Assumptions
Every input, its range, where it comes from and how far to trust it.
119 inputs in 11 groups. Each has a value in the target case, a low and a high end, the value the cautious case uses, a source, the date it was read and a grade.
Grades
Four grades, by letter and color
- Ddocumented13 inputs
- An official filing, or two independent primary sources.
- Vderived9 inputs
- Arithmetic on documented values, shown.
- Jjudged85 inputs
- One source, a secondary source, an analogy from another industry, or the modeller’s estimate.
- Ttarget12 inputs
- What Siderian aims for, not shown anywhere yet. Each target also carries its cautious value.
One thing can move a range after the inputs were frozen: the width test of the random draw, which may only widen a range and so only make the cautious case worse.
Inputs
Plant
Net outputD
target1,117,000
range1,110,000–1,117,000
cautious1,117,000
kW
docs/research/04_cost_inputs.md item 1 (World Nuclear Association reactor database, Vogtle 3)read 2026-11-18
Operating lifeD80 years is run as a separate case
target60
range60–80
cautious60
years
docs/research/04_cost_inputs.md item 2read 2026-11-18
UnitsD
target200
range200–200
cautious200
units
the briefread 2026-11-18
Inputs
Vessel line and vessels a year
Vessels a year from the dedicated lineTevidence for one shop on one design: about 6
target12
range6–12
cautious6
a year
docs/research/01_vessel_line.md items 2, 18, 21; the founder chose 12read 2026-11-18
Months from the order to the first unit’s partsJlongest of the vessel line, the other dedicated lines and Progreso
target54
range54–66
cautious60
months
docs/research/01_vessel_line.md items 7, 23; docs/research/05_vendor_table.md (42 to 54 months lead)read 2026-11-18
Months of ramp to the full rateJ
target12
range12–24
cautious24
months
docs/research/01_vessel_line.md item 23read 2026-11-18
Share of time a station worksJ
target85
range75–90
cautious80
%
judgedread 2026-11-18
Capital of all dedicated vendor linesJrepaid by a charge on each unit over the deliveries
target11.5
range8.0–20.0
cautious16.0
billion USD
docs/research/05_vendor_table.md; judged from plant values: vessel and forging lines, steam generators, pumps, turbine, modulesread 2026-11-18
Months over which the vendor lines are builtJ
target48
range36–60
cautious54
months
docs/research/01_vessel_line.md item 23read 2026-11-18
Months before delivery over which vendor hardware is paidJ
target36
range24–48
cautious42
months
docs/research/01_vessel_line.md item 7read 2026-11-18
Inputs
Vogtle baseline
Vogtle cost before interestDknown to about plus or minus 10%
target15,390
range13,850–16,930
cautious15,390
USD/kW
docs/research/03_vogtle_record.md item 3 (MIT 2024: about 15,000 in 2024 dollars); docs/research/07_cost_capital.md item 1 (factor 1.026)read 2026-11-18
Vogtle, first concrete to commercial operationD
target125.0
range124.6–125.3
cautious125.0
months
docs/research/03_vogtle_record.md item 5read 2026-11-18
Removed as particular to Vogtle (L1)Ttarget removes each in full; cautious removes half and keeps COVID
target3,256
range1,590–3,256
cautious1,590
USD/kW
docs/research/03_vogtle_record.md item 13 (MIT 2024: design 1,000, licence process 1,600, contractor 500, COVID 73)read 2026-11-18
Months removed with those causesT
target57.0
range28.5–57.0
cautious28.5
months
docs/research/03_vogtle_record.md item 13 (19 + 28 + 10 months)read 2026-11-18
Direct craft hours per unit at the Vogtle siteJ
target24,984
range21,400–29,000
cautious24,984
thousand hours
