Siderian

Assumptions

Every input, its range, where it comes from and how far to trust it.

119 inputs in 11 groups. Each has a value in the target case, a low and a high end, the value the cautious case uses, a source, the date it was read and a grade.

Grades

Four grades, by letter and color

Ddocumented13 inputs
An official filing, or two independent primary sources.
Vderived9 inputs
Arithmetic on documented values, shown.
Jjudged85 inputs
One source, a secondary source, an analogy from another industry, or the modeller’s estimate.
Ttarget12 inputs
What Siderian aims for, not shown anywhere yet. Each target also carries its cautious value.

One thing can move a range after the inputs were frozen: the width test of the random draw, which may only widen a range and so only make the cautious case worse.

Inputs

Plant

InputTargetLow to highCautiousUnitSource, date read

Net outputD

target1,117,000

range1,110,000–1,117,000

cautious1,117,000

kW

docs/research/04_cost_inputs.md item 1 (World Nuclear Association reactor database, Vogtle 3)read 2026-11-18

Operating lifeD80 years is run as a separate case

target60

range60–80

cautious60

years

docs/research/04_cost_inputs.md item 2read 2026-11-18

UnitsD

target200

range200–200

cautious200

units

the briefread 2026-11-18

Inputs

Vessel line and vessels a year

InputTargetLow to highCautiousUnitSource, date read

Vessels a year from the dedicated lineTevidence for one shop on one design: about 6

target12

range6–12

cautious6

a year

docs/research/01_vessel_line.md items 2, 18, 21; the founder chose 12read 2026-11-18

Months from the order to the first unit’s partsJlongest of the vessel line, the other dedicated lines and Progreso

target54

range54–66

cautious60

months

docs/research/01_vessel_line.md items 7, 23; docs/research/05_vendor_table.md (42 to 54 months lead)read 2026-11-18

Months of ramp to the full rateJ

target12

range12–24

cautious24

months

docs/research/01_vessel_line.md item 23read 2026-11-18

Share of time a station worksJ

target85

range75–90

cautious80

%

judgedread 2026-11-18

Capital of all dedicated vendor linesJrepaid by a charge on each unit over the deliveries

target11.5

range8.0–20.0

cautious16.0

billion USD

docs/research/05_vendor_table.md; judged from plant values: vessel and forging lines, steam generators, pumps, turbine, modulesread 2026-11-18

Months over which the vendor lines are builtJ

target48

range36–60

cautious54

months

docs/research/01_vessel_line.md item 23read 2026-11-18

Months before delivery over which vendor hardware is paidJ

target36

range24–48

cautious42

months

docs/research/01_vessel_line.md item 7read 2026-11-18

Inputs

Vogtle baseline

InputTargetLow to highCautiousUnitSource, date read

Vogtle cost before interestDknown to about plus or minus 10%

target15,390

range13,850–16,930

cautious15,390

USD/kW

docs/research/03_vogtle_record.md item 3 (MIT 2024: about 15,000 in 2024 dollars); docs/research/07_cost_capital.md item 1 (factor 1.026)read 2026-11-18

Vogtle, first concrete to commercial operationD

target125.0

range124.6–125.3

cautious125.0

months

docs/research/03_vogtle_record.md item 5read 2026-11-18

Removed as particular to Vogtle (L1)Ttarget removes each in full; cautious removes half and keeps COVID

target3,256

range1,590–3,256

cautious1,590

USD/kW

docs/research/03_vogtle_record.md item 13 (MIT 2024: design 1,000, licence process 1,600, contractor 500, COVID 73)read 2026-11-18

Months removed with those causesT

target57.0

range28.5–57.0

cautious28.5

months

docs/research/03_vogtle_record.md item 13 (19 + 28 + 10 months)read 2026-11-18

Direct craft hours per unit at the Vogtle siteJ

target24,984

range21,400–29,000

cautious24,984

thousand hours

docs/research/06_modules_quantities.md sections 4 and 8 (estimate to complete, share complete, cost index)read 2026-11-18

