Method
How the numbers are made.
The problem the model solves, the definition of every headline number, how the answer was found and checked, and one unit’s cost of electricity worked by hand.
The problem
What is given, what is chosen, what results
Build 200 AP1000 units for the United States in the shortest time at the lowest levelized cost of electricity. The pace is given: one vessel line at Doosan, dedicated to the program, sets how many units a year can start. The model chooses where the rest of the work is done.
Given
200 sites, ready, on water, each 15 days by sea from Progreso. How many vessels a year the line makes. The cost of money. The case, target or cautious. Every input on the assumptions page. Westinghouse’s design, module list, lift order and build sequence, unchanged.
Chosen
By the solver: where each work package is done, how far it is finished there and in what piece size; the route of each vendor part, straight to the site or through Progreso; robot or manual for each family of tasks; which test halls are built; stations and shifts in each bay; ships; the design of land preparation. Then, by direct search: the site’s head start on the vessel, extra lead time for land preparation and the buffer of modules at the quay.
Results
Package durations, the site schedule and site months, the crews needed, each unit’s date of first power, spending and energy by month, hours and headcount by place, the use of each bay, cost per kW, LCOE, and the years to unit 200.
One allocation applies to all 200 units; early units differ only through readiness and learning. A vendor that can sell a complete assembly always does. Progreso assembles and tests: it does not roll plate, forge or cast. Each package has a movable share, the part of its hours that can physically leave the site; placing concrete, filling modules, the welds that join modules to each other and cable pulled between modules cannot.
The algebra
The same problem, in symbols
Sets
- u = 1 … 200
- units, in vessel order
- t
- months from the order
- p
- work packages, 50 of them
- f
- task families: plate module welding, rebar cages, pipe spools, cable and electrical, coating, inspection, fit up, concrete, testing; hoursp,f are a package’s hours by family
- b
- Progreso’s bays; each family is worked in one bay. Concrete cannot leave the site and sits in none
- h, k, c
- test halls, ship classes, site trades
Decisions
- xp
- where package p is done and how far it is finished before shipping: on site; at Progreso, bare; at Progreso, fitted out; at Progreso, fitted out and tested. How deeply a module is fitted out before it leaves is the central lesson of Vogtle, so it is a choice, not all or nothing
- gp
- pieces or complete: whether a Westinghouse module ships as sub pieces joined in an assembly building on site, as at Vogtle, or complete as one lift. Nothing larger than Westinghouse’s own lift pieces is allowed
- jp
- the route of the vendor’s part for package p: straight to the site, or through Progreso, where it is received, inspected, held and shipped on with the modules. Work done at Progreso always receives its parts there. The model weighs the detour’s freight and handling and the interest on a part that leaves its vendor earlier against defects caught before they reach the site and a late delivery holding the site up. The reactor vessel cannot leave its line earlier, so routed through Progreso it would reach the site later
- a
- the site’s head start: how many months earlier than strictly needed the site starts, so that work which does not wait for the vessel is further along or finished when it arrives. Tests and inspection records are split into a part that can be done before the vessel and a part that needs it. The model weighs earlier spending and more site months against a shorter wait after the vessel
- zf
- robot cell or manual station, for each family at Progreso
- yh
- whether test hall h is built; a package can be tested at Progreso only if its hall is
- stb, mb(t)
- stations in bay b, sized for the busiest month of the program; and shift stations in use in month t, at most 3 · stb
- vk
- ships of each class
- e, ℓ, q
- the design of land preparation (one standard pad everywhere, or a design for each site); extra months of lead; the buffer of finished modules at the quay
What follows from the decisions
dp = site hoursp(xp, gp)crewp × hours a month , never less than its fixed holds
sq ≥ sp + dp for every precedence p → q
The precedences include the links between chains and Westinghouse’s lift order, so the crane rule is a chain of precedences and not a choice. A package finished at Progreso can be set no earlier than its factory finish, plus loading, 15 days at sea and unloading.