docs/research/06_modules_quantities.md sections 4 and 8 (estimate to complete, share complete, cost index)read 2026-11-18
Site craft, all inV
target84.4
range75.0–100.0
cautious92.0
USD/h
docs/research/04_cost_inputs.md item 31 (47.97 + 17.49 per diem in 2017); docs/research/07_cost_capital.md item 1 (factor 1.289)read 2026-11-18
Field support hours per craft hour on siteD
target53
range33–53
cautious53
%
docs/research/03_vogtle_record.md item 9 (estimate to complete, 2017)read 2026-11-18
Field support, all inV
target64
range55–80
cautious70
USD/h
docs/research/06_modules_quantities.md section 7 (625 million USD for 12.589 million hours in 2017)read 2026-11-18
Staff every site needs whatever its craftJ
target120
range80–200
cautious160
people
judged; with the next input it reproduces Vogtle’s 0.46 staff hours per craft hourread 2026-11-18
Further staff per craft worker presentV
target35.6
range25.0–45.0
cautious35.6
%
docs/research/03_vogtle_record.md item 9read 2026-11-18
Site staff, all inV
target142
range120–165
cautious150
USD/h
docs/research/06_modules_quantities.md section 7 (about 110 USD an hour in 2017)read 2026-11-18
Site general conditions a monthJ
target3.5
range2.0–7.0
cautious5.0
million USD
docs/research/06_modules_quantities.md section 7 (heavy crane, 30 major cranes, concrete plant, temporary works); judgedread 2026-11-18
Hardware and materials, share of Vogtle’s costJ
target20
range14–28
cautious20
%
docs/research/03_vogtle_record.md item 29 (procurement 13.5% of the Georgia Power share, plus part of the original contract)read 2026-11-18
Construction equipment, tools, temporary works and contractor fee, per dollar of site labor and staffJ
target35
range20–50
cautious35
%
docs/research/06_modules_quantities.md section 7 (fee 240 million USD and contingency 12.2% in the estimate to complete; 30 major cranes); judgedread 2026-11-18
Utilities, consumables and tools at Progreso, per dollar of its laborJ
target25
range15–40
cautious35
%
judgedread 2026-11-18
Engineering, licensing and home office, share of Vogtle’s costJ
target22
range15–30
cautious22
%
docs/research/03_vogtle_record.md items 17, 27 to 29 (first of a kind design and licensing; Toshiba paid 3.68 billion USD toward it)read 2026-11-18
Owner’s cost, share of Vogtle’s costD
target13
range10–16
cautious13
%
docs/research/03_vogtle_record.md item 27 (12.57%)read 2026-11-18
Inputs
Places
Hours inside the plant for one shop hour, outfittingJan analogy from shipyards
target8
range4–8
cautious5
times
docs/research/04_cost_inputs.md item 32 (shipbuilding 1 : 3 : 8, quoted by MIT 2018)read 2026-11-18
Hours in an open yard for one shop hour, outfittingJ
target3.0
range1.8–3.0
cautious2.0
times
docs/research/04_cost_inputs.md item 32read 2026-11-18
Hours inside the plant for one shop hour, plate and rebarJ
target3.0
range1.7–3.0
cautious2.0
times
judged: the shop’s advantage is smaller for structureread 2026-11-18
Hours in an open yard for one shop hour, plate and rebarJ
target1.5
range1.2–1.5
cautious1.3
times
judgedread 2026-11-18
Progreso hours against a mature shop, steady stateJ
target115
range100–160
cautious140
%
judged: a new workforce in a new shopread 2026-11-18
Extra hours at Progreso on its first unitJ
target50
range30–120
cautious100
%
docs/research/03_vogtle_record.md item 15 (Lake Charles was a new shop); judgedread 2026-11-18
Units over which that extra fadesJ
target8
range5–20
cautious15
units
judgedread 2026-11-18
Progreso craft, all inJ
target12
range8–20
cautious18