Site craft, all inV

target84.4

range75.0–100.0

cautious92.0

USD/h

docs/research/04_cost_inputs.md item 31 (47.97 + 17.49 per diem in 2017); docs/research/07_cost_capital.md item 1 (factor 1.289)read 2026-11-18

Field support hours per craft hour on siteD

target53

range33–53

cautious53

%

docs/research/03_vogtle_record.md item 9 (estimate to complete, 2017)read 2026-11-18

Field support, all inV

target64

range55–80

cautious70

USD/h

docs/research/06_modules_quantities.md section 7 (625 million USD for 12.589 million hours in 2017)read 2026-11-18

Staff every site needs whatever its craftJ

target120

range80–200

cautious160

people

judged; with the next input it reproduces Vogtle’s 0.46 staff hours per craft hourread 2026-11-18

Further staff per craft worker presentV

target35.6

range25.0–45.0

cautious35.6

%

docs/research/03_vogtle_record.md item 9read 2026-11-18

Site staff, all inV

target142

range120–165

cautious150

USD/h

docs/research/06_modules_quantities.md section 7 (about 110 USD an hour in 2017)read 2026-11-18

Site general conditions a monthJ

target3.5

range2.0–7.0

cautious5.0

million USD

docs/research/06_modules_quantities.md section 7 (heavy crane, 30 major cranes, concrete plant, temporary works); judgedread 2026-11-18

Hardware and materials, share of Vogtle’s costJ

target20

range14–28

cautious20

%

docs/research/03_vogtle_record.md item 29 (procurement 13.5% of the Georgia Power share, plus part of the original contract)read 2026-11-18

Construction equipment, tools, temporary works and contractor fee, per dollar of site labor and staffJ

target35

range20–50

cautious35

%

docs/research/06_modules_quantities.md section 7 (fee 240 million USD and contingency 12.2% in the estimate to complete; 30 major cranes); judgedread 2026-11-18

Utilities, consumables and tools at Progreso, per dollar of its laborJ

target25

range15–40

cautious35

%

judgedread 2026-11-18

Engineering, licensing and home office, share of Vogtle’s costJ

target22

range15–30

cautious22

%

docs/research/03_vogtle_record.md items 17, 27 to 29 (first of a kind design and licensing; Toshiba paid 3.68 billion USD toward it)read 2026-11-18

Owner’s cost, share of Vogtle’s costD

target13

range10–16

cautious13

%

docs/research/03_vogtle_record.md item 27 (12.57%)read 2026-11-18

Inputs

Places

InputTargetLow to highCautiousUnitSource, date read

Hours inside the plant for one shop hour, outfittingJan analogy from shipyards

target8

range4–8

cautious5

times

docs/research/04_cost_inputs.md item 32 (shipbuilding 1 : 3 : 8, quoted by MIT 2018)read 2026-11-18

Hours in an open yard for one shop hour, outfittingJ

target3.0

range1.8–3.0

cautious2.0

times

docs/research/04_cost_inputs.md item 32read 2026-11-18

Hours inside the plant for one shop hour, plate and rebarJ

target3.0

range1.7–3.0

cautious2.0

times

judged: the shop’s advantage is smaller for structureread 2026-11-18

Hours in an open yard for one shop hour, plate and rebarJ

target1.5

range1.2–1.5

cautious1.3

times

judgedread 2026-11-18

Progreso hours against a mature shop, steady stateJ

target115

range100–160

cautious140

%

judged: a new workforce in a new shopread 2026-11-18

Extra hours at Progreso on its first unitJ

target50

range30–120

cautious100

%

docs/research/03_vogtle_record.md item 15 (Lake Charles was a new shop); judgedread 2026-11-18