D = Dpre + A , unit u reaches power at vessel dateu + A
The model gives a head start of 0 months and 0 months, target and cautious. From the vessel’s arrival to power it then takes 34 months and 50 months.
Dpre is the site work before the vessel is set, scheduled backward from the day the vessel arrives; A is the work after it. In the answer Dpre is 29 months and 44 months and A is 34 months and 50 months, target and cautious.
wc = r × dc ÷ 12 , sites open at once = r × D ÷ 12
Crews needed for trade c, which is on a site for dc months, are a result, not a choice; each crew works on 200 ÷ wc units, which is what its learning counts.
Cost of a package, one unit, before learning
costp = hardwarep · (1 − line savingp)
+ Σf hoursp,f · placef(xp, gp) · method(zf) · (1 + support(xp)) · wage(xp)
+ Δdefectsp(xp, y) · repair(xp) + shippingp(gp)
The hours are those left after the first ledger stage has removed what was particular to Vogtle, so no excess is removed twice. Site staff and general conditions are priced by the month, D, not by the hour: shortening the site is the main lever. Learning multiplies hours by family and by cumulative volume; contingency is applied after learning. Bays, robots, halls, ships and the pad design are program capital, added through st, z, y, v and e.
Objective
minimize average unit LCOE(ρ) subject to Σp site hoursp ≤ H
H, the site hours allowed for a unit, is swept in 10 steps from the value with all work on site down to the lowest reachable. The chosen point is the lowest site hours whose LCOE is within 1% of the lowest on the curve; ties go to fewer total hours, then to an earlier last unit. This puts “as little labor as possible, above all on site” into the choice and shows its cost.
Time
T200 = L + R + 199 × 12 ÷ r + A
In months. L is the time to the first unit’s parts and R the ramp, each the longest among the vessel line, every other dedicated line and Progreso’s own readiness; r is the number of vessels a year. L, R and r are given, so the allocation can shorten the program only through A. The problem is solved at 6, 12 and 24 vessels a year.
Constraints
r(t)12 · Σf in b Σp hoursp,f · [xp = Progreso] ≤ mb(t) · hours a shift station a month · 85%
- Bay capacity, above, for every month, with mb(t) ≤ 3 · stb. Idle stations cost money in the objective.
- Precedence and lift order; a package cannot be at Progreso if it must follow a site package.
- Size: each shipped piece within the ship class and the site crane; a ship class only where Progreso and every site quay can take it.
- Ships: vk ≥ voyages a month × the round trip, where voyages for a unit are the larger of tonnes over cargo capacity and deck area over deck.
- Balance: every dedicated vendor line delivers at r; buffers are sized against each line’s availability and carry a cost.
- Holds no labor can shorten: concrete curing, weld inspection, containment pressure and leak tests, cold hydro, hot functional test, inspection closure before fuel load.
- Land preparation: earlier means interest on idle prepared ground; later idles vessel, crane and crew.
LCOE
The definition, and the headline numbers
LCOE(ρ) = Σt Ct (1 + ρ)−tΣt Et (1 + ρ)−t
Monthly, costs and energy at mid month, 2025 dollars. ρ is the real cost of money before income tax, used both for interest during construction and for discounting, because interest during construction is what the money would have earned elsewhere over the same months. No debt and equity split, no income tax. Property tax is an operating cost.
Headline numbers
Average unit LCOE = Σu (unit u’s costs valued at its own first power: spending before that date carried forward at ρ, which is the interest during construction, and later costs discounted back) ÷ Σu (its energy discounted to the same date): a ratio of sums. Each unit carries a fee F for program capital, the same for every unit:
F = PV(program capital)Σu (1 + ρ)−tu
with tu the unit’s delivery date, so the fees exactly repay the capital at ρ. “Program capital” here includes the program’s monthly spending on engineering, management and quality. F splits into two parts that the page shows separately: the unit’s even share of what was spent (inside overnight cost) and the interest carried on it (program carry); a test checks F equals their sum and that the fees’ present value equals the program’s. Each part carries its dedicated line charge, set the same way over that line’s deliveries. Also shown for unit 1, 100 and 200. This is what the buyer of a plant pays.