USD/h
docs/research/07_cost_capital.md item 10 (8 to 13 loaded for a welder or fitter; nuclear premium added)read 2026-11-18
Support hours per craft hour at ProgresoJ
target30
range20–50
cautious45
%
judged: a factory needs less support than a siteread 2026-11-18
Progreso support and engineers, all inJ
target22
range15–35
cautious30
USD/h
docs/research/07_cost_capital.md item 10read 2026-11-18
Share of site hours that is rework, after L1J
target15
range5–25
cautious8
%
docs/research/03_vogtle_record.md items 10, 11 (hours 1.18 to 1.5 times plan; no published rework share)read 2026-11-18
Share of that rework avoided when fitted out and tested in the factoryT
target70
range40–85
cautious50
%
targetread 2026-11-18
Share avoided when fitted out but not testedT
target30
range10–45
cautious20
%
targetread 2026-11-18
Inputs
Robots, bays and test halls
Robot hours of people for one manual hourJ
target45
range35–80
cautious70
%
docs/research/07_cost_capital.md item 12 (arc on time 20 to 30% manual, 60 to 85% in a cell; one cell replaces 2 to 3 welders a shift; vendor sources)read 2026-11-18
One robot cell, installedJ
target0.9
range0.4–2.0
cautious1.5
million USD
docs/research/07_cost_capital.md item 12 (150 to 400 thousand USD a cell before integration)read 2026-11-18
Manual hours one cell replaces a month, per shiftJ
target450
range300–600
cautious350
hours
docs/research/07_cost_capital.md item 12read 2026-11-18
One manual station: floor, cranes, toolsJ
target2.5
range1.5–5.0
cautious4.0
million USD
docs/research/07_cost_capital.md item 11 (heavy hall per square metre; judged)read 2026-11-18
Hours one station gives a month, per shiftJ
target1,040
range870–1,200
cautious950
hours
six people at 173 hours a monthread 2026-11-18
Share of bay time that is productiveJ
target85
range75–90
cautious80
%
judgedread 2026-11-18
Progreso: land, dredging, quay, yard, utilitiesJ
target0.7
range0.4–1.5
cautious1.1
billion USD
docs/research/07_cost_capital.md item 11; docs/research/04_cost_inputs.md items 27, 28 (channel to 13.3 m; quay for 1,000 tonne pieces)read 2026-11-18
Months to build and qualify ProgresoJ
target34
range24–48
cautious44
months
docs/research/05_vendor_table.md (a first nuclear certificate took about 19 months; 18 to 36 judged)read 2026-11-18
Yearly upkeep, share of Progreso capitalJ
target4
range3–6
cautious5
%
judgedread 2026-11-18
Nuclear quality program at Progreso a yearJ
target25
range15–50
cautious40
million USD
judgedread 2026-11-18
Test hall: instrument and control on the simulatorJ
target140
range80–250
cautious200
million USD
judgedread 2026-11-18
Test hall: electrical cabinetsJ
target60
range30–120
cautious90
million USD
judgedread 2026-11-18
Test hall: pipe module pressure testJ
target45
range25–90
cautious70
million USD
judgedread 2026-11-18
Test hall: module to module fit checkJ
target80
range40–160
cautious120
million USD
judgedread 2026-11-18
Inputs
Shipping
Widest piece a crane ship carriesJ
target30
range25–32
cautious28
m
docs/research/06_modules_quantities.md section 6 (deck width not retrieved)read 2026-11-18
Heaviest piece a crane ship liftsD
target2,200
range1,800–2,200
cautious2,000
tonnes
docs/research/04_cost_inputs.md item 23 (BigLift Happy Star: 2 x 1,100 t)read 2026-11-18
Usable deck of a crane shipV
target2,450
range2,000–3,280
cautious2,200
m2
docs/research/06_modules_quantities.md section 6 (3,280 m2, 75% usable)read 2026-11-18
Cargo of a crane shipD
target16,000
range12,000–18,374
cautious14,000
tonnes