Units over which that extra fadesJ

target8

range5–20

cautious15

units

judgedread 2026-11-18

Progreso craft, all inJ

target12

range8–20

cautious18

USD/h

docs/research/07_cost_capital.md item 10 (8 to 13 loaded for a welder or fitter; nuclear premium added)read 2026-11-18

Support hours per craft hour at ProgresoJ

target30

range20–50

cautious45

%

judged: a factory needs less support than a siteread 2026-11-18

Progreso support and engineers, all inJ

target22

range15–35

cautious30

USD/h

docs/research/07_cost_capital.md item 10read 2026-11-18

Share of site hours that is rework, after L1J

target15

range5–25

cautious8

%

docs/research/03_vogtle_record.md items 10, 11 (hours 1.18 to 1.5 times plan; no published rework share)read 2026-11-18

Share of that rework avoided when fitted out and tested in the factoryT

target70

range40–85

cautious50

%

targetread 2026-11-18

Share avoided when fitted out but not testedT

target30

range10–45

cautious20

%

targetread 2026-11-18

Inputs

Robots, bays and test halls

InputTargetLow to highCautiousUnitSource, date read

Robot hours of people for one manual hourJ

target45

range35–80

cautious70

%

docs/research/07_cost_capital.md item 12 (arc on time 20 to 30% manual, 60 to 85% in a cell; one cell replaces 2 to 3 welders a shift; vendor sources)read 2026-11-18

One robot cell, installedJ

target0.9

range0.4–2.0

cautious1.5

million USD

docs/research/07_cost_capital.md item 12 (150 to 400 thousand USD a cell before integration)read 2026-11-18

Manual hours one cell replaces a month, per shiftJ

target450

range300–600

cautious350

hours

docs/research/07_cost_capital.md item 12read 2026-11-18

One manual station: floor, cranes, toolsJ

target2.5

range1.5–5.0

cautious4.0

million USD

docs/research/07_cost_capital.md item 11 (heavy hall per square metre; judged)read 2026-11-18

Hours one station gives a month, per shiftJ

target1,040

range870–1,200

cautious950

hours

six people at 173 hours a monthread 2026-11-18

Share of bay time that is productiveJ

target85

range75–90

cautious80

%

judgedread 2026-11-18

Progreso: land, dredging, quay, yard, utilitiesJ

target0.7

range0.4–1.5

cautious1.1

billion USD

docs/research/07_cost_capital.md item 11; docs/research/04_cost_inputs.md items 27, 28 (channel to 13.3 m; quay for 1,000 tonne pieces)read 2026-11-18

Months to build and qualify ProgresoJ

target34

range24–48

cautious44

months

docs/research/05_vendor_table.md (a first nuclear certificate took about 19 months; 18 to 36 judged)read 2026-11-18

Yearly upkeep, share of Progreso capitalJ

target4

range3–6

cautious5

%

judgedread 2026-11-18

Nuclear quality program at Progreso a yearJ

target25

range15–50

cautious40

million USD

judgedread 2026-11-18

Test hall: instrument and control on the simulatorJ

target140

range80–250

cautious200

million USD

judgedread 2026-11-18

Test hall: electrical cabinetsJ

target60

range30–120

cautious90

million USD

judgedread 2026-11-18

Test hall: pipe module pressure testJ

target45

range25–90

cautious70

million USD

judgedread 2026-11-18

Test hall: module to module fit checkJ

target80

range40–160

cautious120

million USD

judgedread 2026-11-18

Inputs

Shipping

InputTargetLow to highCautiousUnitSource, date read

Widest piece a crane ship carriesJ

target30

range25–32

cautious28

m

docs/research/06_modules_quantities.md section 6 (deck width not retrieved)read 2026-11-18

Heaviest piece a crane ship liftsD

target2,200

range1,800–2,200

cautious2,000

tonnes

docs/research/04_cost_inputs.md item 23 (BigLift Happy Star: 2 x 1,100 t)read 2026-11-18