Fleet LCOE: the whole program discounted to the order date (t = 0); program capital enters on its real dates, not as fees.
LCOE does not see time. A ratio of discounted sums is the same for a fast and a slow fleet of equal plants. So beside it always: years to unit 200, GW online by year, and the energy lost against the 12 a year case in GWh and in years, valued over a stated range of power prices.
Overnight cost, the cost before interest, counts program capital and the vendors’ dedicated lines at what was spent, divided evenly over the 200 units, with no interest. The interest carried on that capital until each unit is delivered is a separate line, program carry, shown beside interest during construction. All in cost adds both to overnight cost.
The cost of money is shown at 3, 5, 7 and 10%, and computed exactly at each of 21 half point steps; nothing is interpolated. At 0% the figures are a check of the arithmetic only.
The ledger
From Vogtle as built to the fleet average, stage by stage
Every difference between Vogtle’s cost before interest and the model’s sits in exactly one stage, so nothing is counted twice. The first stage is Vogtle itself: the packages are calibrated to its hours and cost, a check of arithmetic that leaves 6% and 1% of its cost unexplained, target and cautious. That remainder is carried into the model’s cost unchanged.
| Stage | What it is | target case, USD/kW | cautious case, USD/kW |
|---|---|---|---|
| L0 | Vogtle as built | 15,390 | 15,390 |
| L1 | Causes particular to Vogtle | −3,260 | −1,590 |
| One program | One design and one program for 200 units | −2,910 | −3,040 |
| L2 | Work moved to its place, net of the factory, ships and shipping | −1,390 | −1,720 |
| L3 | Robots and factory tests | −180 | −180 |
| L4 | Dedicated vendor lines | −310 | −100 |
| L5 | Learning, to the fleet average | −970 | −790 |
| + | Contingency | 990 | 2,310 |
| = | Siderian, fleet average | 7,360 | 10,280 |
Removals are negative. The stage “one design and one program” was added to the plan’s ledger: Vogtle paid for its own design, licence and management, and the fleet pays for these once.
How it is solved
The best allocation found, not a proved optimum
A mixed integer program chooses x, g, the routes jp, z, y, st, m, v, e and the start times, for one steady state unit valued at its own first power. It minimizes that unit’s package costs, its site costs by the month and its share of program capital, plus μ · D, under the cap H. Energy is the same for every allocation, so the lowest cost is the lowest LCOE. μ prices only the extra interest on what is already spent when the site takes a month more or less. Solved with the HiGHS solver to a gap of 0.
The full model then evaluates that answer exactly: schedule, cash flows, LCOE.
Learning factors and μ are updated from the exact evaluation, and the two steps repeat until the allocation stops changing, 20 rounds at most, from 2 starting points. It settled after 2 and 3 rounds, target and cautious. The site’s head start, the lead time and the quay buffer are then set by direct search on the exact model. Both new decisions are part of the same search: the routes inside the solver, the head start outside it.
For each case and each number of vessels a year the cap H is swept at 7%, which fixes the chosen point; the problem is then solved at each of the 21 rates. In the cautious headline Progreso, the ships and the vendor lines keep the size the target case gave them for 12 a year, and run at 6.
The answer is the best allocation found, not a proved global optimum, and the page says so. 4 checks back it: no single package moved to the other place lowers the exact LCOE; 4 coherent strategies evaluated exactly (all on site; as Vogtle was built; most to Progreso; everything complete) cost no less; a version with 12 packages solved by trying every case matches; and a table shows which choices flip when inputs move by 20%.
The allocation is solved again at every rate, and some packages change place as money gets dearer or cheaper: 65 and 88 differences from the answer at 7%, target and cautious, over all rates.