docs/research/06_modules_quantities.md section 6read 2026-11-18
Usable deck of a semi submersibleV
target4,300
range3,500–5,785
cautious3,900
m2
docs/research/06_modules_quantities.md section 6 (130 x 44.5 m, 75% usable)read 2026-11-18
Cargo of a semi submersibleD
target45,000
range35,000–54,000
cautious40,000
tonnes
docs/research/06_modules_quantities.md section 6read 2026-11-18
A crane shipJ
target80
range60–120
cautious100
million USD
docs/research/07_cost_capital.md item 13 (two newbuilds for about 156 million USD)read 2026-11-18
A semi submersible heavy transport shipJ
target240
range180–320
cautious280
million USD
docs/research/07_cost_capital.md item 13 (about 240 million USD, 2012, unverified)read 2026-11-18
Running a ship for a year, crew and upkeepJ
target9
range6–14
cautious12
million USD
docs/research/07_cost_capital.md item 13 (no published day rate; judged)read 2026-11-18
Fuel and port for one round tripJ
target1.2
range0.8–2.0
cautious1.6
million USD
judgedread 2026-11-18
Round trip: 30 days at sea, loading, unloading, weatherV
target43
range40–55
cautious50
days
the brief (15 days each way); loading and weather judgedread 2026-11-18
Sea fastening, preservation, inspection on arrival, damage allowanceJ
target350
range200–700
cautious550
USD/tonne
judgedread 2026-11-18
Semi submersible can call at Progreso and the sitesJ
targetyes
rangeno–yes
cautiousyes
docs/research/06_modules_quantities.md section 6 (needs about 12 m at the quay; channel being deepened to 13.3 m)read 2026-11-18
Unloading quay per site, standard designJ
target35
range20–60
cautious50
million USD
judgedread 2026-11-18
Inputs
Routing of vendor deliveries
Extra freight to Progreso and not to the site, from AsiaJ
target0
range−50–100
cautious60
USD/tonne
judged: Progreso and the US sites are about as far from Korea and Japanread 2026-11-18
Extra freight to Progreso and not to the site, from EuropeJ
target20
range−30–120
cautious80
USD/tonne
judgedread 2026-11-18
Extra freight to Progreso and not to the site, from the US and CanadaJ
target130
range60–300
cautious220
USD/tonne
judged: a US made part routed through Progreso makes a detourread 2026-11-18
Extra freight to Progreso and not to the site, from MexicoJ
target−140
range−250–0
cautious−60
USD/tonne
judged: Progreso is nearerread 2026-11-18
Hours at Progreso to receive, inspect and hold a delivery, per million USD of hardwareJ
target20
range10–60
cautious40
hours
judgedread 2026-11-18
Share of vendor hardware, by value, that arrives with a defectJ
target1.0
range0.3–3.0
cautious0.5
%
docs/research/03_vogtle_record.md items 15, 21 (wrong welds from the module shop; the pump redesign in China); no published rateread 2026-11-18
Share of those defects caught at ProgresoT
target60
range30–80
cautious40
%
targetread 2026-11-18
What a defect found on site costs beyond one found at Progreso, per dollar of the partJ
target2
range1–4
cautious1
times
judged: repair in place, and the waitread 2026-11-18
Months a vendor delivery may run lateJ
target0.3
range0.0–1.5
cautious1.0
months
judgedread 2026-11-18
Share of a late delivery that holds the site up, for parts not among the heavy liftsJ
target20
range5–50
cautious30
%
judgedread 2026-11-18
Months earlier a part leaves its vendor when routed through ProgresoJ
target1.5
range1.0–3.0
cautious2.5
months
the brief (15 days by sea) plus receiving and holding; for the reactor vessel, which cannot leave earlier, months later on siteread 2026-11-18
Inputs
Site
Shifts worked on siteJ
target1.6
range1.0–2.0