Usable deck of a crane shipV

target2,450

range2,000–3,280

cautious2,200

m2

docs/research/06_modules_quantities.md section 6 (3,280 m2, 75% usable)read 2026-11-18

Cargo of a crane shipD

target16,000

range12,000–18,374

cautious14,000

tonnes

docs/research/06_modules_quantities.md section 6read 2026-11-18

Usable deck of a semi submersibleV

target4,300

range3,500–5,785

cautious3,900

m2

docs/research/06_modules_quantities.md section 6 (130 x 44.5 m, 75% usable)read 2026-11-18

Cargo of a semi submersibleD

target45,000

range35,000–54,000

cautious40,000

tonnes

docs/research/06_modules_quantities.md section 6read 2026-11-18

A crane shipJ

target80

range60–120

cautious100

million USD

docs/research/07_cost_capital.md item 13 (two newbuilds for about 156 million USD)read 2026-11-18

A semi submersible heavy transport shipJ

target240

range180–320

cautious280

million USD

docs/research/07_cost_capital.md item 13 (about 240 million USD, 2012, unverified)read 2026-11-18

Running a ship for a year, crew and upkeepJ

target9

range6–14

cautious12

million USD

docs/research/07_cost_capital.md item 13 (no published day rate; judged)read 2026-11-18

Fuel and port for one round tripJ

target1.2

range0.8–2.0

cautious1.6

million USD

judgedread 2026-11-18

Round trip: 30 days at sea, loading, unloading, weatherV

target43

range40–55

cautious50

days

the brief (15 days each way); loading and weather judgedread 2026-11-18

Sea fastening, preservation, inspection on arrival, damage allowanceJ

target350

range200–700

cautious550

USD/tonne

judgedread 2026-11-18

Semi submersible can call at Progreso and the sitesJ

targetyes

rangeno–yes

cautiousyes

docs/research/06_modules_quantities.md section 6 (needs about 12 m at the quay; channel being deepened to 13.3 m)read 2026-11-18

Unloading quay per site, standard designJ

target35

range20–60

cautious50

million USD

judgedread 2026-11-18

Inputs

Routing of vendor deliveries

InputTargetLow to highCautiousUnitSource, date read

Extra freight to Progreso and not to the site, from AsiaJ

target0

range−50–100

cautious60

USD/tonne

judged: Progreso and the US sites are about as far from Korea and Japanread 2026-11-18

Extra freight to Progreso and not to the site, from EuropeJ

target20

range−30–120

cautious80

USD/tonne

judgedread 2026-11-18

Extra freight to Progreso and not to the site, from the US and CanadaJ

target130

range60–300

cautious220

USD/tonne

judged: a US made part routed through Progreso makes a detourread 2026-11-18

Extra freight to Progreso and not to the site, from MexicoJ

target−140

range−250–0

cautious−60

USD/tonne

judged: Progreso is nearerread 2026-11-18

Hours at Progreso to receive, inspect and hold a delivery, per million USD of hardwareJ

target20

range10–60

cautious40

hours

judgedread 2026-11-18

Share of vendor hardware, by value, that arrives with a defectJ

target1.0

range0.3–3.0

cautious0.5

%

docs/research/03_vogtle_record.md items 15, 21 (wrong welds from the module shop; the pump redesign in China); no published rateread 2026-11-18

Share of those defects caught at ProgresoT

target60

range30–80

cautious40

%

targetread 2026-11-18

What a defect found on site costs beyond one found at Progreso, per dollar of the partJ

target2

range1–4

cautious1

times

judged: repair in place, and the waitread 2026-11-18

Months a vendor delivery may run lateJ

target0.3

range0.0–1.5

cautious1.0

months

judgedread 2026-11-18

Share of a late delivery that holds the site up, for parts not among the heavy liftsJ

target20

range5–50

cautious30

%

judgedread 2026-11-18

Months earlier a part leaves its vendor when routed through ProgresoJ

target1.5

range1.0–3.0

cautious2.5

months

the brief (15 days by sea) plus receiving and holding; for the reactor vessel, which cannot leave earlier, months later on siteread 2026-11-18