Where the allocation changes with the cost of money
- Containment bottom head: bare/complete at 0%, site+via at 7%
- Containment rings: tested/complete at 0%, tested/pieces at 7%
- Reactor vessel: site+via at 0%, site at 7%
- Steam generators: site+via at 0%, site at 7%
- Turbine generator: site+via at 0%, site at 7%
- Containment bottom head: bare/complete at 0.5%, site+via at 7%
- Containment rings: tested/complete at 0.5%, tested/pieces at 7%
- Reactor vessel: site+via at 0.5%, site at 7%
- Steam generators: site+via at 0.5%, site at 7%
- Turbine generator: site+via at 0.5%, site at 7%
- Containment bottom head: bare/complete at 1%, site+via at 7%
- Containment rings: tested/complete at 1%, tested/pieces at 7%
- Reactor vessel: site+via at 1%, site at 7%
- Steam generators: site+via at 1%, site at 7%
- Turbine generator: site+via at 1%, site at 7%
- Containment bottom head: bare/complete at 1.5%, site+via at 7%
- Containment rings: tested/complete at 1.5%, tested/pieces at 7%
- Reactor vessel: site+via at 1.5%, site at 7%
- Steam generators: site+via at 1.5%, site at 7%
- Turbine generator: site+via at 1.5%, site at 7%
- Containment bottom head: bare/complete at 2%, site+via at 7%
- Containment rings: tested/complete at 2%, tested/pieces at 7%
- Reactor vessel: site+via at 2%, site at 7%
- Steam generators: site+via at 2%, site at 7%
- Turbine generator: site+via at 2%, site at 7%
- Containment bottom head: bare/complete at 2.5%, site+via at 7%
- Containment rings: tested/complete at 2.5%, tested/pieces at 7%
- Reactor vessel: site+via at 2.5%, site at 7%
- Steam generators: site+via at 2.5%, site at 7%
- Turbine generator: site+via at 2.5%, site at 7%
- Containment bottom head: bare/complete at 3%, site+via at 7%
- Containment rings: tested/complete at 3%, tested/pieces at 7%
- Reactor vessel: site+via at 3%, site at 7%
- Turbine generator: site+via at 3%, site at 7%
- Containment bottom head: bare/complete at 3.5%, site+via at 7%
- Containment rings: tested/complete at 3.5%, tested/pieces at 7%
- Reactor vessel: site+via at 3.5%, site at 7%
- Turbine generator: site+via at 3.5%, site at 7%
- Containment bottom head: bare/complete at 4%, site+via at 7%
- Containment rings: tested/complete at 4%, tested/pieces at 7%
- Containment bottom head: bare/complete at 4.5%, site+via at 7%
- Reactor vessel: site+via at 4.5%, site at 7%
- Containment bottom head: bare/complete at 5%, site+via at 7%
- Reactor vessel: site+via at 5%, site at 7%
- Containment bottom head: bare/complete at 5.5%, site+via at 7%
- Containment bottom head: bare/complete at 6%, site+via at 7%
- Basemat rebar cages: site at 8.5%, bare/complete at 7%
- Containment bottom head: site at 8.5%, site+via at 7%
- Containment rings: bare/complete at 8.5%, tested/pieces at 7%
- Basemat rebar cages: site at 9%, bare/complete at 7%
- Containment bottom head: site at 9%, site+via at 7%
- Containment rings: bare/complete at 9%, tested/pieces at 7%
- Steam generators: site+via at 9%, site at 7%
- Coolant pumps: site at 9%, site+via at 7%
- Basemat rebar cages: site at 9.5%, bare/complete at 7%
- Containment bottom head: site at 9.5%, site+via at 7%
- Containment rings: bare/complete at 9.5%, tested/pieces at 7%
- Steam generators: site+via at 9.5%, site at 7%
- Coolant pumps: site at 9.5%, site+via at 7%
- Basemat rebar cages: site at 10%, bare/complete at 7%
- Containment bottom head: site at 10%, site+via at 7%
- Containment rings: bare/complete at 10%, tested/pieces at 7%
- Structural modules CA01, CA02 to CA05, CA20: fitted out/complete at 10%, tested/complete at 7%
- Steam generators: site+via at 10%, site at 7%
- Coolant pumps: site at 10%, site+via at 7%
- Basemat rebar cages: bare/complete at 0%, site at 7%
- Containment bottom head: bare/complete at 0%, site at 7%
- Containment rings: fitted out/complete at 0%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0%, fitted out/complete at 7%
- Reactor vessel: site+via at 0%, site at 7%
- Steam generators: site+via at 0%, site at 7%
- Coolant pumps: site+via at 0%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 0%, site at 7%
- Turbine generator: site+via at 0%, site at 7%
- Basemat rebar cages: bare/complete at 0.5%, site at 7%
- Containment bottom head: bare/complete at 0.5%, site at 7%
- Containment rings: fitted out/complete at 0.5%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 0.5%, fitted out/complete at 7%
- Reactor vessel: site+via at 0.5%, site at 7%