cautious1.4
shifts
docs/research/06_modules_quantities.md section 4 (2,700 of 4,500 craft on one shift)read 2026-11-18
All on site, after L1: first concrete to operationV
target68.0
range60.0–97.0
cautious96.5
months
Vogtle’s 125 months less the months removed in L1; the crew ceilings are scaled to give thisread 2026-11-18
Extra months for unit 1 (then 9, 6, 3)J
target12
range6–24
cautious18
months
judged schedule allowanceread 2026-11-18
Land preparation hours saved by one standard designT
target15
range5–25
cautious8
%
targetread 2026-11-18
Standard pad and quay design, onceJ
target150
range80–300
cautious250
million USD
judgedread 2026-11-18
Site specific design, each siteJ
target12
range6–25
cautious20
million USD
judgedread 2026-11-18
Moving the crews to the next site, per unitJ
target6
range3–12
cautious9
million USD
judged: travel, lodging, lost daysread 2026-11-18
Share of the test program that does not need the reactor vesselJ
target50
range20–70
cautious30
%
judged: component tests, flushing, electrical and secondary side tests run before the primary loop existsread 2026-11-18
Share of inspection records that can close before the vessel is setJ
target60
range20–80
cautious30
%
judged: records of buildings and systems already complete; the rest need the plant as builtread 2026-11-18
Months land preparation may run lateJ
target1
range0–6
cautious3
months
judgedread 2026-11-18
A delivered vessel and its crane and crews waiting a monthJ
target8
range5–15
cautious12
million USD
judged: interest on delivered hardware, idle crane and gangsread 2026-11-18
Months a shipment may run lateJ
target0.5
range0.0–2.0
cautious1.0
months
judged: weather and portread 2026-11-18
A site waiting a month for a moduleJ
target4
range2–8
cautious6
million USD
judgedread 2026-11-18
Heavy lift crane, a month on a siteJ
target0.9
range0.5–1.5
cautious1.2
million USD
docs/research/06_modules_quantities.md section 7 (the Vogtle derrick cost more than 50 million USD, single source)read 2026-11-18
Inputs
Learning
Learning at Progreso, per doublingTapplied to hours: an analogy
target10
range3–12
cautious5
%
docs/research/04_cost_inputs.md items 35, 36 (published nuclear rates are for cost: negative to 6%; NREL 8%)read 2026-11-18
Learning of site crews, per doublingT
target8
range0–10
cautious5
%
docs/research/04_cost_inputs.md items 35, 36; docs/research/03_vogtle_record.md item 6 (Vogtle 4 about 20% cheaper than Vogtle 3)read 2026-11-18
Learning on vendor lines, per doublingT
target6
range0–8
cautious3
%
docs/research/04_cost_inputs.md items 35, 36read 2026-11-18
Lowest hours, share of unit 1J
target45
range40–70
cautious60
%
judgedread 2026-11-18
Hardware saving from a dedicated line, at unit 1T
target15
range0–25
cautious5
%
the brief: dedicated lines are cheaper; size is a targetread 2026-11-18
Inputs
Program and other capital
Finishing the design and the program set up, onceJ
target2.5
range1.5–5.0
cautious4.0
billion USD
docs/research/03_vogtle_record.md item 13 (unfinished design cost Vogtle about 1,000 USD/kW)read 2026-11-18
Engineering, management and integration, a monthJ
target22
range12–45
cautious35
million USD
judgedread 2026-11-18
Owner’s cost: licensing, owner staff, training, spares, connectionJ
target420
range300–900
cautious700
USD/kW
docs/research/07_cost_capital.md item 14 (MIT counts about 1,000 USD/kW with site preparation and cooling, which this model prices in its own packages)read 2026-11-18
First fuel coreD
target328
range300–350
cautious340
USD/kW