Inputs

Site

InputTargetLow to highCautiousUnitSource, date read

Shifts worked on siteJ

target1.6

range1.0–2.0

cautious1.4

shifts

docs/research/06_modules_quantities.md section 4 (2,700 of 4,500 craft on one shift)read 2026-11-18

All on site, after L1: first concrete to operationV

target68.0

range60.0–97.0

cautious96.5

months

Vogtle’s 125 months less the months removed in L1; the crew ceilings are scaled to give thisread 2026-11-18

Extra months for unit 1 (then 9, 6, 3)J

target12

range6–24

cautious18

months

judged schedule allowanceread 2026-11-18

Land preparation hours saved by one standard designT

target15

range5–25

cautious8

%

targetread 2026-11-18

Standard pad and quay design, onceJ

target150

range80–300

cautious250

million USD

judgedread 2026-11-18

Site specific design, each siteJ

target12

range6–25

cautious20

million USD

judgedread 2026-11-18

Moving the crews to the next site, per unitJ

target6

range3–12

cautious9

million USD

judged: travel, lodging, lost daysread 2026-11-18

Share of the test program that does not need the reactor vesselJ

target50

range20–70

cautious30

%

judged: component tests, flushing, electrical and secondary side tests run before the primary loop existsread 2026-11-18

Share of inspection records that can close before the vessel is setJ

target60

range20–80

cautious30

%

judged: records of buildings and systems already complete; the rest need the plant as builtread 2026-11-18

Months land preparation may run lateJ

target1

range0–6

cautious3

months

judgedread 2026-11-18

A delivered vessel and its crane and crews waiting a monthJ

target8

range5–15

cautious12

million USD

judged: interest on delivered hardware, idle crane and gangsread 2026-11-18

Months a shipment may run lateJ

target0.5

range0.0–2.0

cautious1.0

months

judged: weather and portread 2026-11-18

A site waiting a month for a moduleJ

target4

range2–8

cautious6

million USD

judgedread 2026-11-18

Heavy lift crane, a month on a siteJ

target0.9

range0.5–1.5

cautious1.2

million USD

docs/research/06_modules_quantities.md section 7 (the Vogtle derrick cost more than 50 million USD, single source)read 2026-11-18

Inputs

Learning

InputTargetLow to highCautiousUnitSource, date read

Learning at Progreso, per doublingTapplied to hours: an analogy

target10

range3–12

cautious5

%

docs/research/04_cost_inputs.md items 35, 36 (published nuclear rates are for cost: negative to 6%; NREL 8%)read 2026-11-18

Learning of site crews, per doublingT

target8

range0–10

cautious5

%

docs/research/04_cost_inputs.md items 35, 36; docs/research/03_vogtle_record.md item 6 (Vogtle 4 about 20% cheaper than Vogtle 3)read 2026-11-18

Learning on vendor lines, per doublingT

target6

range0–8

cautious3

%

docs/research/04_cost_inputs.md items 35, 36read 2026-11-18

Lowest hours, share of unit 1J

target45

range40–70

cautious60

%

judgedread 2026-11-18

Hardware saving from a dedicated line, at unit 1T

target15

range0–25

cautious5

%

the brief: dedicated lines are cheaper; size is a targetread 2026-11-18

Inputs

Program and other capital

InputTargetLow to highCautiousUnitSource, date read

Finishing the design and the program set up, onceJ

target2.5

range1.5–5.0

cautious4.0

billion USD

docs/research/03_vogtle_record.md item 13 (unfinished design cost Vogtle about 1,000 USD/kW)read 2026-11-18