- Steam generators: site+via at 0.5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 0.5%, site at 7%
- Turbine generator: site+via at 0.5%, site at 7%
- Transformers: site+via at 0.5%, site at 7%
- Basemat rebar cages: bare/complete at 1%, site at 7%
- Containment bottom head: bare/pieces at 1%, site at 7%
- Containment rings: tested/complete at 1%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1%, fitted out/complete at 7%
- Reactor vessel: site+via at 1%, site at 7%
- Steam generators: site+via at 1%, site at 7%
- Coolant pumps: site+via at 1%, site at 7%
- Turbine generator: site+via at 1%, site at 7%
- Transformers: site+via at 1%, site at 7%
- Basemat rebar cages: bare/complete at 1.5%, site at 7%
- Containment bottom head: bare/pieces at 1.5%, site at 7%
- Containment rings: tested/complete at 1.5%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 1.5%, fitted out/complete at 7%
- Reactor vessel: site+via at 1.5%, site at 7%
- Steam generators: site+via at 1.5%, site at 7%
- Coolant pumps: site+via at 1.5%, site at 7%
- Transformers: site+via at 1.5%, site at 7%
- Basemat rebar cages: bare/complete at 2%, site at 7%
- Containment bottom head: bare/pieces at 2%, site at 7%
- Containment rings: tested/complete at 2%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2%, fitted out/complete at 7%
- Steam generators: site+via at 2%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 2%, site at 7%
- Transformers: site+via at 2%, site at 7%
- Basemat rebar cages: bare/complete at 2.5%, site at 7%
- Containment bottom head: bare/pieces at 2.5%, site at 7%
- Containment rings: tested/complete at 2.5%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 2.5%, fitted out/complete at 7%
- Reactor vessel: site+via at 2.5%, site at 7%
- Coolant pumps: site+via at 2.5%, site at 7%
- Transformers: site+via at 2.5%, site at 7%
- Basemat rebar cages: bare/complete at 3%, site at 7%
- Containment bottom head: bare/pieces at 3%, site at 7%
- Containment rings: tested/complete at 3%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3%, fitted out/complete at 7%
- Reactor vessel: site+via at 3%, site at 7%
- Coolant pumps: site+via at 3%, site at 7%
- Moisture separator reheaters: site+via at 3%, site at 7%
- Containment bottom head: bare/pieces at 3.5%, site at 7%
- Containment rings: fitted out/pieces at 3.5%, bare/complete at 7%
- Structural modules CA01, CA02 to CA05, CA20: tested/complete at 3.5%, fitted out/complete at 7%
- Reactor vessel: site+via at 3.5%, site at 7%
- Coolant pumps: site+via at 3.5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 3.5%, site at 7%
- Transformers: site+via at 3.5%, site at 7%
- Reactor vessel: site+via at 4%, site at 7%
- Coolant pumps: site+via at 4%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 4%, site at 7%
- Coolant pumps: site+via at 4.5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 4.5%, site at 7%
- Coolant pumps: site+via at 5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 5.5%, site at 7%
- Moisture separator reheaters: site+via at 5.5%, site at 7%
- Passive safety tanks and heat exchanger: tested/complete at 6%, site at 7%
- Moisture separator reheaters: site+via at 6%, site at 7%
- Coolant pumps: site+via at 6.5%, site at 7%
- Head package and control rod drives: site at 6.5%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 7.5%, tested/complete at 7%
- Head package and control rod drives: site at 7.5%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 8%, tested/complete at 7%
- Head package and control rod drives: site at 8%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 8.5%, tested/complete at 7%
- Head package and control rod drives: site at 8.5%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 9%, tested/complete at 7%
- Head package and control rod drives: site at 9%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 9.5%, tested/complete at 7%
- Head package and control rod drives: site at 9.5%, site+via at 7%
- Shield building roof and water tank: tested/pieces at 10%, tested/complete at 7%
- Head package and control rod drives: site at 10%, site+via at 7%
The two cases
Fixed in advance, shown with equal weight
Target: Siderian’s stated targets; the vessel line makes 12 a year. Cautious: every uncertain input at the unfavourable end of what the evidence supports; the same line, factory and ships, built for 12 a year, reach only 6. A deliberately pessimistic corner, not a central estimate.