docs/research/07_cost_capital.md item 14 (Idaho National Laboratory 2024: 320 USD/kW)read 2026-11-18
Contingency common to the whole programJan expected overrun on the plan; does not shrink with numbers
target10
range5–20
cautious15
%
docs/research/07_cost_capital.md item 6 (MIT uses 25%; mean overrun of nuclear projects about 120%)read 2026-11-18
Contingency per unit, at unit 1J
target20
range10–50
cautious30
%
docs/research/07_cost_capital.md item 6read 2026-11-18
Contingency per unit, at the endJ
target5
range2–15
cautious10
%
docs/research/07_cost_capital.md item 6read 2026-11-18
Contingency on program capitalJ
target30
range15–60
cautious40
%
docs/research/07_cost_capital.md item 6read 2026-11-18
Life of a shipJ
target25
range20–30
cautious25
years
judgedread 2026-11-18
Life of a robot cellJ
target12
range8–15
cautious10
years
judgedread 2026-11-18
Inputs
Operation
Capacity factorD
target93
range90–94
cautious92
%
docs/research/04_cost_inputs.md item 4 (US fleet 90.8 to 93.0% in 2021 to 2025)read 2026-11-18
Capacity factor, first yearJ
target80
range70–90
cautious78
%
docs/research/04_cost_inputs.md item 4 (Vogtle 3: 78% in its first full year)read 2026-11-18
Capacity factor, second yearJ
target88
range80–93
cautious85
%
judgedread 2026-11-18
Staff, upkeep and capital spent during lifeTtarget: one operator, 200 identical units; cautious: today’s single unit average
target191
range170–330
cautious317
USD/kW a year
docs/research/04_cost_inputs.md items 6, 7; docs/research/07_cost_capital.md items 2, 3 (NEI 2026: single unit plants 45.77 USD/MWh of which fuel 6.47; best quarter 28.87 of which fuel 5.13; converted at a 92% capacity factor)read 2026-11-18
FuelV
target10.7
range7.0–13.0
cautious12.5
USD/MWh
docs/research/04_cost_inputs.md items 10, 11 (uranium 99 USD/lb, conversion 53.5 USD/kg, enrichment 181 USD a unit, fabrication 300 USD/kg; 50 GWd/t at 33.5%), in 2025 dollarsread 2026-11-18
Spent fuelD
target1
range1–3
cautious2
USD/MWh
docs/research/04_cost_inputs.md item 12 (the statutory fee of 1 USD/MWh; docs/research/07_cost_capital.md item 15 for storage)read 2026-11-18
Property taxJ
target1.7
range1.2–3.4
cautious3.4
USD/MWh
docs/research/07_cost_capital.md item 9 (about 1.7 to 3.4 USD/MWh)read 2026-11-18
Insurance and NRC fees, if not already in the operating figureJ
target0.0
range0.0–6.3
cautious6.3
USD/kW a year
docs/research/04_cost_inputs.md item 14; docs/research/07_cost_capital.md items 2, 9 (NEI does not say where these sit)read 2026-11-18
DecommissioningJ
target500
range450–1,260
cautious800
USD/kW
docs/research/07_cost_capital.md item 9 (Vogtle about 551 million USD a unit; Vermont Yankee about 1,260 USD/kW)read 2026-11-18
Real return of the decommissioning fundJ
target2
range1–3
cautious2
%
judgedread 2026-11-18
Capital spend at year 60 in the 80 year caseJ
target800
range500–1,500
cautious1,200
USD/kW
judgedread 2026-11-18
Left out
Outside the stylized model, and what each would add
Not modelled, because the brief fixes it or sets it aside.
- Licensing time for each site
- Years before the first units, and a regulator’s finding before each fuel load beyond its fixed duration. Not modelled: the brief gives 200 sites as ready.
- Modules larger than Westinghouse’s own
- Could move more work off site, but would be a design change.
- Adding people to shorten a package
- Would shorten the site at a cost; crews are held at a ceiling.
- Inland transport beyond the port
- A cost and a size limit; the brief puts every site 15 days away by vessel.