Engineering, management and integration, a monthJ

target22

range12–45

cautious35

million USD

judgedread 2026-11-18

Owner’s cost: licensing, owner staff, training, spares, connectionJ

target420

range300–900

cautious700

USD/kW

docs/research/07_cost_capital.md item 14 (MIT counts about 1,000 USD/kW with site preparation and cooling, which this model prices in its own packages)read 2026-11-18

First fuel coreD

target328

range300–350

cautious340

USD/kW

docs/research/07_cost_capital.md item 14 (Idaho National Laboratory 2024: 320 USD/kW)read 2026-11-18

Contingency common to the whole programJan expected overrun on the plan; does not shrink with numbers

target10

range5–20

cautious15

%

docs/research/07_cost_capital.md item 6 (MIT uses 25%; mean overrun of nuclear projects about 120%)read 2026-11-18

Contingency per unit, at unit 1J

target20

range10–50

cautious30

%

docs/research/07_cost_capital.md item 6read 2026-11-18

Contingency per unit, at the endJ

target5

range2–15

cautious10

%

docs/research/07_cost_capital.md item 6read 2026-11-18

Contingency on program capitalJ

target30

range15–60

cautious40

%

docs/research/07_cost_capital.md item 6read 2026-11-18

Life of a shipJ

target25

range20–30

cautious25

years

judgedread 2026-11-18

Life of a robot cellJ

target12

range8–15

cautious10

years

judgedread 2026-11-18

Inputs

Operation

InputTargetLow to highCautiousUnitSource, date read

Capacity factorD

target93

range90–94

cautious92

%

docs/research/04_cost_inputs.md item 4 (US fleet 90.8 to 93.0% in 2021 to 2025)read 2026-11-18

Capacity factor, first yearJ

target80

range70–90

cautious78

%

docs/research/04_cost_inputs.md item 4 (Vogtle 3: 78% in its first full year)read 2026-11-18

Capacity factor, second yearJ

target88

range80–93

cautious85

%

judgedread 2026-11-18

Staff, upkeep and capital spent during lifeTtarget: one operator, 200 identical units; cautious: today’s single unit average

target191

range170–330

cautious317

USD/kW a year

docs/research/04_cost_inputs.md items 6, 7; docs/research/07_cost_capital.md items 2, 3 (NEI 2026: single unit plants 45.77 USD/MWh of which fuel 6.47; best quarter 28.87 of which fuel 5.13; converted at a 92% capacity factor)read 2026-11-18

FuelV

target10.7

range7.0–13.0

cautious12.5

USD/MWh

docs/research/04_cost_inputs.md items 10, 11 (uranium 99 USD/lb, conversion 53.5 USD/kg, enrichment 181 USD a unit, fabrication 300 USD/kg; 50 GWd/t at 33.5%), in 2025 dollarsread 2026-11-18

Spent fuelD

target1

range1–3

cautious2

USD/MWh

docs/research/04_cost_inputs.md item 12 (the statutory fee of 1 USD/MWh; docs/research/07_cost_capital.md item 15 for storage)read 2026-11-18

Property taxJ

target1.7

range1.2–3.4

cautious3.4

USD/MWh

docs/research/07_cost_capital.md item 9 (about 1.7 to 3.4 USD/MWh)read 2026-11-18

Insurance and NRC fees, if not already in the operating figureJ

target0.0

range0.0–6.3

cautious6.3

USD/kW a year

docs/research/04_cost_inputs.md item 14; docs/research/07_cost_capital.md items 2, 9 (NEI does not say where these sit)read 2026-11-18

DecommissioningJ

target500

range450–1,260

cautious800

USD/kW

docs/research/07_cost_capital.md item 9 (Vogtle about 551 million USD a unit; Vermont Yankee about 1,260 USD/kW)read 2026-11-18

Real return of the decommissioning fundJ

target2

range1–3

cautious2

%

judgedread 2026-11-18

Capital spend at year 60 in the 80 year caseJ

target800

range500–1,500

cautious1,200

USD/kW

judgedread 2026-11-18

Left out

Outside the stylized model, and what each would add

Not modelled, because the brief fixes it or sets it aside.

