWh at 7%

23.6years

from the order to unit 200

USD/MWh at 7%

42.2years

from the order to unit 200