- Customs, tariffs and US content rules
- A cost on everything shipped from Mexico, and possibly on tax credits.
- US export control for nuclear technology in Mexico
- An approval before Progreso can hold the design.
- Mexican labor law and the supply of nuclear grade welders
- Could slow the ramp of Progreso.
- Taxes and subsidies
- The model is before income tax and takes no tax credit.
- Whether the grid can absorb 200 units
- About 223 GW, in the order of two fifths of today’s US generation.
- Uranium supply for 200 units
- Only its price range is modelled.
- The integrator failing
- As Westinghouse did in 2017. Not modelled.
Vendors
Who makes what, what they ship, and what the program asks of them each year
| Part | Vendor, place | Second source | Ships | Asked each year | Capacity today | Status |
|---|---|---|---|---|---|---|
| Reactor vesselcritical | Doosan EnerbilityChangwon, South Korea | BWXT Canada (agreement only) | complete, tested, by sea | 12 vessels | about 5 sets a year (World Nuclear Association, marked uncertain) | verified |
| Large forgingscritical | Japan Steel WorksMuroran, Japan | Doosan; Sheffield Forgemasters; Framatome Le Creusot | forgings | 60 vessel forgings, plus steam generator, pressurizer and pump forgings | 12 vessel sets a year claimed; 4 documented to 2007 | verified |
| Steam generatorscritical | Doosan EnerbilityChangwon, South Korea | ENSA, Spain (to verify); BWXT Canada (agreement) | complete | 24 | no stated output found; 124 made in about 40 years | verified |
| Coolant pumpscriticalone maker | Curtiss-WrightCheswick, Pennsylvania | none qualified | complete pump | 48 | 12 to 16 a year (secondary source) | verified |
| Internals, control rod drivescritical | WestinghouseNewington, New Hampshire | none found | complete | 12 sets | no stated output found | verified |
| Head package | Premier TechnologyBlackfoot, Idaho | none found | fitted at its maker | 12 | no stated output found | verified |
| Pressurizer, core makeup tankscritical | Mangiarotti (Westinghouse)Monfalcone, Italy | Doosan; ENSA (candidates) | complete | 12 and 24 | no stated output found | to verify |
| Squib valvescriticalone maker | SPX Copes-VulcanMcKean, Pennsylvania | none found | complete valve | 12 sets | no stated output found | verified |
| Containment vessel plates | IHIYokohama, Japan | Polish yards with Westinghouse orders | formed plates | 12 sets | no stated output found | verified |
| Shield building panels | Newport News IndustrialNewport News, Virginia | Polish yards (to verify) | panels | 12 sets of about 160 | no stated output found | verified |
| Structural sub modules | Vigor (Oregon Iron Works) and othersPortland, Oregon | Mostostal Kielce, Mostostal Kraków, EPG, FAMAK (Poland) | sub modules | 12 sets | no stated output found | verified |
| Mechanical modules | AeconCambridge, Ontario | Turner Industries; CB&I Laurens | tested modules | 12 sets | no stated output found | verified |
| Turbine generatorcritical | ToshibaYokohama, Japan | Mitsubishi Heavy Industries; Arabelle (EDF) | complete | 12 | no stated output found | verified |
| Condenser | BHI (Toshiba design)Haman, South Korea | Doosan Škoda (to verify) | complete, in modules | 12 | no stated output found | verified |
| Protection and control, control roomcritical | WestinghouseCranberry, Pennsylvania | none found | cabinets, factory tested | 12 sets | no stated output found | verified |
| Simulator | GSE SystemsColumbia, Maryland | none found | complete | 1 for the fleet, then updates | not applicable | verified |
| Safety pumps and valves | Flowserve and othersRaleigh, North Carolina | Velan, Canada (to verify) | complete | 12 sets | no stated output found | verified |
| Nuclear cable | General CableWillimantic, Connecticut | none found | reels | 12 sets | no stated output found | verified |
| Fuel assemblies | WestinghouseColumbia, South Carolina | Västerås, Sweden | complete assemblies | 12 first cores, then reloads | no stated output found | verified |
| Enrichment | Urenco USAEunice, New Mexico | Orano (planned, Oak Ridge) | enriched uranium | about 2.4 million units a year at 200 units | about 5 million units a year | verified |
Glossary
The terms used on the page, in plain words
- LCOE
- The levelized cost of electricity: every dollar spent over a plant’s life and every MWh it makes, each discounted at the cost of money, one sum divided by the other. Here in real dollars, before income tax.