Licensing time for each site
Years before the first units, and a regulator’s finding before each fuel load beyond its fixed duration. Not modelled: the brief gives 200 sites as ready.
Modules larger than Westinghouse’s own
Could move more work off site, but would be a design change.
Adding people to shorten a package
Would shorten the site at a cost; crews are held at a ceiling.
Inland transport beyond the port
A cost and a size limit; the brief puts every site 15 days away by vessel.
Customs, tariffs and US content rules
A cost on everything shipped from Mexico, and possibly on tax credits.
US export control for nuclear technology in Mexico
An approval before Progreso can hold the design.
Mexican labor law and the supply of nuclear grade welders
Could slow the ramp of Progreso.
Taxes and subsidies
The model is before income tax and takes no tax credit.
Whether the grid can absorb 200 units
About 223 GW, in the order of two fifths of today’s US generation.
Uranium supply for 200 units
Only its price range is modelled.
The integrator failing
As Westinghouse did in 2017. Not modelled.

Vendors

Who makes what, what they ship, and what the program asks of them each year

PartVendor, placeSecond sourceShipsAsked each yearCapacity todayStatus
Reactor vesselcriticalDoosan EnerbilityChangwon, South KoreaBWXT Canada (agreement only)complete, tested, by sea12 vesselsabout 5 sets a year (World Nuclear Association, marked uncertain)verified
Large forgingscriticalJapan Steel WorksMuroran, JapanDoosan; Sheffield Forgemasters; Framatome Le Creusotforgings60 vessel forgings, plus steam generator, pressurizer and pump forgings12 vessel sets a year claimed; 4 documented to 2007verified
Steam generatorscriticalDoosan EnerbilityChangwon, South KoreaENSA, Spain (to verify); BWXT Canada (agreement)complete24no stated output found; 124 made in about 40 yearsverified
Coolant pumpscriticalone makerCurtiss-WrightCheswick, Pennsylvanianone qualifiedcomplete pump4812 to 16 a year (secondary source)verified
Internals, control rod drivescriticalWestinghouseNewington, New Hampshirenone foundcomplete12 setsno stated output foundverified
Head packagePremier TechnologyBlackfoot, Idahonone foundfitted at its maker12no stated output foundverified
Pressurizer, core makeup tankscriticalMangiarotti (Westinghouse)Monfalcone, ItalyDoosan; ENSA (candidates)complete12 and 24no stated output foundto verify
Squib valvescriticalone makerSPX Copes-VulcanMcKean, Pennsylvanianone foundcomplete valve12 setsno stated output foundverified
Containment vessel platesIHIYokohama, JapanPolish yards with Westinghouse ordersformed plates12 setsno stated output foundverified
Shield building panelsNewport News IndustrialNewport News, VirginiaPolish yards (to verify)panels12 sets of about 160no stated output foundverified
Structural sub modulesVigor (Oregon Iron Works) and othersPortland, OregonMostostal Kielce, Mostostal Kraków, EPG, FAMAK (Poland)sub modules12 setsno stated output foundverified
Mechanical modulesAeconCambridge, OntarioTurner Industries; CB&I Laurenstested modules12 setsno stated output foundverified
Turbine generatorcriticalToshibaYokohama, JapanMitsubishi Heavy Industries; Arabelle (EDF)complete12no stated output foundverified
CondenserBHI (Toshiba design)Haman, South KoreaDoosan Škoda (to verify)complete, in modules12no stated output foundverified
Protection and control, control roomcriticalWestinghouseCranberry, Pennsylvanianone foundcabinets, factory tested12 setsno stated output foundverified
SimulatorGSE SystemsColumbia, Marylandnone foundcomplete1 for the fleet, then updatesnot applicableverified
Safety pumps and valvesFlowserve and othersRaleigh, North CarolinaVelan, Canada (to verify)complete12 setsno stated output foundverified
Nuclear cableGeneral CableWillimantic, Connecticutnone foundreels12 setsno stated output foundverified
Fuel assembliesWestinghouseColumbia, South CarolinaVästerås, Swedencomplete assemblies12 first cores, then reloadsno stated output foundverified
EnrichmentUrenco USAEunice, New MexicoOrano (planned, Oak Ridge)enriched uraniumabout 2.4 million units a year at 200 unitsabout 5 million units a yearverified