The inputs were committed before the first full run. Both cases are published whatever they show. Between them sits one random draw: every judged and target input drawn within its range, triangular, centred between its target and cautious values, with inputs tied by three common factors (productivity everywhere; delay with cost; wages with productivity). Its band is a spread from the stated ranges, not a probability.
The sensitivities hold each case’s allocation at its answer for 7%, so no solve is repeated.
Departures from the plan
What changed after trial numbers were seen, and where the build differs
Before the inputs were frozen, 18 November 2026
While the calibration to Vogtle was being built, short trial runs showed three things, which were changed. They are recorded because they were made after trial numbers had been seen, and because they lowered the result.
- A cost line was missing. The first accounts left 15% of Vogtle’s cost unexplained in the target case, and 23% once the hardware share was corrected. The estimate to complete filed with the Georgia regulator shows what was missing: a constructor’s fee, its contingency, construction equipment and temporary works. A new input now carries these, 35% on each dollar of site labor and staff, judged, and it applies to Siderian’s site labor in the same way. Progreso has its own, 25%.
- Hardware share of Vogtle’s cost: 28% changed to 20%. The earlier figure came from a generic split and was too high against Georgia Power’s accounts.
- Engineering, licensing and home office share: 15% changed to 22%. Vogtle carried a first design and licence, and Toshiba paid 3.7 billion USD toward it.
Effect: the unexplained remainder fell to 6% and 1% of Vogtle’s cost, and the trial LCOE of the target case at 7% moved from about 131 USD/MWh to about 114 USD/MWh. No learning rate, ratio of factory to site hours, contingency, wage or operating input was changed after trial numbers were seen.
Where the build departs from the plan
- A ledger stage was added, one design and one program for 200 units; without it the ledger would not add up.
- The random draw is one draw for both cases, centred between the target and cautious values, with the vessel line built for 12 a year and reaching a drawn rate between 6 and 12.
- The solver’s answer is polished on the exact model: every single change of one package, one robot family, one test hall and the pad design is tried and taken if it lowers LCOE. The plan’s check became a step.
- The sweep of the site hours cap: in both cases LCOE falls all the way, so the chosen point is the lowest site hours.
- Spending is taken as even over each window (vendor hardware over the months before delivery, factory work over its months, site work over the site months), not as a bell curve, so that present values have a closed form and the second calculation reproduces them exactly.
- Stations in each bay are sized by the busiest month, and shifts fall afterwards; because early units need more hours than late ones, steady use of the stations is below what the plan hoped for. The page shows the figure as it is: 68% and 30%.
- The Westinghouse module list with all its weights was not public; the package table was built from public counts and the published weights of the large modules, and is graded judged.
- Not found, and so judged: time at each step of vessel making; hours worked by place at Vogtle; ship day rates; Korean and Japanese hours per kW; stated yearly output for most vendors. Each is marked on the assumptions page.
Checks
A second calculation, and published work the engine must reproduce
The second calculation. A separate script in Python takes the monthly cost and energy series the model writes out and recomputes every LCOE, and recomputes the worked example from its own typed inputs. The two must agree within 0.1 USD/MWh.