- Average unit LCOE
- The headline number. Each unit is valued at its own first power and carries an equal fee that repays the program’s capital. It is what the buyer of a plant pays.
- Fleet LCOE
- The whole program discounted to the order date, with program capital on its real dates.
- Cost of money
- The real yearly rate, before income tax, used both to carry spending forward to first power and to discount what comes after. There is no split into debt and equity.
- Cost before interest (overnight cost)
- What a unit would cost if it were built overnight, with no interest. Here it counts program capital and the vendors’ dedicated lines at what was spent, an even share for every unit, as well as the first fuel core, the owner’s cost, contingency and the part of Vogtle’s cost the packages do not explain.
- Interest during the build
- What the money spent on a unit before its first power would have earned elsewhere over the same months, at the cost of money.
- Interest on the program’s own capital (program carry)
- The interest carried on program capital (Progreso, robots, ships, design, management, the vendors’ lines) from the day it was spent until each unit is delivered. Shown beside interest during the build, outside the cost before interest.
- All in cost
- Cost before interest plus interest during the build plus interest on the program’s own capital.
- Vessels a year (cadence)
- Vessels a year from the dedicated line. It sets the pace of the whole program: units online can never exceed vessels delivered.
- Movable share
- The part of a package’s hours that can physically leave the site. Placing concrete, filling modules, the welds that join modules to each other and cable pulled between modules cannot.
- Fitted out
- A module that leaves Progreso with its pipe, cable and equipment already in it. “Bare” leaves as structure only; “fitted out and tested” has also passed its tests in a factory hall.
- Route
- Where a vendor’s part goes when it leaves the vendor: straight to the site, or through Progreso, where it is received, inspected, held and shipped on with the modules. Work done at Progreso always receives its parts there.
- Head start
- How many months earlier than strictly needed a site starts, so that the work which does not wait for the reactor vessel is further along, or finished, when the vessel arrives.
- Pieces or complete
- Whether a Westinghouse module ships as sub pieces to be joined on site, as at Vogtle, or complete as one lift.
- Target case
- Siderian’s stated targets, with the vessel line at its design rate.
- Cautious case
- Every uncertain input at the unfavourable end of what the evidence supports, with the same line, factory and ships reaching half their design rate. A deliberately pessimistic corner, not a central estimate.
- The draw
- One random draw of all uncertain inputs within their ranges, for both cases. Its band is a spread from the stated ranges, not a probability.
- Contingency
- An expected overrun on the plan, not a reserve: a part common to the whole program, a part for each unit that falls with repetition, and a part on program capital.
- Learning
- Hours falling with repetition, by a fixed share for every doubling of volume, down to a floor. Applied to hours, never to materials.
- Dedicated line
- A vendor’s production line built for this program alone, repaid by a charge on each unit over its deliveries.
- Ledger stages
- The steps from Vogtle’s cost to the model’s, each difference in exactly one stage:
- L0 Vogtle as built
- L1 Causes particular to Vogtle
- One program One design and one program for 200 units
- L2 Work moved to its place, net of the factory, ships and shipping
- L3 Robots and factory tests
- L4 Dedicated vendor lines
- L5 Learning, to the fleet average
All money is in 2025 US dollars, real.