Glossary

The terms used on the page, in plain words

LCOE
The levelized cost of electricity: every dollar spent over a plant’s life and every MWh it makes, each discounted at the cost of money, one sum divided by the other. Here in real dollars, before income tax.
Average unit LCOE
The headline number. Each unit is valued at its own first power and carries an equal fee that repays the program’s capital. It is what the buyer of a plant pays.
Fleet LCOE
The whole program discounted to the order date, with program capital on its real dates.
Cost of money
The real yearly rate, before income tax, used both to carry spending forward to first power and to discount what comes after. There is no split into debt and equity.
Cost before interest (overnight cost)
What a unit would cost if it were built overnight, with no interest. Here it counts program capital and the vendors’ dedicated lines at what was spent, an even share for every unit, as well as the first fuel core, the owner’s cost, contingency and the part of Vogtle’s cost the packages do not explain.
Interest during the build
What the money spent on a unit before its first power would have earned elsewhere over the same months, at the cost of money.
Interest on the program’s own capital (program carry)
The interest carried on program capital (Progreso, robots, ships, design, management, the vendors’ lines) from the day it was spent until each unit is delivered. Shown beside interest during the build, outside the cost before interest.
All in cost
Cost before interest plus interest during the build plus interest on the program’s own capital.
Vessels a year (cadence)
Vessels a year from the dedicated line. It sets the pace of the whole program: units online can never exceed vessels delivered.
Movable share
The part of a package’s hours that can physically leave the site. Placing concrete, filling modules, the welds that join modules to each other and cable pulled between modules cannot.
Fitted out
A module that leaves Progreso with its pipe, cable and equipment already in it. “Bare” leaves as structure only; “fitted out and tested” has also passed its tests in a factory hall.
Route
Where a vendor’s part goes when it leaves the vendor: straight to the site, or through Progreso, where it is received, inspected, held and shipped on with the modules. Work done at Progreso always receives its parts there.
Head start
How many months earlier than strictly needed a site starts, so that the work which does not wait for the reactor vessel is further along, or finished, when the vessel arrives.
Pieces or complete
Whether a Westinghouse module ships as sub pieces to be joined on site, as at Vogtle, or complete as one lift.
Target case
Siderian’s stated targets, with the vessel line at its design rate.
Cautious case
Every uncertain input at the unfavourable end of what the evidence supports, with the same line, factory and ships reaching half their design rate. A deliberately pessimistic corner, not a central estimate.
The draw
One random draw of all uncertain inputs within their ranges, for both cases. Its band is a spread from the stated ranges, not a probability.
Contingency
An expected overrun on the plan, not a reserve: a part common to the whole program, a part for each unit that falls with repetition, and a part on program capital.
Learning
Hours falling with repetition, by a fixed share for every doubling of volume, down to a floor. Applied to hours, never to materials.
Dedicated line
A vendor’s production line built for this program alone, repaid by a charge on each unit over its deliveries.
Ledger stages
The steps from Vogtle’s cost to the model’s, each difference in exactly one stage:
  • L0 Vogtle as built
  • L1 Causes particular to Vogtle
  • One program One design and one program for 200 units
  • L2 Work moved to its place, net of the factory, ships and shipping
  • L3 Robots and factory tests
  • L4 Dedicated vendor lines
  • L5 Learning, to the fleet average
Contingency is then added. The amounts are on the method page.

All money is in 2025 US dollars, real.