Against published work. The International Energy Agency’s 2020 figures for new nuclear in the United States (4,250 USD/kW, a load factor of 85%, 7 years to build, 60 years of life, with its own operating, fuel and decommissioning lines, in its own dollars) are run through the LCOE engine. It reproduces the published 43.9, 71.3 and 98.6 USD/MWh at 3, 7 and 10% within 3%. This tests the engine alone; it is never used to set an input.
Used as inputs: Vogtle (baseline hours, cost and causes), MIT’s studies (factory against site hours, and the size of causes), the Nuclear Energy Institute (operation). Used to bound a range: the published cost of the next AP1000 pair, in the width test of the random draw. Used only as checks: the comparison plants on the page, each its published capital cost and build time run through this model.
Tests of the model. LCOE equals the closed form annuity result for a simple case and rises with the cost of money. Hours at vendor, Progreso and site add to the total. Units online never exceed vessels delivered. The fees repay program capital exactly. No single package flip improves the exact LCOE.
One unit by hand
The average unit’s LCOE at 7%, from five numbers
Everything is per kW of net output and valued at the day of first power. Capital comes from the model; the operating years are added month by month at mid month, as in the definition.
target case
| Cost before interest (overnight cost)what the unit costs with no interest, program share included | 7,360 USD/kW |
| + interest during constructioneach payment carried at 7% from its date to first power; spent evenly over the 63 site months alone it would be 1,480 USD/kW: vendors and the factory are paid before the site opens | 1,550 USD/kW |
| + program carryinterest on Progreso, ships, design and vendor lines until this unit is delivered | 150 USD/kW |
| = capital at first power | 9,050 USD/kW |
| Energy in a full year8,766 hours × a capacity factor of 93%; lower in the first 2 years | 8.2 MWh per kW |
| Energy over 60 years, discountedundiscounted it is 488 MWh per kW; at 7% the later years count for little | 116.9 MWh per kW |
| Fixed operating cost, discountedstaff, upkeep and capital spent during life, fees and the payment into the decommissioning fund: 195 USD/kW a year | 2,840 USD/kW |
| Fuel, discounted10.7 USD/MWh; none for the first 18 months, because the first core is in capital | 1,140 USD/kW |
| Spent fuel and property tax, discounted2.7 USD/MWh | 320 USD/kW |
| (capital + operation) ÷ energy | 114.2 USD/MWh |
| The model’s average unit LCOEa ratio of sums over all 200 units, which share one operating block, so the hand figure matches it | 114 USD/MWh |
cautious case
| Cost before interest (overnight cost)what the unit costs with no interest, program share included | 10,280 USD/kW |
| + interest during constructioneach payment carried at 7% from its date to first power; spent evenly over the 94 site months alone it would be 3,280 USD/kW: vendors and the factory are paid before the site opens | 3,310 USD/kW |
| + program carryinterest on Progreso, ships, design and vendor lines until this unit is delivered | 620 USD/kW |
| = capital at first power | 14,210 USD/kW |
| Energy in a full year8,766 hours × a capacity factor of 92%; lower in the first 2 years | 8.1 MWh per kW |
| Energy over 60 years, discountedundiscounted it is 482 MWh per kW; at 7% the later years count for little | 115.4 MWh per kW |
| Fixed operating cost, discountedstaff, upkeep and capital spent during life, fees and the payment into the decommissioning fund: 330 USD/kW a year | 4,800 USD/kW |
| Fuel, discounted12.5 USD/MWh; none for the first 18 months, because the first core is in capital | 1,320 USD/kW |
| Spent fuel and property tax, discounted5.4 USD/MWh | 620 USD/kW |
| (capital + operation) ÷ energy | 181.5 USD/MWh |
| The model’s average unit LCOEa ratio of sums over all 200 units, which share one operating block, so the hand figure matches it | 181 USD/MWh |
Capital amounts are rounded to ten USD/kW as everywhere on the page; the division uses the unrounded figures.